We still have many utility inspections to go; however, to round off the Margaret S. Hayward Playground Renovation, tennis courts will be CLOSED for resurfacing from10/26 through mid-November 2020.
Over the last two years, tennis courts received an entirely new southern edge: a new foundation, new drainage and new fencing, new gate and accessible path to the rest of the park, new drinking fountain (within the park) and all new windscreens. The lights that were disabled for crew safety during demolition, are reconnected and will resume with electrical inspection approval in mid-November.
Thank you for your patience and continued support throughout construction.
During this construction, please visit one of the nearby tennis courts during this work:
- Alamo Square Tennis Courts (Grove Street & Steiner Street)
- Hamilton Tennis Courts (Post Street & Pierce Street)
See these postings that just went up: