Posted on: March 20, 2023
As a quick update on the Stow Lake Perimeter Path Renovation, construction is moving faster than anticipated. We are nearly finished with the first half of the project
Hi neighbors! As a quick update on the Stow Lake Perimeter Path Renovation, construction is moving faster than anticipated. We are nearly finished with the first half of the project, we should be repositioning the fencing and starting the second half of t...
Read on...
Additional Info...
Stow Lake Perimeter Path Renovation
Posted on: February 13, 2023
We are happy to report that the first quarter of the Stow Lake Perimeter Path Renovation is now complete. . .
Hey Neighbors! We are happy to report that the first quarter of the Stow Lake Perimeter Path Renovation is now complete – ahead of schedule! Our contractor is now moving into the next phase. Preparation for this work has begun. This work will in...
Read on...
Additional Info...
Stow Lake Perimeter Path Renovation
Posted on: September 14, 2022
Hi all- We are pleased to report that on August 18, the RPD Commission approved the contract award for the construction of Stow Lake. . .
Hi all- We are pleased to report that on August 18, the RPD Commission approved the contract award for the construction of Stow Lake. Pre-construction coordination will begin at the end of September with an anticipated construction start date of early Oct...
Read on...
Additional Info...
Stow Lake Perimeter Path Renovation
Posted on: March 18, 2022
Our biologist will conduct a few more wildlife surveys at Stow Lake over the next month. Once complete, we will incorporate measures
Our biologist will conduct a few more wildlife surveys at Stow Lake over the next month. Once complete, we will incorporate measures into our specifications that ensure the protection of special status species during construction. We are also co...
Read on...
Project page
Stow Lake Perimeter Path Renovation
Posted on: February 24, 2022
Our biologist has been conducting surveys of the wildlife at Stow Lake. Once the surveys wrap up later this Spring, we will be
Hi folks- Our biologist has been conducting surveys of the wildlife at Stow Lake. Once the surveys wrap up later this Spring, we will be incorporating measures into our specifications to ensure the protection of special status species during construction....
Read on...
Project Page
Stow Lake Perimeter Path Renovation
Posted on: January 21, 2022
We are anticipating having a biologist on-site in January and February to conduct wildlife surveys. . . .
Hi all- We are anticipating having a biologist on-site in January and February to conduct wildlife surveys. We are still looking forward to bidding later this Spring! For questions, please reach out to Project Manager, Alexis Ward, at alexis.ward@sfgov.or...
Read on...
Additional Info...
Stow Lake Perimeter Path Renovation
Posted on: December 17, 2021
Hi all- We will be working with a biologist to conduct surveys around Stow Lake for red-legged frogs and to make recommendations on how to minimize any biological impacts. . .
Hi all- We will be working with a biologist to conduct surveys around Stow Lake for red-legged frogs and to make recommendations on how to minimize any biological impacts. Once this is finalized, we will advertise the project to potential contractors. &am...
Read on...
Additional Info...
Stow Lake Perimeter Path Renovation
Posted on: November 18, 2021
Hi all- The project team is working with a biologist to minimize impacts to the wildlife around the lake. . .
Hi all- The project team is working with a biologist to minimize impacts to the wildlife around the lake. We will be moving forward with the hazardous tree removals later this year. We are aiming to advertise the project to potential contractors in the co...
Read on...
Additional Info...
Stow Lake Perimeter Path Renovation