Following up on our last update at the end of May, we’re pleased to report that major demolition is now 40% completed. In the past few weeks, demolition focused on removing the plaza surfacing near the pagoda and west side of the plaza. The crew is working to expose the structural slab, surface beams, and fountain base. Note that all the vents and drains have been covered and protected from construction debris.
We have also completed all the necessary removal of landscaping features. The plants that are being preserved for later replanting have been delivered to the Rec & Park Nursery in Golden Gate Park. Our staff will care for them until they are replanted in the plaza at the end of construction.
Major demolition is expected to continue into August. In next few weeks, we expect to complete the demolition of the plaza wall along Geary Blvd, the planter wall near East Mall, and the lower level of the plaza surface to expose the structural slab.
Remember! Japan Center Malls remain open throughout the construction duration. Please be aware of the following pedestrian detours:
- Access from Geary Boulevard – Detour to both East Mall and West Mall through the Geary Boulevard parking garage
- Access from Post Street – Enter through existing fenced paths near the buildings to East Mall and West Mall
- SIDEWALK CLOSED on the north side of Geary Boulevard from Laguna Street to Buchanan Street (mid-block crosswalk).
Thank you for your support as we embark on this exciting project!
For more information about the project, visit the project page >>
Marien Coss, Project Manager, (628) 652-6647, marien.coss@sfgov.org