News Flash

RPD Park Improvements: Esprit Park

Posted on: April 28, 2022

Esprit Park Project Update 4/28!

Capital Project Update

The design team is continuing to close design and coordination loops as efficiently as possible, still with the goal of finalizing construction documents and advertising to contractors this spring.

Here are some specific updates from this month:

  • SFPUC has provided conditional approval for our Stormwater Control Plan (today!)
  • We are working with our third party cost estimator to make multiple updates to the cost estimate to reflect design updates as we have them, including to soils management costs that are driven by Maher Program compliance and tree protection goals
  • Engaging the Public Works Contract Prep team, so that they can start to pull together documents toward advertising the project
  • Received documentation from UCSF on availability of funds for construction
  • Coordinating with UCSF on timely disbursement of funds pending confirmation of responsive bidder

Stay tuned for more updates.

Additional Info...
Facebook Twitter Email

Other News in RPD Park Improvements: Esprit Park

Capital Project Update

Esprit Park Renovation Update 12/22!

Posted on: December 22, 2022
Capital Project Update

Preparing for Tree Work at Esprit Park

Posted on: September 12, 2022
Capital Project Update

Esprit Commission Presentation Sept 7!

Posted on: September 1, 2022
Capital Project Update

Esprit Park Project Update 6/2!

Posted on: June 3, 2022
Capital Project Update

Esprit Park Project Update 3/23/2022

Posted on: March 23, 2022
Capital Project Update

Esprit Park Project Update 2/23/2022

Posted on: February 24, 2022
Capital Project Update

Esprit Park Project Update 11/23!

Posted on: November 23, 2021
Capital Project Update

Esprit park Project News 9/30/21!

Posted on: September 30, 2021
Capital Project Update

Esprit Park Project Update 9/11!

Posted on: September 10, 2021
Capital Project Update

Esprit park Project News 6/14!

Posted on: June 14, 2021
Capital Project Update

Esprit park Project News 4/23/21!!

Posted on: April 23, 2021
Capital Project Update

Esprit Park Renovation Update MAR '21

Posted on: March 29, 2021
Capital Project Update

Esprit park Project News 2/23!

Posted on: February 23, 2021
Capital Project Update

Esprit park Project Update 1/22!

Posted on: January 22, 2021
Capital Project Update

Esprit Park Renovation Update Dec '20

Posted on: December 23, 2020
Capital Project Update

Esprit park Project Update 10/29!

Posted on: October 29, 2020
Capital Project Update

Esprit park Project Update 9/18!

Posted on: September 18, 2020
Capital Project Update

Esprit Park Project Update 8/21!

Posted on: August 21, 2020
Capital Project Update

Esprit Park Project Update 7/24!

Posted on: July 24, 2020
Capital Project Update

Esprit Park Project Update 5/22

Posted on: May 22, 2020
Capital Project Update

Esprit Park Project Update 4/17

Posted on: April 17, 2020
Capital Project Update

Esprit Park Project Update

Posted on: March 23, 2020
Capital Project Update

POP-IN WORKSHOP SUMMARY FEB 2020

Posted on: February 21, 2020
Capital Project Update

ESPRIT PARK WORKSHOP- CONCEPT PLAN

Posted on: January 31, 2020
Capital Project Update

ESPRIT PARK COMMUNITY OUTREACH UPDATE

Posted on: December 18, 2019
Capital Project Update

POP-UP PLAYDATE AT ESPRIT PARK!

Posted on: November 18, 2019
Capital Project Update

ESPRIT PARK RENOVATION

Posted on: November 6, 2019