Much progress has been made over the past couple months on the utility and sitework, including concrete curbs, walls, paving and ramps, regrading, as well as installation of irrigation systems, water service, PG&E power, and gas service. The multi-purpose sports court surface has been installed, and planting is expected to begin next month. The mural restoration and expansion is nearing completion, blending new mural sections with the old for a seamless transition. 

On the interiors, tiling and drywall are complete and casework installation is underway. The contractor is hard at work on the natatorium interior, with extensive plaster work and other finishing of the walls and structure underway. Trench drains are being set now, in preparation for the new pool deck waterproofing and concrete slab which will be installed in the coming weeks. Installation of pool and mechanical/electrical/plumbing equipment and connections is on-going. 

Completion and reopening of the pool is expected fall/winter 2020.

Mural with blue and green dragon is on the left. Window next to the entrance is shown on the right.

The photo shows a half basketball court in the middle, partially covered in brown construction paper

The photo shows the empty pool with construction materials sitting inside of it. The left side shows

On the far left side of the mural is a green octopus underneath a red clay cliff, below is is two sc

Phot shows the new mural on the Garfield Pool Building. The mural depicts a blue and green dragon ea


  1. Footer site
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow