Waterproofing and drainage work continues on the second half of the plaza. We expect some odor during this process, and industrial fans will be used to help with airflow.
Also, please be advised that we expect some limited Saturday construction work in December.
Other construction highlights for this month include:
Plaza/Pagoda Work:
- Lower plaza concrete topping slab was poured mid-November.
- Steel tendons to support the Pagoda were woven through each level, secured on upper-level garage ceiling, and are now being properly tensioned. These steel tendons are the black vertical lines on either side of columns.
Garage Work:
- Plumbing/Electrical layout and installation continues.
- Scaffolding and shoring work continues in the ramp leading to lower level.
Access to Japan Center Malls and Parking Garage:
- Access from Geary Boulevard: Use the Geary Boulevard parking garage to access both East Mall and West Mall.
- Access from Post Street: Use the new posted detours into East Mall adjacent to U.S. Bank and to West Malls adjacent West Mall building.
- Sidewalk: Accessible pedestrian detour is open along the north side of Geary between Laguna to Buchanan Streets. For safety, follow all detours, stay within fenced pedestrian detour lane, and avoid walking in the bus lanes.
- Parking Garage: 60 parking spots under pagoda, in both upper and lower garage levels will be occupied through early 2026. Drive cautiously in the garage and follow posted detours signs on both upper and lower levels. Please do not walk on the ramp between levels.
๐ฌ Have questions or concerns?
Feel free to contact the project manager:
J. Marien Coss
๐ 628-652-6647
Please visit the project webpage at:
Japantown Peace Plaza Renovation Project