The design team is closing in on 100% completion of the construction documents and the project will soon be advertised for bids. The project is on track to begin construction in early 2023 for an 8 month construction duration. Rec and Parks will coordinate closely with SFMTA to route transit, pedestrians, bikes and traffic through the intersection at 9th and Lincoln to minimize disruption and maintain access to Golden Gate Park throughout the life of the project.
- NewsFlash
- Rec Park Improvements: Golden Gate Park - 9th & Lincoln Gateway
News Flash
Golden Gate Park – 9th and Lincoln Gateway Project Update September 2022!
The design team is closing in on 100% completion of the construction documents and the project will soon be advertised for bids. . .