Garfield Pool Renovation Update 10/27!

Rec Park Improvements | All Project Updates Posted on October 27, 2020

The major construction activities have been completed and we are near the finish line on this much anticipated addition to the neighborhood! The Design and Construction teams have been working hard, and much progress has been made over the past couple of months on the exterior and interior of the project. See highlights below:

  • Pool Plastering,
  • Filling pool with water,
  • Installation of Wood Slats in Natatorium,
  • Multipurpose Room finishes,
  • Landscape work including tree planting, ground cover, and new sod,
  • Trespa panel installation at the Clubhouse exterior façade ,
  • Art Glass installation, and
  • Mural restoration by Precita Arts Muralists.

Completion and reopening of the pool is expected winter 2020/21. We Look forward to sharing this project with you!

Interior of the pool building, wood slat walls, bulkhead, dive platforms, mural on glass windows

Interior of the clubhouse, grey and white variegated vinyl flooring, white ceiling, wall of windows

Blue and white tile clubhouse building, Pool Building, planter beds, cement pathway and patio

Wood slat walls, white open ceilings, life guard chairs and pool filled with water

Clubhouse interior, blue and white tile walls, cement floor and wood slat ceiling