We are excited to announce Notice to Proceed was issued to the Contractor, Cazadoro Construction, Inc, on April 20. Here are some specific updates:
- We are working around a bird nest that has been identified by a certified biologist, per the survey requirements outlined in our contract specifications
- The contractor will be removing trees outside the bird nest buffer the week of May 2
- The contractor is completing survey work related to site drainage scope
- We anticipate that the Shields Street sidewalk work will commence in May and be completed within approximately 1 month. Pedestrians will be directed to use the sidewalk on the north side of Shields Street during this time.
We’re still working to finalize plans for tile work on the park wall above the plaza, to recognize community contributions. Please stay tuned for additional updates.