Much has happened in the park these past two months!
The main path was blocked during the weekdays in Nov while the construction crew potholed, trenched, and laid conduits and backfilled the area parallel to the main path- Although easy to peer over the barriers, here are photos of the progression.
Where are we now? Waiting for light fixtures to arrive, which is due early next year post holiday. Next month will mark the installation of light poles, the bollard lights in front to the restrooms and minimal trenching NE corner of the park for the last light pole.
Note the main path sliver of concrete removed by the skilled contractor! Matching the color of aged, warm tone concrete is impossible, but since the crew surgically removed this piece, it will be installed and only two thin lines mark the work. Almost seamless. 😊