Construction work continues at the Alice Chalmers Playground. Azul Works, Inc. has completed the installation of all site walls, retaining curbs, and the two sloped ADA walkways. Utilities, including drainage and irrigation lines have been installed below the sub-grade and will support irrigation of the new landscaping on the site.Two of the three planter benches have been formed and poured, and we are excited to see progress and the playground taking shape. More updates to come!