Golden Gate Park - Stow Lake Perimeter Path Renovation
Background
Stow Lake is popular destination in Golden Gate Park for strolling, boating and picnicking. The existing asphalt path that circles the perimeter of the lake has deteriorated and is in need of repair. The project’s design will keep the perimeter path in its current alignment to minimize impact on the overall site and the landscaping. Additionally, the site furnishings will be refurbished.
Scope of Work
The intent of this project is to renovate the existing perimeter path at Stow Lake and the site furnishings, including benches and picnic tables to achieve ADA compliance. The construction will be performed in two phases so that half of the perimeter path will be open at all times. No work will be occurring in the area in front of the Boathouse.
Funding
This project is being funded by multiple sources including the following:
- Recovery Stimulus and Critical Repairs
- General Fund
- Mayor’s Office on Disability
Project Schedule
Phase | Timeline |
Planning | Spring 2014 |
Design | Summer 2018 |
Construction | Spring 2023 |
Open to the public | Fall 2023 |
Project Updates
If you would like to sign up for updates click here and scroll down to the NewsFlash and select the alerts you would like to receive.
-
-
Stow Lake Path Project Update - 2/13/2023
We are happy to report that the first quarter of the Stow Lake Perimeter Path Renovation is now complete. . . Read on... -
Stow Lake Pathway Improvement Project Update 9/6/22!
Hi all- We are pleased to report that on August 18, the RPD Commission approved the contract award for the construction of Stow Lake. . . Read on... -
Stow Lake Perimeter Path Project Update March 2022
Our biologist will conduct a few more wildlife surveys at Stow Lake over the next month. Once complete, we will incorporate measures Read on... -
Stow Lake Perimeter Path Project Update 2/23/2022
Our biologist has been conducting surveys of the wildlife at Stow Lake. Once the surveys wrap up later this Spring, we will be Read on... -
Stow Lake Perimeter Path Project Update 1/21/22!
We are anticipating having a biologist on-site in January and February to conduct wildlife surveys. . . . Read on... -
Stow Lake Path - Pathway interruption 12-14 through 17!
Path may be interrupted by tree removal . . . Read on... -
Stow Lake Perimeter Path Project Update 12/17!
Hi all- We will be working with a biologist to conduct surveys around Stow Lake for red-legged frogs and to make recommendations on how to minimize any biological impacts. . . Read on... -
Stow Lake Perimeter Path Project Update 11/18!
Hi all- The project team is working with a biologist to minimize impacts to the wildlife around the lake. . . Read on...
Project Details
- N/A
Commission Materials
- N/A
Community Meetings - Notes and Presentations
- N/A
-
Steve Tucker
Project Manager