We are excited to share some significant project progress since our last construction update in June. Abatement and demolition work of the old facility has been completed.
Our foundations subcontractor, Drilltech, is mobilizing to begin the test program for Deep Soil Mixing (DSM) ground improvements. This is the first step to gain the information we need to move forward with the DSM itself, which is a means to structurally stabilize the soil underneath the rec center. This method has been utilized at many nearby projects. It will take several months and while not much is visible, please know that this below grade work is fundamental to the project’s success. More information on Deep Soil Mixing (DSM) is available here >>
NOTE TO NEIGHBORS: We anticipate the Contractor team will be working this Saturday, August 3, from 7 am to 7 pm. We anticipate more Saturday work and extended hours in August or September, once DSM site work commences. We’ll follow up once we have more details.
Thank you for your support of this project.
Melinda Sullivan, Project Manager, Melinda.Sullivan@sfgov.org.
For more information, visit the project webpage >>