Marina Yacht Harbor Renovation Projects
The San Francisco Marina is composed of two harbors, known as East Harbor (Gashouse Cove) and West Harbor. The East Harbor consists of 342 boat slips, the City Yachts sales, and fuel concession, and parkland, which includes a restroom and two parking lots. The Marina Green, a part of the marina and a major city park, is situated between the East and West Harbors.
The San Francisco Marina facilities have existed in their present configuration since 1963. The floating docks and gangways are made of timber and have degraded over time. The on-dock utilities have degraded as well as become obsolete.
Harbor Renovation Program
The San Francisco Marina Renovation Project includes waterside improvements over the entire 39-acre waterside portion of the marina and on 12 of the total 19 landslide acres. Phase I of the project, renovation of the West Harbor, is complete and open. Phase 2 of the project, renovation of the East Harbor, is in progress.
Renovations
East Marina renovations shall include:
- Landscaping, site and public access improvements
- Maintenance dredging
- One new wave attenuation structure (contingent upon funding)
- Reconstruction of portions of the degraded riprap slopes around the interior shorelines
- Repairs to the existing sheet-pile breakwater
- Replacement and reconfiguration of the floating docks and slips
Timeline
Phase II: East Harbor Renovation
If you would like to sign up for updates click here and scroll down to the NewsFlash and select the alerts you would like to receive.
Season | Renovation Plan |
---|---|
Winter to Spring 2015 | Site investigation, including sediment sampling and analysis will be performed. |
Summer 2015 | Consulting engineers selected for East Harbor Renovation project will be hired. |
Fall 2015 | Development of project plans, and specifications, including harbor plans, coastal engineering, environmental, and geotechnical elements. |
2016 | Development of Contracting Documents and securing of required Permits. |
Spring 2019 | Bidding and pre-construction activities. |
TBD | Project construction delivered in phases over the course of one to two years. |
San Francisco Marina East Harbor Renovation
- Addendum Number 1: Revised Appendix C (July 31, 2015) (PDF)
- Addendum Number 2 Revisions to Section 12 (August 5, 2015) (PDF)
- Addendum Number 3: Revisions to Section 7 (August 17, 2015) (PDF)
- Environmental Impact Report (PDF), San Francisco Marina Renovation Program (January 2007)
- New! Request for Proposals (PDF): Design Services for the San Francisco Marina East Harbor Renovation (July 2015)
- Pre-Proposal Conference Sign-In Sheet (August 5, 2015) (PDF)
- San Francisco MYH Renovation Conceptual Plan (PDF)
- Staff Report August 5, 2015 (PDF)
- Staff Report August 5, 2015 (PDF)
- Monthly Capital Report
-
Charlene Angsuco
Project ManagerPhone: 1-628-652-6642