Rossi Pool Project Update 4/28!

Capital Project Update

Project progress is moving along well. Current construction activities include: 

  • Sitework/Landscaping – The site utility subcontractor is currently working on the side sewer scope from Arguello East towards the property.  
  • Struct...
Read on...

Additional Info... Angelo J. Rossi Pool Renovation
Posted on: March 9, 2021

Rossi Pool Project Update 3/9/21!

Capital Project Update

Project progress is moving along well, despite some recent construction delays due to unforeseen site conditions. Current construction activities include: Exterior window and doors installation, interior tiling, epoxy flooring, painting. Pool and mechanic...

Read on...

Additional Info... Angelo J. Rossi Pool Renovation
Posted on: October 29, 2020

Rossi Pool Project Update 10/28!

Capital Project Update

Much progress has been made over the past couple months on the utilities, sitework and interiors. Highlights include formwork for the new North Stairs, Mechanical Enclosure steel columns, and Boiler System connections in the basement.

On the interiors, wal...

Read on...

Additional Info... Angelo J. Rossi Pool Renovation
Posted on: June 27, 2018

ROSSI POOL PROJECT UPDATE

Capital Project Update

Planning for the Rossi Pool renovation is moving along as the design team completes construction documents. We intend to put the project out to bid later this year – 2018.

The department anticipates keeping the pool and programming open through t...

Read on...

Angelo J. Rossi Pool Renovation
Posted on: January 6, 2020

ROSSI POOL RENOVATION PROJECT UPDATE

Capital Project Update

Rossi Pool Renovation Project is moving forward as scheduled.   Work has included demolition of old infrastructure and equipment and the contractor is starting on new structural improvement work.  All going as planned.

By: Dan Mauer

Read on...

Angelo J. Rossi Pool Renovation