Since our last update in May, the contractor team has made significant progress with the installation of infrastructure, and you can really start to see what the renovated park will look like. If you haven’t been by the site recently, take a look!
The most visible sign of this progress is in the network of concrete pathways and plazas, most of which have now been graded; some have been formed and poured.
In the next month, we will continue to plant the park’s new trees and plants, as well as place the sod for the lawns. We will also be installing the new site lighting.
Stay tuned for more updates, and thanks again for your support of this project.
Melinda Sullivan, melinda.sullivan@sfgov.org, 628-652-6648.
For more information, visit our Esprit Park Renovation Project webpage.
Photos: Grading and formwork for pathways; Concrete installation in progress along Minnesota