We wanted to share an update on the work to modernize the elevator equipment in Portsmouth Square Garage, since our last update in July.
The contractor is currently working on elevator car 1 and on-track to be finished later this fall. Once elevator car 1 is complete and back in service, the contractor will begin work on elevator car 2.
Feel free to reach out with any questions.
Jeannine Kane, Project Manager, jeannine.kane@sfgov.org
For more information, please visit the project page >>