RPD Park Improvements: Angelo J. Rossi Pool

Posted on: October 29, 2020

Rossi Pool Project Update 10/28!

Capital Project Update

Much progress has been made over the past couple months on the utilities, sitework and interiors. Highlights include formwork for the new North Stairs, Mechanical Enclosure steel columns, and Boiler System connections in the basement.

On the interiors, wall framing, drywall and insulation in locker room areas are near completion. The contractor is hard at work in the natatorium with pool gutter and tile install. Pool and mechanical/electrical/plumbing equipment and connections is on-going.

Completion and reopening of the pool is expected Spring of 2021.

Construction crew working on the interior of the pool.

Wood temporary safety railing on the exterior of the pool. Pool deck tile with the words No Running

Metal wall joists outside of the existing pool building.


Stair forms made of wood and rebar inside concrete walls.

Construction worker installing drywall in front office of pool building.