Golden Gate Park - Stow Lake Perimeter Path Renovation

Opened to the public September 2023!Stow Lake construction paving - new paved path curving through wooded area


Scope of Work

Stow Lake is popular destination in Golden Gate Park for strolling, boating and picnicking. Before construction, the asphalt path that circles the perimeter of the lake had deteriorated and was in need of repair.

This project renovated the Stow Lake perimeter path and site furnishings, including benches and picnic tables to achieve ADA compliance. The construction was performed in two phases so half of the perimeter path was open at all times.

Funding

This project was funded by multiple sources including the following:

  • Recovery Stimulus and Critical Repairs
  • General Fund
  • Mayor’s Office on Disability

The construction contract award for this project was approved by Recreation and Parks Commission on August 3, 2022 (PDF); This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project's funding sources. 

Project Schedule

PhaseTimeline
PlanningSpring 2014
DesignSummer 2018
Construction contract awardedAugust 3, 2022
ConstructionSpring 2023
Open to the publicFall 2023


Get Out and Play!

Thanks for supporting Park Improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews

You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!

  1. Documents and Materials