Hi neighbors! We wanted to share an update on the turf replacement happening now at Crocker Soccer. Fields 1 and 2 will be re-opened by late July and then fields 3 and 4 will close for renovation, ensuring at least 2 fields are always open. Field 5, which is currently under renovation, will be completed and re-open at the beginning of August.
We’re also opting to expand the scope of the project to include a new rain garden, an expansion of the parking lot, and some irrigation system rerouting. These changes would increase the contract budget just under $1,000,000 since the project was last approved by our Rec and Park Commission, and so we will be bringing this proposal to the Rec and Park Commission on July 20 for discussion and approval.
For more information, please visit the project website: https://sfrecpark.org/1664/McLaren-Park---Crocker-Amazon-Soccer-Fie
Omar Davis, Project Manager, omar.davis@sfgov.org