News Flash

Posted on: September 20, 2023

Ocean Beach Climate Change Adaptation Project (OBCCAP) | Response to Comments Published

Capital Project Update

The San Francisco Planning Department has published the Responses to Comments document for the Draft Environmental Impact Report (EIR) for the Ocean Beach Climate Change Adaptation Project on the San Francisco Planning Department’s website at sf...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 18, 2023

Buchanan Street Mall | Memory Walk design reviews + workforce development meetings this week!

Capital Project Update

This is a full week for the Buchanan Street Mall Renovations project!

The Buchanan Street Mall project team is seeking San Francisco Arts Commission Civic Design Review committee approval on the landscape features of the Memory Walk: decorative paving and ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 12, 2023

Herz Playground Now Open! | Project update September 2023

Capital Project Update

Hello neighbors!

Following a spectacular, $3.38 million dollar renovation, we were pleased to re-open Herz Playground at the end of August. Read our press release here >>

Thank you to all of the community members who attended the ribbon cutting ceremo...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 11, 2023

Marina Project Update | NEW Rec Park Commission Meeting Information

Capital Project Update

Due to the significance of this project, we will be presenting this to the Rec Park Commission on two occasions in October. The first will be to the Capital Committee on Wednesday, October 4th, at 2 pm. Following this meeting, we will be returning to the ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 30, 2023

Golden Gate Park - Middle Lake | Construction update, August 30, 2023

Capital Project Update

Hello neighbors! Construction at Middle Lake in Golden Gate Park took a brief break during August to make room for Outside Lands but the project is now back up and running!

Next steps are grading and construction of the second island, planting around the l...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 30, 2023

Herz Playground Now Open! | Community, City Officials Celebrate $3.38 Million Makeover

Capital Project Update

SAN FRANCISCO—Creative new play equipment for kids of all ages and a park makeover inspired by nature greeted families Thursday evening at the unveiling of the renovated Herz Playground in McLaren Park, the San Francisco Recreation and Park Depa...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 30, 2023

San Francisco Marina Improvement and Remediation Project | Community Meeting Update and Survey Link!

Capital Project Update

Thank you to all those who were able to attend our two community meetings on August 23 and 26. We had 279 people attend and we heard a lot of feedback on this project and its elements.  

For those of you who were not able to attend the meetings, p...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 29, 2023

Gene Friend Rec Center | Call for Artists, Zoning Variance, Contract Amendment

Capital Project Update

Excited to report on some updates for the Gene Friend Rec Center Project!

Call for Artists!

The Request for Qualifications (RFQ) for artists for public art for the project has been posted on the Arts Commission website. Please note that the deadline for qua...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 25, 2023

Golden Gate Park - Golf Clubhouse | construction update August 2023

Capital Project Update

The construction of the Golf Clubhouse is progressing nicely. Our contractor has been working on installing all of the building rough-ins, the ductwork, finishing the roof, and site work for the area surrounding the clubhouse. There has ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 25, 2023

McLaren Park - Louis Sutter Playground ADA | Project update August 2023

Capital Project Update

The Louis Sutter ADA project is currently in the design phase. We're excited to announce that the project was recently awarded a Green Infrastructure Grant by the San Francisco Public Utilities Commission (SFPUC), which will allow us enhance stor...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 25, 2023

Buena Vista Park | Project update August 2023

Capital Project Update

The topographic survey for this project has been received and we are coordinating with the Department of Public Works to bring a design team fully on board. We anticipate the design process starting in the fall of this year. Please stay tuned and we will ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 24, 2023

Esprit Park | Construction update, August 2023

Capital Project Update

Thanks to community members who have been keeping an eye on the park and on construction progress and reaching out to the Rec and Park team with questions and concerns.

A majority of inquiries we’ve received are in the following two categories:

  1. Wh...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 22, 2023

Japantown Peace Plaza Renovation | Construction bid opportunity now advertised!

Capital Project Update

Japantown Peace Plaza Renovation bid has been advertised! Please share the links below with interested contractors and subcontractors.

Bid Opening: 

Wednesday, September 27, 2023, at 2:30pm (conducted live online via Microsoft Teams)

Links to Bid Ad...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 22, 2023

Louis Sutter Playground | Temporary parking closure, August 23 + 24

Capital Project Update

San Francisco Recreation & Park announces a temporary parking closure at Louis Sutter Playground. The southern parking lot and driveway from University Street at Woolsey Street will be closed Wednesday, August 23 through Thursday, August 24 for irriga...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 17, 2023

Ocean Beach Climate Adaptation Project | Project update August 2023

Capital Project Update

Upcoming Opportunity to Provide Public Comment for the Ocean Beach Climate Adaptation Project (OBCCAP)

Phase 3 of the San Francisco Arts Commission’s Civic Design Review for the Ocean Beach Climate Change Adaptation Project will be taking place on Monday, ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 10, 2023

Gene Friend Rec Center | RFQ for Public Art with Online Pre-Application Workshop, August 30

Capital Project Update

The Arts Commission approved the Public Art Project Plan for the Gene Friend Rec Center Project earlier this week. The Request for Qualifications (RFQ) for artists has been posted on the Arts Commission website. Please note that the deadline for qualifica...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 10, 2023

Herz Playground | Reopening Celebration, August 24!

Capital Project Update

Herz Playground Ribbon Cutting Celebration

Join us to celebrate the renovation of Herz Playground.

August 24, 5 to 6 p.m.

1701 Visitacion Avenue

Refreshments | Kids Activities | Brief Speaking Program

A project of the Let'sPlaySF Initiative

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 9, 2023

Last call for the Buchanan Mall Memory Walk survey!

Capital Project Update

Thanks for all the wonderful feedback folks have shared on the latest designs for the Buchanan Street Mall Memory Walk.

If you haven’t yet, please take 10 minutes to complete the survey before 5pm on this Thursday, 8/10/2023!

TAKE THE SURVEY >&...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 5, 2023

San Francisco Marina Improvement and Remediation Project | Community meetings, August 23 and 26

Capital Project Update

Community meetings for San Francisco Marina Improvement and Remediation Project

Please join us for our second round of community meetings to discuss the future of the San Francisco Marina.

Session 1: Wednesday, August 23, 6 to 7:30 p.m.

Session 2:&a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 3, 2023

Herz Rec Center | Project update August 2023

Capital Project Update

Hello neighbors! We have some excellent news to share. On June 15, our Rec and Park Commission unanimously approved a contract award to SJ Amoroso Construction Co., LLC. to construct the new Herz Rec Center. 

To get an idea of what the new Rec Cen...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 3, 2023

South Sunset Clubhouse | Project Update August 2023

Capital Project Update

We’re happy to announce that we have brought Paulett Taggart Architects and MARJANG Architecture onboard as our project designers for South Sunset Clubhouse to work alongside the mechanical and structural engineers from San Francisco Public Work...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 3, 2023

Fillmore Turk Mini Park | Project Update August 2023

Capital Project Update

We’re happy to report that construction on Fillmore Turk Mini Park is moving right along. The majority of the precast furnishings have been delivered and placed on site. Most of the pavers have been laid out and additional soil is being brought to site as...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 3, 2023

Noe Valley Town Square Restroom | Project update August 2023

Capital Project Update

Good news. Since our last update, the design plans for the new restroom were approved by the State of California. With this approval, we can now finish the final design for the exterior grounds, including how the restroom ties into existing landscaping an...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 3, 2023

Golden Gate Park - San Francisco Botanical Garden Bookstore

Capital Project Update

In response to a citizen complaint about access into the San Francisco Botanical Garden Bookstore in Golden Gate Park, Rec and Park will be performing construction work to ensure that the Botanical Garden Bookstore complies with current building codes and...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 2, 2023

McLaren Park Vision Plan Update + Upper Yosemite Creek Daylighting Project | August 2023

Capital Project Update

Hello neighbors! We have two important updates to share about John McLaren Park:

1) McLaren Park Planning Survey Extended through 8/25/2023!

The McLaren Park 2020 Bond Planning priorities survey has been extended through 8/25/2023. Please complete this map-...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 1, 2023

Gene Friend Recreation Center | Project update August 2023

Capital Project Update

We have hit some exciting milestones for the Gene Friend Rec Center Project!

On July 17, the Arts Commission Civic Design Review Committee approved the project to move forward from schematic design into design development, also known as Phase 2 of the thre...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 25, 2023

Golden Gate Park - 9th and Lincoln Gateway | Project update July 2023

Capital Project Update

We have great news to share. On July 20, our Rec and Park Commission unanimously approved a contract award to Bauman Landscape and Construction for project work that we believe will greatly improve and revitalize Golden Gate Park's 9th Avenue Gateway. Com...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 26, 2023

Golden Gate Park - Middle Lake | Project update July 2023

Capital Project Update

Construction at Middle Lake in Golden Gate Park is moving along nicely. Work on the cascade below the Angler’s Lodge casting ponds continues. Check dams and pools are scheduled to be constructed soon. 

In preparation for Outside Lands, t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 25, 2023

Richmond Playground | Project update July 2023

Capital Project Update

We’re excited to share that a construction contract award for the Richmond Playground was approved by Rec and Park Commission on July 20!

Treaty Construction plans to begin work in the coming months and we’re aiming to reopen the new pl...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 24, 2023

Esprit Park | Construction update, July 2023

Capital Project Update

Thanks to community members who have been keeping an eye on the park and on construction progress. A couple of community members have reached out to express concerns about the dryness of the trees preserved on site.

The viability and health of the trees on...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 24, 2023

Crocker Amazon Soccer Fields | Construction updates July 24, 2023

Capital Project Update

Hi neighbors! Good news! As of July 18, Crocker Soccer Fields 1 and 2 are now completely renovated and opened to the public again. 

We opted to complete the replacement of Crocker Amazon’s five fields in three phases this year so that th...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 24, 2023

Golden Gate Park - BAYS Memorial Garden | Project update July 2023

Capital Project Update

Hi neighbors! The BAYS Memorial Garden is wrapping up the design phase, having received approval of the concept design from the Recreation and Parks Commission earlier this year. Below is an image of the concept design, which was developed and refined wit...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 20, 2023

Buchanan Street Mall Renovations | Healing circles and Memory Walk design

Capital Project Update

Thanks to everyone who is showing up and participating in summer healing circles. Community gatherings continue every other Wednesday (see below for details). National Healing Collective and Atunse Justice League are also preparing a training to skill com...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 20, 2023

Louis Sutter Playground | Path improvements complete | Construction update July 2023

Capital Project Update

Our replacement of a failed asphalt pathway south of Louis Sutter Playground is now complete! The fencing has been removed, large logs are in position to prevent vehicle access, and the adjacent area is prepared for future planting. This new Outdoor Recre...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 18, 2023

Gene Friend Recreation Center | Visual Arts Committee and Civic Design Review Updates

Capital Project Update

Public Art Project Plan Presentation for Gene Friend Rec Center

Thank you to community members who have provided input on the Public Art Project Plan!

The Public Art Project Plan for Gene Friend Rec Center will be presented to the Arts Commission Visual Art...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 14, 2023

Gene Friend Recreation Center | Civic Design Review and Visual Arts Committee Next Week

Capital Project Update

The Gene Friend Rec Center project team will be presenting to the Arts Commission, Civic Design Review Phase 2, this coming Monday, July 17, 2:00 pm. This is a public meeting and there is an opportunity for public comment. Registering your comments in thi...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 10, 2023

Stow Lake Perimeter Path | Construction update July 2023

Capital Project Update

Hi neighbors! The repaving work at Stow Lake continues to be moving along very well. We have completed 75% of our repaving work and are still on pace to finish by August. The areas of pathway that have been completed are open to the public and look great....

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 7, 2023

Louis Sutter Playground | Construction update July 2023

Capital Project Update

Hello neighbors! A quick construction update on Louis Sutter Playground. We passed our accessibility inspections and construction fencing is coming down soon. You will see ongoing planting work after the fencing is removed, but we’re excited to ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 6, 2023

Crocker Amazon Soccer Fields | Construction updates July 2023

Capital Project Update

Hi neighbors! We wanted to share an update on the turf replacement happening now at Crocker Soccer. Fields 1 and 2 will be re-opened by late July and then fields 3 and 4 will close for renovation, ensuring at least 2 fields are always open. Field 5, which...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 5, 2023

Complete the McLaren Park 2020 Bond Planning priorities survey

Capital Project Update

Happy summer, McLaren Park neighbors and visitors!

We’ve created a new map-based survey to collect your thoughts on possible programming, infrastructure, and connectivity improvements in John McLaren Park.

Please take 15-20 minutes over the next s...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 5, 2023

Golden Gate Park - Golf Clubhouse construction update | July 2023

Capital Project Update

Hi neighbors! Construction of the Golf Course Clubhouse is moving right along. Over the next few weeks, the contractor will be working on installing the roof of the clubhouse, as well as excavating the area around the clubhouse in preparation for landscap...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 29, 2023

Golden Gate Park - Middle Lake | Project update June 2023

Capital Project Update

Hi neighbors! The rehabilitation work at Middle Lake continues. The scope of this project includes recontouring the lake bottom, installing a clay liner to help the lake hold water, installing an aeration system to promote the lake’s ecological ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 28, 2023

Herz Playground | Project update June 2023

Capital Project Update

Hi neighbors! The Herz Playground renovation is rounding the corner this summer and you can see the space is really taking shape! The new play equipment has been installed and the foundation for the climbing wall is now up. The playground surface is being...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 28, 2023

Richmond Playground | Project update June 2023

Capital Project Update

Hi neighbors! We’re looking forward to starting construction at Richmond Playground later this year. The project will feature a complete renovation of the Children’s Play Area, accessibility improvements at the park entry and restrooms...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 26, 2023

Buchanan Street Mall Renovations | Join us for Summer Community Gatherings in June, July, and August

Capital Project Update

Join neighbors and facilitators to continue conversations on healing and transformation in our community. Help recreate Buchanan Street Mall as a park that strengthens the neighborhood, builds economic opportunity, and improves health and wellness for eve...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 21, 2023

San Francisco Marina Improvement and Remediation | Project Update June 21, 2023

Capital Project Update

We are gearing up for our next round of community meetings to be held at the end of August. We will post the meeting info here as soon as they are confirmed.

We look forward to utilizing these community meetings to share what we've been hearing fr...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 16, 2023

Portsmouth Square Improvement Project | Project update June 2023

Capital Project Update

Hello neighbors! We wanted to share some updates from the Portsmouth Square Improvement Project, a complete renovation of the park slated to begin next year. We have just completed construction drawing updates to include design improvements to the followi...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 16, 2023

Buena Vista Park | Project update June 2023

Capital Project Update

Hello neighbors! A quick update on the Buena Vista Park Improvement Project, a construction project slated for 2025 that will make extensive improvements to the paved path network throughout the interior of the park.

The topographic survey that we said in ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 14, 2023

Shelley Promenade Project in McLaren Park | Reminder: Proposal at Rec & Parks Commission tomorrow

Capital Project Update

Shelley Promenade Project in McLaren Park – Recreation and Parks Commission – June 15, 2023, 10:00 a.m.

 The Recreation and Parks Commission will hear the proposed Shelley Promenade Project tomorrow at 10:00 a.m.

  • The Pr...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 14, 2023

South Sunset Clubhouse | Project Update June 2023

Capital Project Update

Hello neighbors! Rec and Park has completed our review of proposals for the complete renovation of the interior spaces of South Sunset Clubhouse and we are one step closer to bringing on a design team for the project. Once the team is of...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 14, 2023

Fillmore Turk Mini Park | Project Update June 2023

Capital Project Update

Hi neighbors! Construction continues at Fillmore Turk Mini Park. We're happy to report that most of the underground work is now wrapped up. The pavers are on site and the construction crew has begun laying them out. Some of the new site furnishin...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 12, 2023

Gene Friend Rec Center | Civic Design Review meeting today cancelled

Capital Project Update

Hi neighbors! We found out today that the SF Arts Commission (SFAC), Civic Design Review Committee meeting scheduled for this afternoon was cancelled due to lack of quorum. We anticipate that the project team’s presentation about Gene Friend Rec...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 12, 2023

Esprit Park | Construction update, June 2023

Capital Project Update

You may have noticed that the pace of construction at Esprit Park has slowed over recent weeks. This is in part because the project team is working together to minimize impact to the roots of trees on site. We have also experienced a large amount of vanda...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 9, 2023

Gene Friend Rec Center | Submit Feedback on Gene Friend Proposed Public Art Plan by 6/15

Capital Project Update

Thanks to all who joined for our online community update on June 8. Project updates were well-received by attendees.

To view the full presentation by Rec and Park and Arts Commission staff, click here >>.

Current schedule is for Arianne G. Davidian, P...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 8, 2023

Gene Friend Rec Center | Virtual Community Update meeting today + Civic Design Review this Monday

Capital Project Update

Gene Friend Rec Center | Virtual Community Update and Civic Design Review

The project team has completed the design development phase of the project and is working with the Construction Manager/General Contractor (CM/GC) and three cost estimating ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 7, 2023

Buchanan Street Mall Renovations | Summer Community Gatherings, June-August

Capital Project Update

Join neighbors and facilitators to continue conversations on healing and transformation in our community. Help recreate Buchanan Street Mall as a park that strengthens the neighborhood, builds economic opportunity, and improves health and wellness for eve...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 1, 2023

San Francisco Marina Improvement and Remediation | Project Update June 2023

Capital Project Update

The San Francisco Marina Improvement and Remediation Project is really two projects in one: 1) a legally mandated environmental remediation project to clean up old industrial pollutants in the harbor and 2) a marina improvement project to enhance accessib...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 1, 2023

11th and Natoma Park Project Update | Public Art Survey and Meeting on June 14

Capital Project Update

11th & Natoma Park: Public Art Survey and Meeting on June 14

Join the San Francisco Arts Commission and Rec and Park for a virtual community presentation on the upcoming public art opportunity at 11th and Natoma Park on Wednesday, June 14 from 6 to 7 p...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 31, 2023

Gene Friend Rec Center | Virtual Community Update: Thursday, June 8, 6:00-7:30 p.m.

Capital Project Update

Virtual Community Update | Gene Friend Rec Center

The project team has completed the design development phase of the project and is working with the Construction Manager/General Contractor (CM/GC) and three cost estimating teams to update the cost estimate...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 25, 2023

Shelley Promenade Project in McLaren Park | Proposal goes to Recreation and Parks Commission in June

Capital Project Update

Shelley Promenade Project in McLaren Park – Recreation and Parks Commission – Operations Committee, June 1, 2023

 The Operations Committee of the Recreation and Parks Commission will hear the proposed Shelley Promenade...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 23, 2023

Herz Rec Center | Project update May 2023

Capital Project Update

Hello neighbors! Bids from contractors for the construction of Herz Recreation Center opened on May 17. Rec and Park is now reviewing the bids we have received and contractor qualifications. Once that is complete, we look forward to moving into t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 22, 2023

Merced Heights Playground’s Lower Terrace Transformed by Renovation

Capital Project Update

A $1.67 million renovation has transformed a former grassy field at Merced Heights Playground into a paradise for neighborhood recreation, with areas for people to picnic or exercise, dogs to frolic, and hummingbirds and butterflies to feed.

The San Franc...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 17, 2023

India Basin Waterfront Park | Project update May 2023

Capital Project Update

On May 12, India Basin Waterfront Park project partners welcomed attendees from the Together Bay Area conference to India Basin Shoreline Park. More than 30 conference attendees learned about the rich history and culture of the Bayview-Hunters Po...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 16, 2023

Crocker Amazon Soccer Fields Project | Project updates May 2023

Capital Project Update

Hello neighbors! We’re excited to report that construction work to replace the field turf at Crocker Amazon has begun.

Construction will occur in three phases so that for the duration of construction there will always be access to a minimum of tw...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 16, 2023

McLaren Park - Louis Sutter Playground | Project update May 2023

Capital Project Update

The pathway replacement work south of Louis Sutter Playground is almost complete! The new stabilized natural surface trail is the first segment of a new multi-use ribbon trail that will be built to extend all the way to the Mansell Tai Chi court within th...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 12, 2023

Buchanan Street Mall | May Community Gatherings focus on the Memory Walk

Capital Project Update

Thanks to everyone who has participated in healing circles over the past several weeks as part of the Buchanan Street Mall Equity Action Initiative. Our project team has received very positive feedback from Fillmore community members on the quality of sha...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 12, 2023

Esprit Park | Project update May 2023

Capital Project Update

You may have noticed a slow down in the pace of noticeable progress on site. The project team is working hard to protect the roots of mature trees during the course of construction. This involves careful exploration with hand tools, as well as working wit...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 12, 2023

Merced Heights Playground Lower Lawn Terrace | Project update May 2023

Capital Project Update

Merced Heights Playground Lower Lawn Terrace Gets Its Finishing Touches

Rec & Park Operations staff and our contractor are putting finishing touches on the Lower Lawn Terrace of Merced Heights Playground, in preparation for our re-opening celebration a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 11, 2023

Herz Playground | Project update May 2023

Capital Project Update

If you have driven down Visitacion Avenue this week, you may have noticed the large towers erected at the Herz Playground construction site. The playground equipment is being installed! The tallest tower is the basis of equipment for age 5-12, in which tw...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 11, 2023

Golden Gate Park - Middle Lake | Project update May 2023

Capital Project Update

Middle Lake Rehabilitation is moving along quickly! Rough grading of the lake and cascade between the lakes is nearly complete and we are almost finished with soil off-haul. Installation of the clay liner is ongoing and moving quickly and installation of ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 9, 2023

Noe Valley Town Square Restroom | Project update May 2023

Capital Project Update

Hi neighbors! Good news – We’ve moved much closer to having public restroom installed at Noe Valley Town Square.

As you may know, in November 2022, the Department was approached by two companies, Volumetric Building Companies and the Pu...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 9, 2023

Fillmore Turk Mini Park | Project Update May 2023

Capital Project Update

Hi neighbors! Construction at Fillmore Turk Mini Park is moving right along! Most all of the necessary digging is now complete. Our construction team has begun pouring the concrete for the new light pole footings. Underground utilities are being set in pl...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 9, 2023

South Sunset Clubhouse | Project Update May 2023

Capital Project Update

Hello neighbors! We have a quick update to share on the progress of the South Sunset Clubhouse renovation. We are currently reviewing proposals for a complete renovation of the interior spaces that were submitted by the anticipated design team. More detai...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 28, 2023

Merced Lower Terrace Re-Opening Celebration | May 19, 12 to 1 PM

Capital Project Update

Join us on Friday, May 19, from 12 to 1 pm, for a re-opening celebration of the Merced Heights Playground Lower Lawn Terrace.

We will be honoring community members who have made significant contributions to the park over the years at this event. The terrac...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 24, 2023

Herz Recreation Center Project update | Bids open May 17

Capital Project Update

Hi Neighbors. 

Earlier this month, we held a pre-bid meeting on-site to review the scope of the Herz Recreation Center Project with potential bidders. We are looking forward to opening bids on May 17th.

As a reminder, the bid information can be fou...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 24, 2023

Water Board meeting + public comment period | SF East Harbor + Outside East Harbor Clean Up Plans

Capital Project Update

Hello Neighbors,

We wanted to pass along the following announcement by our partners at California Regional Water Quality Control Board, San Francisco Bay Region (Water Board) regarding the upcoming environmental remediation work that will be happening in E...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 21, 2023

Esprit Park construction update | April 2023 - Construction Resumes at Esprit Park

Capital Project Update

Due to heavy rain and winds, and then saturated soil, construction at Esprit Park was paused for nearly a month. We are happy to report that our contractor is back on site and making progress. Recent updates include:

  • Street Improvement Permit approved by t...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 21, 2023

Golden Gate Park - Golf Clubhouse construction update | April 2023

Capital Project Update

After a rainy winter, construction for the Golden Gate Park Golf Clubhouse has hit the ground running. Our contractor has poured the slab for the new clubhouse and has started to install the structural elements for the building. As you can see from these ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 19, 2023

Follow up from McLaren 2020 Bond Planning meeting on April 11th

Capital Project Update

Thanks to the forty community members who joined us on April 11th for our second virtual community meeting in our public engagement to determine how to spend the $6 million of 2020 Health & Recovery Bond funding that was designated for capital improve...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 13, 2023

Nancy Pelosi Secures $3 Million in Funding for Japantown Peace Plaza

Capital Project Update

On Wednesday, Speaker Emerita Nancy Pelosi announced that she had secured $3 million in federal funding for the Japantown Peace Plaza Renovation Project, which will install new paving, plantings, informal seating and more. 

The Peace Plaza is an i...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 12, 2023

Design for Improved Jackson Park Moves Forward

Capital Project Update

SAN FRANCISCO, CA – A new playground, sports viewing areas, community learning gardens and an outdoor ball court are among the features included in the Jackson Park concept design approved Thursday by the San Francisco Recreation and Park Commiss...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 7, 2023

Twin Peaks Improvement Project | Virtual Community Meeting on April 25, 6 pm

Capital Project Update

Please join us for an update on the Twin Peaks Improvement Project. We will be providing you with the latest information about the upcoming project. We hope you can join us!

Tuesday, April 25, at 6:00pm

Join Zoom Meeting: https://bit.ly/twinpeaksmtg42523

Mee...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 4, 2023

Herz Recreation Center Project update | April 2023

Capital Project Update

Herz Recreation Center is out to bid! Bids are due on May 17, 2023 at 2:30 pm PDT. 

Please see links below for more information including the pre-bid meeting, bid documents, requirements and more:

Alexi...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 3, 2023

UPDATED! - Buchanan Mall Equity in Action April Gatherings

Capital Project Update

Buchanan Street Mall - Equity in Action 

April Happenings: Coming this month to the Buchanan Mall Community 

Wednesday April 5, 2023 -- CANCELLED -- NO COMMUNITY GATHERING ON WEDNESDAY, APRIL 5.

Stay tuned! A survey and ac...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 24, 2023

McLaren Trails design is underway! Virtual meeting, 4/11 at 6pm

Capital Project Update

We have been working on environmental compliance for the McLaren Trails project, which is complicated, as most of the trail work falls within natural resource management areas and under that Environmental Impact Report (EIR) for the Natural Resources Mana...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 23, 2023

Virtual Community Meeting, April 11 | McLaren 2020 Bond – Possible Projects and Priorities

Capital Project Update

McLaren 2020 Bond – Possible Projects and Priorities

Virtual Community Meeting

April 11th, at 6:00 pm

Join Zoom Meeting

https://bit.ly/mclarenmtg41123

Meeting ID: 861 9658 9635     Passcode: 386700

Dial in: 669.900.6833

The project team will sh...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 23, 2023

Buchanan Mall Equity in Action April Gatherings!

Capital Project Update

April Buchanan Street Mall - Equity Action Gatherings

Coming this month to the Buchanan Mall Community 

Wednesday April 5, 2023 -- CANCELLED -- NO COMMUNITY GATHERING ON WEDNESDAY, APRIL 5.

Stay tuned! A survey and activities are being plan...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 21, 2023

Gene Friend Recreation Center update | March 2023

Capital Project Update

The Gene Friend Recreation Center project represents the wholescale construction of a brand-new facility. Currently, the project team is working on implementing the Construction Manager/General Contractor (CM/GC) contract mechanism, where the contractor t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 20, 2023

Waller Street Skate Park Project | Project Complete! Now open!

Capital Project Update

Hello neighbors! Waller Street Skate Park is now open, and we hope you get out there and enjoy it! Check out the photos below from the ceremonial ribbon cutting we hosted in October 2022. 

This will be our last blog update for the project. If you ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 20, 2023

Stow Lake Perimeter Path Renovation | update March 2023

Capital Project Update

Hi neighbors! As a quick update on the Stow Lake Perimeter Path Renovation, construction is moving faster than anticipated. We are nearly finished with the first half of the project, we should be repositioning the fencing and starting the second half of t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 20, 2023

San Francisco Marina Improvement and Remediation Project | Survey + Community Meeting Presentation

Capital Project Update

Thank you to everyone who took part in our first two community meetings this month!

These presentations were intended to introduce the community to the project and provide an opportunity for everyone to provide feedback to the project team. You can find ou...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 20, 2023

Stern Grove Playground Renovation | March 2023 update

Capital Project Update

Hi neighbors! As a quick update on the Stern Grove Playground Renovation, we are making some refinements to the final concept design, while continuing regulatory and construction bid preparation. We are on target to begin construction work within the next...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 20, 2023

Lake Merced Project update | March 2023

Capital Project Update

Hi neighbors! As a quick update, the upcoming Lake Merced project, which involves renovation of pathways and other site improvements, is undergoing preparation to take construction bids. This involves reviewing regulatory and permitting work, as well as a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 17, 2023

Noe Valley Town Square Restroom Project Update

Capital Project Update

The project will go to the Board of Supervisors at the end of March 2023. Upon approval, the project will proceed with construction drawings to integrate the prefabricated restroom into the existing site.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 17, 2023

Community Gathering on March 22 | Buchanan Street Mall – Park Improvement Equity Action Initiative

Capital Project Update

Buchanan Street Mall Gathering

Join Us for the Next Community Healing Circle

Be a part of the conversation on healing & transformation in our community.

March 22nd 5:30-8pm (dinner from 5:30-6pm)

Rosa Parks Senior Center, 1111 Buchanan Street SF CA 94115

H...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 16, 2023

Yosemite Creek Daylighting Project Update | March 2023

Capital Project Update

Dear Neighbor,

In partnership with the San Francisco Municipal Transportation Agency and San Francisco Recreation & Parks Department, we are excited to share this project update for March 2023 (PDF). 

You can also check out this updated Upper Y...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 15, 2023

Merced Heights Playground Lower Lawn Terrace | Construction Nearing Completion

Capital Project Update

Thank you for your patience through some project delays, first due to bird nesting and, more recently, due to all this rain! 

The contractor should be reaching substantial completion on the project within the next 1-2 weeks. A portion of the curb ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 13, 2023

Japantown Peace Plaza Renovation | Upcoming Opportunities to Provide Public Comment

Capital Project Update

Hello neighbors!

We wanted to share that there are a few upcoming opportunities to provide input into the Japantown Peace Plaza Renovation:

1) San Francisco Arts Commission’s Civic Design Review for Phase 2 & 3 will be taking place on Monday, March 20, ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 10, 2023

Lafayette Park Lighting Improvements Update | March 2023

Capital Project Update

All foundation work is now completed! The last light pole foundations were installed late February and the bollard light foundations in front of the restroom were installed earlier this week. These concrete ‘bases’ take about a month to cure before the th...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 9, 2023

Esprit Park Renovation | Presentation from March 8 Community Update now available

Capital Project Update

Thanks to all of the community members who joined us last night for an update on the renovation of Esprit Park.

Please click here for last night’s presentation (PDF). This presentation is also available in the "Documents and Materials" tab of the...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 8, 2023

RPD Capital and Planning Team wins three awards at the 5th Annual SF Collaborative Partnering Awards

Capital Project Update

At the end of January, the SF Collaborative Partnering Steering Committee hosted its annual Collaborative Partnering Awards event to recognize project teams in San Francisco departments who demonstrate excellence in collaboration and the application of pa...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 8, 2023

SF Rec and Park Commission Meeting at Joe Lee Rec Center | March 16 at 10 a.m.

Capital Project Update

Come meet your Recreation and Park Commissioners at our offsite Commission meeting at Joe Lee Rec Center!

March 16, 2023 | 10 a.m. | Joe Lee Recreation Center, 1598 Oakdale Avenue, San Francisco, CA 94124

Agenda and meeting info can be found at sfrecpark.or...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 8, 2023

Upcoming Opportunity to Provide Public Comment for 11th and Natoma Park Project | March 20 at 2 pm

Capital Project Update

Phase 1 of the San Francisco Arts Commission’s Civic Design Review for the 11th and Natoma Park Project will be taking place on Monday, March 20th at 2:00 PM. Any member of the public is welcome to attend the meeting and provide public comment. We will be...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 7, 2023

Golden Gate Park - Golf Clubhouse construction update | March 2023

Capital Project Update

We're happy to report that the Golden Gate Park Golf Clubhouse project has received its building permit and construction is underway. The contractor has recently installed the underground plumbing for the new clubhouse and over the next few weeks will be ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 7, 2023

Golden Gate Park – 9th and Lincoln Gateway Project Update | March 2023

Capital Project Update

The 9th Avenue Gateway is moving forward and is scheduled to be advertised for bids in April! If the city receives acceptable bids, we can expect the project to break ground in early summer for an estimated eight month construction timeline. Traffic and t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 7, 2023

11th and Natoma Park Project Update | March 2023

Capital Project Update

Thank you to everyone who has taken part in the development of the 11th and Natoma concept design! At a recent fourth community meeting a final concept design was presented and discussed. The concept has been developed over a significant outreach process ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 6, 2023

Buchanan Street Mall – Park Improvement Equity Action Initiative: First Community Gathering on 3/15

Capital Project Update

Help shape the future of the Fillmore! Your participation is key for redesigning Buchanan Street Mall to strengthen the neighborhood, create economic opportunity, and improve health and wellness for everyone.

Come to our first community gathering to circle...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 6, 2023

Esprit Park Renovation Reminder: March 8 Online Community Update

Capital Project Update

A reminder to please join us for an online community meeting update hosted by Rec and Park. We will provide updates on project progress and dedicate at least half of the meeting to questions and answers. If you’re unable to make this meeting time, please ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 1, 2023

Herz Playground – Construction Update | March 2023

Capital Project Update

Even with these heavy winter rains, we continue to make progress at Herz Playground. The new sewer lines that serve the clubhouse, restrooms, and site drainage are in, and the rough plumbing for the restroom renovation is complete. As we uncover old plumb...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 28, 2023

Japantown Peace Plaza Project Update | Feb 28, 2023, 6:30 PM - 7:30 PM

Capital Project Update

Join us for an update on the renovation, being presented at a Community Briefing hosted by Japantown Task Force.

February 28, 2023 at 6:30-7:30 PM via Zoom. 

Learn more and register at: https://peaceplaza.org/

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 27, 2023

People want a Promenade | McLaren Park - John Shelley Drive

Capital Project Update

Thanks to the 40 people who attended the virtual community meeting on February 23rd!

We discussed the creation of a permanent promenade along John Shelley Drive West, and possible traffic calming and pedestrian and bicycle safety improvements along Shelley...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 24, 2023

Louis Sutter Playground update | February 2023

Capital Project Update

Construction is underway south of Louis Sutter Playground! We are removing a failing pathway and grading the hillside to achieve an easy slope from the parking lot to the existing path between Dwight and the Hidden Bridges. This is the first segment of a ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 23, 2023

Fillmore Turk Mini Park update | February 2023

Capital Project Update

Hello neighbors! The site is transforming before our very eyes! Construction is fully underway with demolition almost completed (light poles are gone!) and subsurface drainage is being installed. The big mound of concrete seen in the panoramic photo below...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 23, 2023

Twin Peaks Pedestrian Walkway update | February 2023

Capital Project Update

Hello neighbors! As you may know, the Twin Peaks Pedestrian Walkway project will convert the eastern roadway into a linear park. At this early stage, we continue to refine design elements such as overlooks, benches, multi-use features, bicycle racks, inte...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 22, 2023

Upcoming community meetings for San Francisco Marina Improvement and Remediation Project

Capital Project Update

Community meetings for San Francisco Marina Improvement and Remediation Project

Please join us for our first two community meetings to discuss the future of the San Francisco Marina. 

Session 1: Saturday, March 11 from 10:30am to 11:30am

Se...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 17, 2023

Herz Recreation Center Project update | February 2023

Capital Project Update

Hi all, We are finalizing our bid set of documents for the Herz Recreation Center Project. We hope to advertise it to contractors in the coming weeks. We will share an update as soon as the bid solicitation is available online. Contact Project Manager, Al...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 16, 2023

Stern Grove Playground Renovation | February 2023 update

Capital Project Update

Hello everyone! We are wrapping up our construction documentation for the playground renovation at Stern Grove. We aim to get permits in March. For questions please contact Project Manager, Steve Tucker, at steven.tucker@sfgov.org.

Approved concept design....

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 13, 2023

Stow Lake Path Project Update - 2/13/2023

Capital Project Update

Hey Neighbors! We are happy to report that the first quarter of the Stow Lake Perimeter Path Renovation is now complete – ahead of schedule! Our contractor is now moving into the next phase. Preparation for this work has begun. This work will include ligh...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 9, 2023

Esprit Park - March 8 Online Community Update and Construction Progress

Capital Project Update

Save the Date for an online community meeting update hosted by Rec and Park

Wednesday, March 8

6:00 pm – 7:00 pm

Zoom Link: https://bit.ly/espritmarch8mtg

Meeting ID 889 9042 2696#

Passcode: 156715 

Dial in: 669.444.9171

The Contractor has mobilized and...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 1, 2023

Construction Progress for Merced Heights Playground Lower Lawn Terrace

Capital Project Update

Trees and plants are in the ground and contractor will be completing installation of mulch by early next week. 

The sod lawn is also installed.

We’ll be keeping the lowest terrace closed for a couple more months, to allow the lawn and plants to tak...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 1, 2023

Lake Merced Project Preparing Bid Documents!

Capital Project Update

We are happy to report that the project team is in the process of preparing for the project to go out to bid. We will keep you updated as to when the project will be going into construction. Watch for signs to appear around the Lake, informing you of clos...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 24, 2023

11th and Natoma New Park Project Virtual Community Meeting #4

Capital Project Update

Please join us for our fourth community meeting to discuss the future park at 11th and Natoma!  Recreation and Parks invites you to attend a presentation of the concept design, which has been developed through community input and includes many of...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 23, 2023

Crocker Amazon Fields Project Update 1/23!

Capital Project Update

The fencing work for this project was completed in August 2022 and the contract for the Field Replacement portion of this project has been awarded to Minerva Construction.  We plan to start construction in March 2023 and work will be completed by...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 23, 2023

South Sunset Clubhouse Project Update 1/23!

Capital Project Update

The Public Works design team is developing a concept plan for the renovations at the Clubhouse that will be shared with the community at a public meeting to be held later this winter.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 20, 2023

John Shelley Drive in McLaren Park – Virtual Community Meeting

Capital Project Update

Please join us in discussing the future of John Shelley Drive, including a proposed car-free promenade segment on the Western portion of the road. Together we will review:

-             Extent ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 20, 2023

Buena Vista Improvements - Project Update 1/21!

Capital Project Update

Design Update

The Public Works design team in now engaged for this project and the topographic survey will be prepared by March 2023.  

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 20, 2023

Esprit Park Fencing to Go Up Week of Jan 23rd!

Capital Project Update

We are excited to announce that, following January 19 Notice to Proceed (NTP) and January 20 groundbreaking ceremony, the contractor will be mobilizing the week of January 23.

We expect perimeter fencing to be installed around the park as early as Tuesday,...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 20, 2023

Ocean Beach Climate Change Adaptation Project Update 1/20!

Capital Project Update

Design Update : The design team is finalizing the 95% Construction Documents and Rec Park will be conducting a thorough review as this project progresses.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 20, 2023

Herz Recreation Center Project Update 1/20!

Capital Project Update

Hi everyone, We are thrilled to share that we obtained our building permit for the Herz Recreation Center Project! We are aiming to bid the project to potential contractors in February. Stay tuned for updates. We will announce once the project is advertis...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 9, 2023

Esprit Park Renovation Groundbreaking Event and Construction Start!

Capital Project Update

We are excited to announce that we have a Notice to Proceed (NTP) date for the construction contract for the Esprit Park Renovation Project.

NTP date is January 19.

Please join us  groundbreaking ceremony at the park on Friday, January 20, at 1 pm ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 23, 2022

Lafayette Park Lighting Improvements Update- 12/22/22

Capital Project Update

Much has happened in the park these past two months!

The main path was blocked during the weekdays in Nov while the construction crew potholed, trenched, and laid conduits and backfilled the area parallel to the main path- Although easy to peer over the ba...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 22, 2022

GGP Golf Clubhouse Construction Update 12/22!

Capital Project Update

Now that the temporary facilities are up and running, the contractor has started to prepare the site for the construction of the new Golf Clubhouse.  They have started the demolition of the foundation of the previous clubhouse.  Over the...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 22, 2022

Merced Heights Playground Lower Lawn Terrace Construction Update

Capital Project Update

Construction is progressing and the lower terrace of Merced Heights Playground is starting to look like a park!

Concrete plaza and pathways within the park are poured and the dog play area is installed. Irrigation and drainage improvements have also been m...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 22, 2022

Esprit Park Renovation Update 12/22!

Capital Project Update

We are excited to announce that we completed a pre-construction planning meeting with the contractor this month and anticipate construction starting in early 2023.  Please stay tuned for more details soon after the New Year, including invitation ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 22, 2022

Updates Related to the New Gene Friend Recreation Center

Capital Project Update

Notice to Proceed for pre-construction services was awarded to Swinerton Builders just prior to Thanksgiving, and they have hit the ground running, working with the design team to review documents and start cost estimating and constructability. As a remin...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 20, 2022

McLaren Park Improvement Projects Update 12/20/22!

Capital Project Update

Thank you to everyone who participated in our community meeting on December 6th. We appreciated hearing feedback on top priorities for investing the 2020 Bond funding in McLaren Park. We look forward to returning to the community in Spring 2023 to present...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 20, 2022

Herz Rec Project Update 12/20/22

Capital Project Update

Hi folks, We enjoyed celebrating a joint groundbreaking for the new Community Center with our project partners Mercy Housing, Related CA, the Boys & Girls Club and Wu Yee Children’s Services in early December. We are very close to finalizing our build...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 19, 2022

Twin Peaks Pedestrian Walkway and Trail Improvement Project is Making Progress on Design

Capital Project Update

Over the last several months we’ve been working on construction documents for the three remaining trail segments slated for renovation: the trail up and over Noe Peak, the switch back trail south of Noe Peak, and the trail to Crestline Drive. We are still...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 19, 2022

Herz Playground – Construction Demolition Almost Complete!

Capital Project Update

Treaty Construction is busy at work with their backhoe! Demolition is nearly complete at Herz Playground. At least 75% of materials being disposed of are sorted, reused, or recycled in compliance with San Francisco’s Recovery Plan. The playground sand was...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 6, 2022

San Francisco Breaks Ground on New Community & Recreation Center at Sunnydale Hope SF

Capital Project Update

Contact: Mayor’s Office of Communications, mayorspressoffice@sfgov.org   

San Francisco, CA — Today, Mayor London Breed joined community leaders to celebrate the groundbreaking of the Sunnydale Community Hub, a joint development comprised...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 1, 2022

McLaren Park Trails Project Presentation to Commission on 12/7!

Capital Project Update

The final draft conceptual design for the McLaren Trails Priority Improvements project will be presented to the Recreation and Parks Capital Committee next Wednesday 12/7 at 2pm. Connection details are at the bottom of this post.

A summary of the project s...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 1, 2022

Fillmore Turk Construction Groundbreaking, CANCELLED!

Capital Project Update

Fillmore Turk Renovation starts 12/12/22 with construction fence installation and the contractor prepares the site for demolition. 

Thank you to all who have helped us get to this point!

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 29, 2022

McLaren Park Improvement Projects Community Meeting December 6th online!

Capital Project Update

Due to expected rain, the McLaren Park Project Improvements meeting on December 3rd will now be held virtually on December 6th. See information below.

Join us to share ideas and prioritize park improvements!

We are seeking input on how to invest the 2020 He...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 22, 2022

Golden Gate Park Golf Clubhouse Construction Update 11/22!

Capital Project Update

The Construction of the new Golden Gate Park Golf Clubhouse is getting underway! The Notice to Proceed was issued to the Contractor in late September. The contractor has mobilized on the site, and set up the temporary golf clubhouse, which First Tee will ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 17, 2022

11th and Natoma New Park Project Virtual Community Meeting

Capital Project Update

Please join us for a third community meeting to discuss the future park at 11th and Natoma! Recreation and Parks invites you to attend for a presentation of a consolidated concept design for the park based on the community input to date. This is another o...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 10, 2022

McLaren Park Improvement Projects Community Meeting December 6th online!

Capital Project Update

Join us in person to share ideas and prioritize park improvements!

We are seeking input on how to invest the 2020 Health & Recovery Bond funding in McLaren Park. Staff will be presenting preliminary project ideas to gather community feedback.

Tuesday, D...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 27, 2022

Twin Peaks Project Update 10/27/22!

Capital Project Update

Our design team at Public Works is busy at work developing details for the renovation of trails. We’re focused on the three remaining trails to be renovated: 1.) the trail up and over the south peak, 2.) the trail south of the peaks that connects to the c...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 26, 2022

McLaren Park Vision Plan Update 10/26!

Capital Project Update

Hi everyone-

We are busy behind the scenes preparing to host a community meeting later this year. Stay tuned for announcement on the date/time. We will be discussing potential project ideas to receive funding from the 2020 Health & Recovery Bond. For q...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 26, 2022

Herz Recreation Center Update 10/26/22

Capital Project Update

Hi all- We are excited to share that the children’s playground at Herz is now in construction! The recreation center project is still moving along in the design and permitting phase. We hope to share an updated schedule soon. Please reach out to Project M...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 25, 2022

SF City leaders, families celebrate groundbreaking of improvement project at Herz Playground

Herz Groundbreaking

SAN FRANCISCO — The San Francisco Recreation and Park Department broke ground on renovations at Herz Playground in Visitacion Valley on Monday as part of the Let’sPlaySF! initiative that is delivering creative play spaces to children across San F...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 20, 2022

Herz Playground Groundbreaking Celebration October 24th!

Capital Project Update

Save the date! Please join, Monday, October 24 from 4:30-5:30, in celebration of the much-anticipated renovation of Herz Playground. Come share a memory and look forward to the revitalization of the neighborhood park. The builders are set to mobi...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 20, 2022

Middle Lake Rehabilitation Project Update October 2022!

Capital Project Update

The rehabilitation project received a low bid from Bauman Landscape and Construction Inc. which will be presented to the RP Commission for approval on 10/20. With approval from the Commission we plan to move forward with the tree removals (the first part ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 20, 2022

Commission and Permitting and Construction for Esprit

Capital Project Update

The Recreation and Park Commission has approved the construction contract, and we are working to get our contractor started as soon as possible.

We have posted “Construction Coming” advisories at the park.

Please stay tuned for updates as we have them on co...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 12, 2022

Presentation of the McLaren Trails final draft plans, Monday 10/17/2022 at 6:30pm

Capital Project Update

Thanks to everyone who attended trail walks or otherwise shared dialogue with staff this summer, as we continue to refine the concept design for priority trail improvements and enhancement of natural features in McLaren Park.

You can click these links to r...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 6, 2022

Merced Heights Playground Lower Lawn Terrace Construction Update

Capital Project Update

You may have noticed a pause in construction recently. Work stopped as we discovered some infrastructure below ground that we had not anticipated. 

The landscape architect has issued updated direction to the contractor, who has been back on site a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 6, 2022

Fillmore Turk Mini Park Update- 10/05/22

Capital Project Update

We are excited to report that the construction contractor is currently being certified after receiving Commission approval to award. In preparation,  tree removal notices were posted last week.

Stay tune for a ground breaking event before year end...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 6, 2022

Lafayette Park Lighting Improvements Update- 10/05/22

Capital Project Update

Construction will start this Fall 2023 through Early 2023 (target mid October -mid February). See attached construction advisory notices with site map that was installed throughout the park mid Sept.. 

The construction will be confined to the dash...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 29, 2022

India Basin - City Breaks Ground on New Waterfront Park

Capital Project Update

Together with community members who shaped the historic project from its conception, San Francisco officials broke ground last month on the future India Basin Waterfront Park.

The groundbreaking ceremony marks the beginning of construction of the future pa...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: September 20, 2022

Japantown Peace Plaza Project Update, Sept 2022

Capital Project Update

September 20, 2022 at 6:30-7:30 PM via Zoom

The Japantown Task Force is hosting a virtual Community Briefing on the Peace Plaza Renovation Proje...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: September 19, 2022

Waller Street Skate Park Project Construction Update 9/19!

Capital Project Update

2 inches of fine asphalt was laid during the last week of August. After the asphalt cured, the Sportsmaster Skatemaster system was applied; first with a layer of acrylic then later with a sealant atop. The project will look to develop the adjacent landsca...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 16, 2022

Herz Rec Construction Update 9/16!

Capital Project Update

Hi everyone- We are making steady progress on having our construction documents reviewed by the Department of Building Inspection and other City agencies.

Construction has begun adjacent to the park on the new Community Center, which will be home to the lo...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 16, 2022

McLaren Park Vision Plan Update 9/16!

Capital Project Update

Hi all-

We are looking forwarding to meeting with the community this Fall to discuss project ideas for investing the 2020 Bond funding. Also, the golf operator at Gleneagles Golf Course will be ending their lease Fall 2023. We have the opportunity to re-im...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 15, 2022

Merced Heights Playground Lower Lawn Terrace Construction Update

Capital Project Update

You may have noticed a pause in construction recently. Work stopped as we discovered some infrastructure below ground that we had not anticipated. 

The landscape architect has issued updated direction to the contractor, who is back on site this we...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 14, 2022

Stow Lake Pathway Improvement Project Update 9/6/22!

Capital Project Update

Hi all- We are pleased to report that on August 18, the RPD Commission approved the contract award for the construction of Stow Lake. Pre-construction coordination will begin at the end of September with an anticipated construction start date of early Oct...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 12, 2022

Preparing for Tree Work at Esprit Park

Capital Project Update

Rec and Park is coordinating with the Public Works Bureau of Urban Forestry (BUF) to notice community members about upcoming tree work at Esprit, as part of a wholescale renovation of the park. BUF will be posting trees within the right of way proposed fo...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 7, 2022

Middle Lake Rehabilitation Project Update September 2022!

Capital Project Update

The rehabilitation project was advertised for bids last month and, because of the complexity of the project, the bid due date was extended to today, 9/7/2022. The bidding contractors will be named shortly. Assuming a low bid is received within range of th...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 7, 2022

Golden Gate Park – 9th and Lincoln Gateway Project Update September 2022!

Capital Project Update

The design team is closing in on 100% completion of the construction documents and the project will soon be advertised for bids. The project is on track to begin construction in early 2023 for an 8 month construction duration. Rec and Parks will coordinat...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 6, 2022

Ocean Beach Climate Change Adaptation Project Art Proposals are posted!

Capital Project Update

Ocean Beach Climate Change Adaptation Project Art Proposals are posted! The three finalists are Mark Baugh-Sasaki, Leo Bersamina, and Ana Teresa Fernandez. One of these art proposals will be selected for construction and installation. Public comment on th...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 2, 2022

Great Highway Pilot Project Legislation

Capital Project Update

This Fall 2022, the San Francisco Board of Supervisors will consider legislation that will authorize a three-year pilot study using the Upper Great Highway between Lincoln Way and Sloat Boulevard as a car-free promenade on weekends, holidays, and Friday a...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: September 1, 2022

Esprit Commission Presentation Sept 7!

Capital Project Update

Staff have worked with Public Works Contract Administration and the City’s Contract Monitoring Division to confirm responsiveness of the low bid contractor, Bauman Landscape and Construction, Inc.  Staff will present award of construction contrac...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 24, 2022

Contract Awarded for Herz Playground Construction

Capital Project Update

On August 18, 2022, Commission approved that Treaty Construction be awarded the contract to renovate Herz Playground. Not only was Treaty the lowest, responsive bidder, we’ve had great success working with them in the past. Treaty Construction has built s...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 24, 2022

Herz Recreation Center Update 8/24!

Capital Project Update

Hi all- We are closing to wrapping up the permitting review through the Department of Building Inspection! Once this is finalized we will be ready to move into the bid phase.  E-mail Project Manager, Alexis Ward, at alexis.ward@sfgov.org for ques...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 24, 2022

Twin Peaks Pedestrian Walkway and Trail Improvement Project Receives Construction Funding

Capital Project Update

Earlier this season Twin Peaks was awarded $500K from the State Coastal Conservancy (SCC), Priority Conservation Area Grant (PCA). That coupled with $1MIL from the SF 2020 Health & Safety Bond, set our design team in motion planning for the restoratio...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 17, 2022

Richmond Playground Construction Update 8/17.

Capital Project Update

We’re almost at 100% completion of the construction drawings, which is a big milestone! We are on target for mid-winter to start construction, which we’ve estimated at an 8 month duration, and we should expect the playground to be open to the public aroun...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 17, 2022

Esprit Project Update Presentation and Commission Award of Construction Contract

Capital Project Update

Thanks to the nearly 30 people who attended and participated in yesterday evening’s online community meeting update. Please click here to view the presentation from last night. In addition, please click here to find the Materials Plan from the bid set, wh...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 12, 2022

India Basin - Contractor Approved to Build New Waterfront Park

Capital Project Update

The San Francisco Recreation and Park Commission last month approved construction firm Swinerton to build the first portion of India Basin Waterfront Park, a community-led project that will train and hire Bayview-Hunters Point residents.

Crews, which will ...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: August 2, 2022

Visitacion Avenue Pedestrian and Bicycle Safety Project, Site Walk 8/25 at 6pm

Capital Project Update

Please join Rec and Park and SFMTA staff for a site walk to review design options proposed for slowing traffic and improving pedestrian and bicycle safety and access along Visitacion Avenue.

Thursday 8/25/2022, 6-7:30pm 

Meet in front of Coffman Po...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 2, 2022

Lafayette Park Lighting Improvements Update- 07/29/22

Capital Project Update

The construction contract has been awarded!

It was a journey through design, pandemic challenges to get us to this point. The contractor has ordered the lights (four month to manufacture) and our team held multiple meetings to prepare for construction some...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 2, 2022

Community Opportunity Fund Update - 07/29/22

Capital Project Update

Thank you, neighborhood park advocates, for your continued support of the Community Opportunity Fund Program, which is in its third Bond cycle. We are updating the process for the next application cycle, Round 6, and will have more information on those ch...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 27, 2022

LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING.

Capital Project Update

LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING. 

The meeting will be at 1981 Sutter St, San Francisco, CA 94115

The Buchanan Street Mall project team is hosting our first community meeting for the Memory Walk on Wednesday 7/27, 5-7pm ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 27, 2022

Esprit Park Renovation Project Virtual Community Meeting August 16th!

Capital Project Update

We are hosting an online meeting on August 16 to update community members on project progress and answer questions.  

Please join us!

Tuesday, August 16, 6:00-7:00 pm

Here is the link to join the Zoom meeting: https://bit.ly/espritaug2022 

M...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 20, 2022

Gene Friend Rec Center Project Update 7/20/22

Capital Project Update

The design team is up and running and working on completing schematic design by later this Summer. Please stay tuned for details on design updates.

We have issued Notification of Intent to Award to Swinerton Builders for the Construction Manager / General ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 18, 2022

India Basin - Water Barrier Removed

Capital Project Update

We are excited to share that the water barrier has been removed at 900 Innes, a huge step in completing the remediation of this site that allows water to return to the cleaned area. We have additional work to wrap-up the project and anticipate finishing r...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: July 14, 2022

Sidewalk Work at Merced Heights Playground.

Capital Project Update

Today our contractor began work demolishing sections of the sidewalk along Byxbee, from the main playground entrance to the corner of Byxbee and Shields Streets.

Please note that the contractor is currently providing temporary pedestrian access around this...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 14, 2022

Sanjay Vora selected for the Herz Rec Center Public Art Piece!

Capital Project Update

Hi everyone- We are thrilled to share that Sanjay Vora has been selected as the artist for the public art piece at the new Herz Recreation Center! You can review his proposal under the Documents tab. Please contact Rec Park Project Manager, Alexis Ward, a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 13, 2022

Thank you for attending the Buena Vista Park Improvement Project Meeting!

Capital Project Update

Thank you to all those who attended the July 12, 2022 Community Meeting. With over 50 people in attendance, we finalized the project scope to include improving the pathways throughout the park.  The meeting presentation is available by c...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 12, 2022

Memory Walk Design at Buchanan Street Mall - Community Meeting

Capital Project Update

Core to the community-driven redesign of Buchanan Street Mall, the Memory Walk is envisioned to physically connect all five blocks of the park, showcase local art, and honor community history.

Thanks to grant funding from the Prop 68 Statewide Parks Progra...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 12, 2022

Esprit Park Renovation Project is Out to Bid!

Capital Project Update

The Esprit Park Renovation Project is out to bid! The solicitation and supporting documents can be found by clicking here.

Bids are due July 27!  Pending receipt and confirmation of a bid we can afford, from a contractor team that meets the requir...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 6, 2022

Bids received for Herz Playground Construction!

Capital Project Update

Hi everybody- We have great news to share- we received 7 bids on the Herz Playground Renovation Project! We are currently identifying the lowest, responsive bidder. We plan to present the contract award for construction to the Recreation and Park Departme...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 6, 2022

Art finalists for Herz Rec Center!

Capital Project Update

Hi all- Thank you to those who provided input the proposed artwork for the Herz Recreation Center. Arts Commission staff will soon be making a final recommendation on the selected artist. To review the three finalists’ proposal click here. The project tea...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 1, 2022

Twin Peaks Pedestrian Walkway Commission Approval and Project Manager Transition

Capital Project Update

The Twin Peaks Pedestrian Walkway conceptual design was approved by the Recreation and Park Commission in June 2022!

Design aspects that will be addressed and refined during schematic design and onward, some of which is based on input from community stakeh...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 1, 2022

Construction Updates for Merced Heights Lower Lawn Area!

Capital Project Update

We are excited to report that, as of early June, the contractor’s certified consulting biologist has confirmed that bird nesting activity on site has been completed.  Thank you for your patience as we waited for the eggs to hatch and the baby bir...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 29, 2022

Trail walks in McLaren Park 6/29 and 7/14

Capital Project Update

Recreation & Parks is hosting two trail walks to share proposed priority trail improvements, highlight natural resources, and hear park user suggestions for signage that will help people navigate and appreciate McLaren Park. We will also discuss propo...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 29, 2022

11th and Natoma Street New Park Project Meeting #2

Capital Project Update

Please join us for a second virtual community meeting to discuss the future park at 11th and Natoma! Recreation and Parks invites you to attend and share your input on the design, character, and programming of this exciting new park site in the South of M...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 27, 2022

Buena Vista Park Improvement Project Virtual Community Meeting July 12th!

Capital Project Update

Please join us for a virtual community meeting to review the findings of the 2020 Buena Vista Park Needs Assessment and Cost Analysis and finalize the scope of the improvements to be funded with three million dollars from the 2020 Health & Recovery Bo...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 13, 2022

McLaren Trails Project Walk POSTPONED for the June 14th event

Capital Project Update

We apologize for the inconvenience as our Project Manager is out sick. We will be postponing the June 14th 8:30 am site walk, but will still be moving forward with the 29th. We will reschedule as soon as possible.

Thanks for your continued interest in McLa...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 3, 2022

Esprit Park Project Update 6/2!

Capital Project Update

We are happy to report that 100% bid documents have been submitted by the design team and shared with the Public Works Contract Preparation group, to prepare for advertisement to contractors. 

The set of drawings and specifications that comprise t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 3, 2022

Trail Walks in McLaren Park, June 14th (Postponed) and June 29th!

Capital Project Update

Kickoff summer with some time out in nature and join us for one or two upcoming walks through McLaren Park!  

Our McLaren Trails project team will be sharing proposed priority trail improvements in four areas of the park, as identified in the 2017...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 24, 2022

11th and Natoma New Park Survey Closing Soon!

Capital Project Update

Are you interested in the future of the 11th and Natoma park property? Take our 11th and Natoma park survey! We’ve extended the deadline and the survey will be open until May 25th. The survey is available online at: https://forms.gle/vMz5viNaZhARF8qH8. A ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 24, 2022

Twin Peaks Pedestrian Walkway Concept Design to Rec and Park Commission for Approval in June

Capital Project Update

Rec and Park is incorporating feedback we received from our online update and survey (Oct-Nov 2021) and moving forward presenting a conceptual plan for the pedestrian walkway to the Rec and Park Commission in June. Click here for the proposed concept desi...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 20, 2022

Contractor bids are due on Wednesday, May 25! for Herz Playground!

Capital Project Update

Hi all- We nearing the end of our advertisement period for Herz Playground! Contractor bids are due on Wednesday, May 25! We will update everyone on our schedule and the start of construction once bids are received. For questions on the project, please re...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 20, 2022

Herz Recreation Center Update 5/20!

Capital Project Update

Hi all- Thank you to those who provided input the proposed artwork for the Herz Recreation Center. The Selection Committee will be meeting in early June to review the community input and make a final recommendation to the Arts Commission. For questions on...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 18, 2022

Please take a short survey regarding Visitacion Avenue Pedestrian and Streetscape Improvements

Capital Project Update

Please take a moment to fill out a survey about improvements you would like to see made on Visatacion Avenue no later than June 20th, 2022.

Click the link here to begin. https://bit.ly/Visitacion-Ave-Survey

Please look for surveys in other languages at the ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 3, 2022

11th and Natoma New Park Survey!

Capital Project Update

Please take a brief survey to help shape the design of this new Park in Western South of Market (SoMa) area. The survey will close on May 18th, 2022.

https://forms.gle/kxpT4RnuRvsYEThbA

Thanks so much!

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 2, 2022

Upcoming Opportunity to Provide Public Comment for Ocean Beach Project

Capital Project Update

Phase 2 of the San Francisco Arts Commission’s Civic Design Review for the Ocean Beach Climate Change Adaptation Project will be taking place on Monday, May 16th at 2:00 PM.  Any member of the public is welcome to attend the meeting and provide p...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 2, 2022

Twin Peaks Project Update 5/2/22!

Capital Project Update

Thanks to the 698 people who completed our online survey in Fall 2021 regarding Twin Peaks Promenade design. We will share some highlights of information gleaned from the survey in our next update, in the coming weeks, as we move to finalize a concept des...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 28, 2022

Construction Has Begun on Merced Heights Lower Lawn Area!

Capital Project Update

We are excited to announce Notice to Proceed was  issued to the Contractor, Cazadoro Construction, Inc, on April 20. Here are some specific updates:

  1. We are working around a bird nest that has been identified by a certified biologist, per the surve...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 28, 2022

Esprit Park Project Update 4/28!

Capital Project Update

The design team is continuing to close design and coordination loops as efficiently as possible, still with the goal of finalizing construction documents and advertising to contractors this spring.

Here are some specific updates from this month:

  • SFPUC has p...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 26, 2022

Fillmore Turk Mini Park Project Update 04/26/22

Capital Project Update

The contractor asked to be relieved from the construction contract and in February, Commission approved the termination so that we can close this chapter and rebid the project to get back on track.

Contract termination does not happen very often and takes ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 25, 2022

Thank You for Joining Our April 20th Webinar!

Capital Project Update

On April 20, 2022 the Recreation & Park Department, San Francisco Public Utilities Commission and San Francisco Municipal Transportation Agency hosted a multi-agency, virtual community webinar to share status updates on the City’s Ocean Beach Climate ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 22, 2022

Japantown Peace Plaza April 2022 Update!

Capital Project Update

Bringing the vision plan to a buildable reality….

During the first quarter of 2022,  the project team addressed code issues, structure, the intricacies of access throughout the multi-level plaza, researched durable exterior materials for the highl...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 22, 2022

11th and Natoma New Park Project Virtual Meeting 5/3/22!

Capital Project Update

We are excited to announce an upcoming community meeting for a new park in the South of Market Area.

Recreation and Parks invites you to attend and provide your input on the character, programming, and design of this future park space.

Please join us for a ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 22, 2022

Herz Rec Art Proposals on Display, View them at Coffman Pool.

Capital Project Update

The Herz Recreation Center Artist Selection Panel has selected three artists to create proposals for artworks for the new Herz Recreation Center. The proposals are currently on display at Coffman Pool, 1700 Visitacion Avenue. Come visit and share your fee...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 22, 2022

Herz Playground Project is going out to bid!

Capital Project Update

Hi everyone- We will be advertising the Herz Playground Renovation Project this week. Please see below for a link to the bid documents. 

Public Works Bid Opportunities

City Partner

Contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org with ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 9, 2022

Visitacion Avenue Sidewalk & Streetscape Meeting Recap

Capital Project Update

Recreation and Park, together with the SFMTA, presented the first public meeting on the Visitacion Avenue Sidewalk and Streetscape Project. The project is part of the departments larger efforts to address pedestrian, bike and street improvements throughou...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 8, 2022

Mansell Tai Chi Court Open to the Public

Capital Project Update

Mansell Tai Chi Court is open to the public! A ceremony on 3/12/22 kicked off with a beautiful Tai Chi demonstration and marked the official opening for the space. The court is intended to serve the needs of Tai Chi practitioners, but the space has an end...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: April 8, 2022

Richmond Playground Project Update April 2022

Capital Project Update

Richmond Playground is moving forward! The project is at 60% design review and moving fast. We expect that the project will be advertised for bids by the fall 2022. 

Project Page RPD Park Improvements | All Project Updates
Posted on: April 8, 2022

Golden Gate Park Middle Lake Rehab Project Update April 2022

Capital Project Update

Middle Lake Rehabilitation is on track to go out to bid in April or May 2022. That means that the project could be in construction by the fall! Thank you everyone for your patience as this wonderful project progresses – the rehabilitation will create a be...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: April 1, 2022

Ocean Beach Climate Change Adaptation Project—Webinar on April 20

Capital Project Update

The San Francisco Public Utilities Commission, San Francisco Municipal Transportation Agency, and Recreation & Park Department will be holding a multi-agency, virtual community webinar to share status updates on the City’s Ocean Beach Climate Change A...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: March 28, 2022

Buchanan Mall stage preview and last call for the Phase 1 design refinement survey!

Capital Project Update

Design is progressing for the stage on the McAllister to Fulton block, thanks to the thoughtful input input provided by local performing art stakeholders, including the African American Art & Culture Complex, African-American Shakespeare Company, Afro...

Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: March 25, 2022

Gene Friend Rec Center Project Update 3/25

Capital Project Update

We are officially under contract with the architecture and engineering team, the Mark Cavagnero Associates + Kuth Ranieri Architects Joint Venture, as of March 23. We are looking forward to working with this team to finalize the project design and constru...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 25, 2022

Volunteers on Saturdays at the McLaren Native Plant Garden

Capital Project Update

Interested in helping improve our parks? Volunteer at the McLaren Park Native Plant Garden in Visitacion Valley on Saturdays from 10 a.m. to 12:30 p.m. The garden is located on Visitacion Avenue across from Herz Playground. Work will include moving mulch ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 23, 2022

Esprit Park Project Update 3/23/2022

Capital Project Update

The design team is continuing to close design and coordination loops as efficiently as possible, still with the goal of finalizing construction documents and advertising to contractors this spring.

Here are some examples of specific things we’re working th...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 18, 2022

Herz Rec Center Project Update March 2022

Capital Project Update

The project team and Rec Park staff continue to finalize details in the design of the new Rec Center and outdoor spaces. We are happy to announce that the public art proposals will be on display in the lobby of Coffman Pool in April. Community feedback on...

Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: March 18, 2022

Herz Playground Project Update March 2022

Capital Project Update

We have finalized structural engineering for the playground equipment and we aim to bring the construction documents to the Department of Building Inspection for permitting by April. Please contact Project Manager, Alexis Ward, at alexis.ward@sfg...

Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: March 18, 2022

Merced Heights - Notice to Proceed to Contractor in Early April 2022

Capital Project Update

We are excited to announce that we are on track to issue Notice to Proceed to the Contractor, Cazadoro Construction, Inc, by early April.  Here are some specific updates:

  1. There’s often a lag between when NTP is issued and when you observe work hap...
Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: March 18, 2022

Stow Lake Perimeter Path Project Update March 2022

Capital Project Update

Our biologist will conduct a few more wildlife surveys at Stow Lake over the next month. Once complete, we will incorporate measures into our specifications that ensure the protection of special status species during construction.  We are also co...

Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: February 24, 2022

Stow Lake Perimeter Path Project Update 2/23/2022

Capital Project Update

Hi folks- Our biologist has been conducting surveys of the wildlife at Stow Lake. Once the surveys wrap up later this Spring, we will be incorporating measures into our specifications to ensure the protection of special status species during construction....

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 24, 2022

Esprit Park Project Update 2/23/2022

Capital Project Update

The design team has completed and submitted 90% construction documents drawings and specifications.  These are currently being reviewed by several individuals and agencies for the following: accessibility, cost, tree impacts,  maintenanc...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 24, 2022

Herz Playground Project Update 2/23/2022

Capital Project Update

Hi folks- We have our final set of drawings and specifications ready for bidding! We are coordinating with the Public Works Contract Preparation group to advertise the project to potential contractors. We will also be taking the project to the Department ...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 24, 2022

Herz Recreation Center Project Update 2/23/2022

Capital Project Update

Hi folks- We are excited to share that the Board of Supervisors approved the grant/gift acceptance of $10 million from Sunnydale LLC! This funding is essential to completion of the new Recreation Center. Our design team has submitted the project drawings ...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 23, 2022

Buchanan Street Mall Phase 1 – Community Meeting on 2/24/2022

Capital Project Update

COMING SOON: Renovations on Buchanan Street Mall

It’s time to CELEBRATE! For seven years, the Western Addition community has dreamed about what Buchanan Mall could become with the right vision and resources. Those dreams are coming true!

With our p...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 14, 2022

Gene Friend Rec Center Project Updates

Capital Project Update

Here are some updates on the project:

 

  1. We are finalizing contracting with the architecture and engineering team, the Mark Cavagnero Associates + Kuth Ranieri Architects Joint Venture, and hope to officially have them on board by early Mar...
Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 14, 2022

Merced Heights - Award of Construction Goes Before RecPark Commission

Capital Project Update

We are happy to report that we will be presenting award of construction contract to the Recreation and Park Commission for approval this Thursday, February 17.

 

We received 10 bids from contractors on January 25.  We have confirmed the co...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 10, 2022

Public Art Opportunity at Ocean Beach!

Capital Project Update

The San Francisco Arts Commission invites artists and artist teams residing in the United States to submit qualifications for a public art opportunity at Ocean Beach in San Francisco. Proposals for this public art opportunity for the Ocean Beach Climate C...

Read on...

Visit the project page RPD Park Improvements | All Project Updates
Posted on: February 9, 2022

Trails update and Visitacion Ave Streetscape Meeting 2/10

Capital Project Update

The McLaren Trails Priority Improvements project team has been working with the Planning Department on environmental compliance, thoroughly reviewing the proposed trail improvements and natural features restoration work alongside the activities previously...

Read on...

Meeting Link RPD Park Improvements | All Project Updates
Posted on: January 31, 2022

Rossi Pool Project Update 1/31/22

Capital Project Update

Great news! The Rossi Pool Renovation project is nearly complete! The construction team is putting on the final touches, and everyone is eagerly awaiting the grand re-opening.

Recent construction activities include site and landscape planting, mechanical a...

Read on...

Back to the Project Page RPD Park Improvements | All Project Updates
Posted on: January 31, 2022

Yosemite Creek Daylighting Project Update January 2022

Capital Project Update

The Yosemite Creek Daylighting Project is moving forward following a number of Commission approvals.  On December 16, 2021 RPD Commission approved the 2018 concept design and draft MOU (Memorandum of Understanding) between RPD and PUC.  ...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: January 26, 2022

Lake Merced Joint City Agency Project Updates Meeting February 17th!

Capital Project Update

Please join Recreation and Parks, the Public Utilities Commission (PUC), and the Municipal Transportation Authority (MTA) for a virtual community meeting to get the latest updates on all the projects related to Lake Merced.

February 17th at 5:30 pm

Join via...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 25, 2022

McLaren Park Pedestrian, Bike and Streetscape Projects Community Meeting 2/10!

Capital Project Update

Please join us for a Virtual Community Meeting to discuss improvements to Visitación Ave in McLaren Park including new sidewalks, bike lanes, and traffic calming. We look forward to your feedback on the draft plan.

 February 10th at 5:30p...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 21, 2022

Bay View/KC Jones Playground Opening Celebration - Jan 2022

Capital Project Update

Please join us for a day of fun events:

2:30PM                Brief remarks and ribbon cutting

2:30-4PM             Free swimming a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 21, 2022

Herz Recreation Center Project Update 1/21/22!

Capital Project Update

Hi everybody- In February, are looking forward to presenting to the Board of Supervisors for a grant/gift acceptance of $10 million for the project! Additionally, the Arts Commission will be publicly displaying three proposals from artists for the public ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 21, 2022

Stow Lake Perimeter Path Project Update 1/21/22!

Capital Project Update

Hi all- We are anticipating having a biologist on-site in January and February to conduct wildlife surveys. We are still looking forward to bidding later this Spring! For questions, please reach out to Project Manager, Alexis Ward, at alexis.ward@sfgov.or...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 21, 2022

Herz Playground Project Update 1/22!

Capital Project Update

Hi everybody- We are putting the final touches on our permit set of drawings and we are planning to advertise the project to contractors in February. Stay tuned for more updates! Please e-mail Project Manager, Alexis Ward, at alexis.ward@sfgov.org with qu...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 7, 2022

Happy New Year rainbow over Francisco Park!

Capital Project Update

On January 5 we reached a major milestone moving closer to the park opening when permanent power went live at Francisco Park. Final work is being done on the Children’s Play Area and Community Garden.  During this time some final grading and plan...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 5, 2022

Japantown Peace Plaza Project Update January 2022

Capital Project Update

Happy New Year! This year we will bring the vision plan into a buildable reality.

2021 marked a year of investigations, structural testing, materials studies and confirming the permit codes with Department of Building Inspections (DBI) and work on the pago...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: December 23, 2021

Merced Heights Lower Terrace Project - Contractor Bid Advertisement!

Capital Project Update

We are happy to report that the project has been advertised to contractors!

Bids are due on January 25. If you know any contractors who may be interested in bidding on the project, please direct them to this page

Thanks to all who took our online...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 23, 2021

Bay View Playground Renovation, update 12/2021!

Capital Project Update

We're excited to announce that Bayview Playground is open! Thank you for your patience as we’ve worked to complete the renovation. Fences have been removed and the site is available for you to play. An official park opening will be on Jan 22, 2022. Stay t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 22, 2021

Fillmore Turk Mini Park Project Update 12/2021

Capital Project Update

Say goodbye to 2021 and to the drainage problems at Fillmore Turk—then, welcome the start of the transformative renovation taking place throughout 2022!

These Construction Advisory notices are posted on site in preparation for the upcoming renovation. Janu...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 17, 2021

Herz Recreation Center Project Update 12/17!

Capital Project Update

Hi everybody- Our project team is finalizing the structural design of the building and then we will submit for a Building Permit. The Arts Commission has selected three finalists who will create proposals for the public art piece at the new Rec Center. Th...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 17, 2021

Herz Playground Project Update 12/17!

Capital Project Update

Hi everybody- We have wrapped up our permit set of drawings and the next step is to have the drawings reviewed by the Building Department for approval. We hope to advertise the project to contractors early in 2022. Please e-mail Project Manager, Alexis Wa...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 17, 2021

Stow Lake Perimeter Path Project Update 12/17!

Capital Project Update

Hi all- We will be working with a biologist to conduct surveys around Stow Lake for red-legged frogs and to make recommendations on how to minimize any biological impacts. Once this is finalized, we will advertise the project to potential contractors. &am...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 9, 2021

Draft EIR for Ocean Beach Climate Change Adaptation Project Published

Capital Project Update

The San Francisco Planning Department has published the draft environmental impact report for the Ocean Beach Climate Change Adaptation Project. The Draft EIR is available for review at www.sfplanning.org/sfceqadocs, at the San Francisco Permit Center (49...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 29, 2021

Gene Friend Rec Project Architecture and Engineering Services Team Updates

Capital Project Update

We are excited to be moving toward onboarding our new design team for the project!

We completed recruitment via a competitive RFP process and received 3 very strong proposals, including one from a joint venture that included the architecture firm that comp...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 23, 2021

Middle Lake Rehabilitation Project Update 11/22!

Capital Project Update

The Middle Lake Rehabilitation project is moving forward and 90% design documents are nearly complete. In order to pave the way for a smooth construction project on the main scope of work, now due to go out to bid in the summer of 2022, we are initiating ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 23, 2021

Esprit Park Project Update 11/23!

Capital Project Update

Recreation and Park, together with Fletcher Studio, presented updates on the Esprit Park Renovation Project to over 35 members of the community on Thursday, November 18. The team also responded to many community member questions about design development a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 23, 2021

Fillmore Turk Mini Park Project Update 11/23/21

Capital Project Update

We are awarding the construction contract in December!! Then, the contractor, sub-contractors, and engineers will be entering all pertinent data in city system for ground breaking in the new year. Construction advisory notices are on site and additional p...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 23, 2021

Bay View Playground Renovation, update 11/23/21!

Capital Project Update

The project is 95% completed! The sod still needs a bit more time to be fully established. Visible from these images, are the brown spots and joints that have not fully mended; however, that recent rainfall and fog has proven nourishing!  All sys...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 18, 2021

Stow Lake Perimeter Path Project Update 11/18!

Capital Project Update

Hi all- The project team is working with a biologist to minimize impacts to the wildlife around the lake. We will be moving forward with the hazardous tree removals later this year. We are aiming to advertise the project to potential contractors in the co...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 18, 2021

Stern Grove Playground Virtual Community Meeting #3 12/14 at 5pm!

Capital Project Update

Join us for the third community meeting for the Stern Grove Playground Renovation Project. We invite you to share input and feedback on proposed playground design options. The playground is part of the Let’sPlaySF! Initiative, a partnership between the Re...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 18, 2021

Herz Playground Project Update 11/18!

Capital Project Update

Hi everybody- We are putting the finishing touches on the permit set of drawings, which we will submit to the Building Department for approval. We will also be conducting a final cost estimate for the project. Please e-mail Project Manager, Alexis Ward, a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 18, 2021

Herz Recreation Center Project Update 11/18!

Capital Project Update

Hi all-  The Building Department has completed their Site Permit review and the permit notification has been posted at the park. The next step will be submitting additional drawings for the Building Permit. The Arts Commission team is busy as the...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 16, 2021

Construction at the McLaren Park Native Plant Garden will begin this week!

Capital Project Update

The McLaren Park Native Plant Garden will showcase the benefits of California Native Plants, beautify the Visitacion Avenue corridor, increase public access and participation, and provide a venue for outdoor education. Click here to view the site plan.

Sta...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 12, 2021

Fillmore Turk Mini Park Project Update 11/2021

Capital Project Update

The construction contract is being awarded in November 2021 and the team, preparing for site work, has posted these notices throughout the park. Please check back for actual closure date which we will post here.

Thank you all within the community who have ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 2, 2021

Rossi Pool Project Update 11/2/21!

Capital Project Update

The Rossi Pool Renovation Project progress is moving along well, and we have reached a significant milestone: the pool shell has been plastered and is currently being filled with water! Current construction activities are now focused on pool mechanical eq...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 28, 2021

Esprit Park Project Virtual Community Meeting on November 18th!

Capital Project Update

Rec and Park is hosting an online update to community members on the Esprit Park Renovation Project on Thursday, November 18, from 5:30 pm – 6:30 pm.

This update will include a presentation from staff on the following items:

  • Progress on the park design and ...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 15, 2021

Victoria Manalo Draves Park - VMD reopening Saturday, 10/16/2021

Capital Project Update

We are please to announce the re-opening of Victoria Manalo Draves Park! The summer renovation included installation of new sports lighting, new pedestrian lighting, expansion and reconfiguration of the community garden, the addition of a nature explorati...

Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: October 13, 2021

McLaren Park Tai Chi Court Project Update

Capital Project Update

Construction on the Mansell Tai Chi Court is underway and moving fast! The plants haven’t even been installed yet one can already feel the new berm sheltering the future plaza from wind. We hope to have this beautiful space open to the public by the end o...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 9, 2021

Francisco Park construction moves forward towards December completion

Capital Project Update

Francisco Park construction is moving forward towards a December 2021 completion!

The Hyde Street stairway has been installed and the view from the top is spectacular.  The pathway from the stairway to the great lawn will be poured next week. &...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: October 5, 2021

Juri Commons is now open to the public!

Capital Project Update

Juri Commons is open to the public! On September 13th the city held a ribbon cutting celebration to commemorate the park’s opening with many neighbors, community members, donors and city leadership in attendance. The process for getting Juri Commons renov...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 5, 2021

Lake Merced Boat Dock Ribbon Cutting Ceremony November 13th!

Capital Project Update

We are happy to announce that construction for the Lake Merced Boat Dock is complete, and the site is open to the public. Construction fencing was removed on 9/16/21 and the new dock, boat ramp, seating area, and ADA parking stall are ready for use! A rib...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 2, 2021

Victoria Manalo Draves Park - Construction wrapping up at VMD

Capital Project Update

Lighting and safety improvements at VMD are close to completion. We have had a few unfortunate delays from suppliers and subcontractors, but are in the home stretch of construction! PG&E will be installing our new meter and energizing the site on Octo...

Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: September 30, 2021

Esprit park Project News 9/30/21!

Capital Project Update

Consultant on site at Esprit this week to inventory the condition of the storm drainage system that was installed approximately 15 years ago. The goal of this inventory is to understand what existing infrastructure can be retained and incorporated into ou...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 20, 2021

Fillmore Turk Mini Park Project Update 9/2021

Capital Project Update

We received seven bids in June and Public Works contracting administration is in the final stages of identifying the lowest responsive and responsible bidder. We are excited to be so close to awarding the contract. Stay tuned.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 20, 2021

Herz Playground Project Update 9/20!

Capital Project Update

Hi everybody- We are getting close to wrapping up our construction document for the new playground and the bathroom renovation at Herz Clubhouse. We aim to get permits through the Building Department in November. For questions please contact Project Manag...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 20, 2021

Bay View Playground Renovation, update 9/2021!

Capital Project Update

The project is 85% completed! The sod was recently installed and needs 60 days for full establishment (recommended time for roots to attach to the earth and grow strong before being walked on) The fences are 90% installed, fixtures are starting to be inst...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 20, 2021

Herz Recreation Center Project Update 9/20!

Capital Project Update

Hi all- The Arts Commission received over 100 applications from potential artists for the public art piece at Herz Recreation Center. The Arts Commission staff will work with a selection panel to narrow down the applicants and establish a shortlist for fu...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 18, 2021

Jerry Garcia Amphitheater Opens Following Major Renovation

JGA 1

SAN FRANCISCO, CA – Jerry Garcia Amphitheater, an outdoor concert venue nestled in McLaren Park, re-opened today following a $1.45 million facelift that made it more comfortable and accessible for both performers and audience members, the San Francisco Re...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 15, 2021

Buchanan Mall, Turk – Golden Gate at SFAC Civic Design Review Monday 9/20

Capital Project Update

After almost seven years of community-driven engagement and visioning, SF Rec and Parks is thrilled to be moving forward with a clear schedule for detailed design and construction of the Turk – Golden Gate block of Buchanan Street Mall!

We have an importan...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 13, 2021

Juri Commons Park Reopens Following Renovation

Juri Commons Ribbon Cut

SAN FRANCISCO, CA –Juri Commons reopened today following a $1.9 million renovation honoring the Mission District park’s railroad history while featuring a seamless redesign with new plantings, an improved play space for children, grass for dogs, and an ad...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 10, 2021

Esprit Park Project Update 9/11!

Capital Project Update

We have been assessing conditions on site over the past few months, including the following:

  • Soils investigation (infiltration study, testing for Maher Ordinance compliance, and agricultural suitability), with the Public Works Site Assessment and Remediati...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: September 5, 2021

Victoria Manalo Draves Construction Updates and Support for Neighboring Bessie Carmichael School

Capital Project Update

CONSTRUCITON UPDATES:

This lighting project was anticipated to be completed in Fall 2021 (as noted on construction banners). We are several weeks away from the start of Fall and construction work continues (see photos below).

We do not have a firm reopening...

Read on...

Project page RPD Park Improvements | All Project Updates
Posted on: August 20, 2021

Herz Playground Project Update 8/20!

Capital Project Update

Hi folks- The landscape architect is developing the construction documents for the project. We are sharing the drawings with our Structural Maintenance team to ensure that the new playground is beautiful, fun and maintainable by our staff!  For q...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 20, 2021

Richmond Playground Project Update 8/20!

Capital Project Update

Design work for the Richmond Playground renovation has resumed! We are thankful to everyone who helped get this project moving again and remain hopeful that we can have the project in construction by mid 2022. Thank you to the wonderful community who has ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 20, 2021

Golden Gate Park - 9th and Lincoln Gateway Project Update 8/20!

Capital Project Update

As this project neared 60% design completion it was put on hold due to COVID related funding delays – but we are back up and running! With new funding allocated to the project the design team is moving forward and we hope to put the project out to bid by ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 20, 2021

Golden Gate Heights Playground Update 8/20!

Capital Project Update

Hi folks- We have wrapped up work on the Golden Gate Heights Playground & Field Renovation. It was great to celebrate with many of you at the park opening celebration. Thank you again to all of the community members who spent countless hours helping t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 20, 2021

Herz Recreation Center Project Update 8/20!

Capital Project Update

Hi everybody- The architects and engineers are still hard at work finalizing the details of the building and landscape design. We are also hoping to receive our Site Permit from the Department of Building Inspection soon. Construction is still planned for...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 17, 2021

Updates to RFP for Architectural & Engineering Services and Recruitment Timeline for Gene Friend Rec

Capital Project Update

Thank you for helping us to get the word out to folks who may be interested in working on the project.

An online pre-proposal conference will be held on Wednesday, August 18, at 10 am (this was postponed from August 5).

The deadline for written questions is...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 16, 2021

Design continues and additional funding received for Buchanan Street Mall!

Capital Project Update

Thanks to the 174 people who participated in the survey to refine the design of Buchanan Street Mall, Turk – Golden Gate block. There are clear community preferences for a big kids play structure, belt swings, bench swings, stationary bikes, balance-focus...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 16, 2021

Juri Commons Construction continues 8/16!

Capital Project Update

Thank you everyone for your continued patience with this renovation project. Construction is nearing completion and we are now waiting on a few final sign-offs. Look for a posting for the official ribbon cutting soon! We are aiming for early-mid September...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 12, 2021

McLaren Park Native Plant Garden Project Plans

Capital Project Update

The McLaren Park Native Plant Garden transforms a blighted and hazardous corner of McLaren Park into a functional open space, providing a safe resource for recreation and environmental education about the value of planting native plants throughout the Cit...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: August 6, 2021

Construction expedited for Bessie Carmichael students

Capital Project Update

Good news is that construction is going great! Our new utility work on Sherman was inspected and approved by PG&E and trenching across the street and down the sidewalk will be repaired by early next week.

Sports lighting pole foundations were inspected...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 26, 2021

Construction progress at Victoria Manalo Draves

Capital Project Update

Construction is moving forward quickly at VMD! Cazadoro Construction, Inc. has been a collaborative partner in accelerating the schedule, with the goal of opening key areas of the park prior to the start of the SFUSD academic year.

 

Recent activit...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 26, 2021

George Christopher project wrapping up,

Capital Project Update

The final piece of work for George Christopher’s renovations, resurfacing the tennis court, is almost complete! The slip sheet system requires dry weather and our contractor experienced many schedule delays due to the dripping fog the park experienced thr...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 23, 2021

George Christopher Playground is Now Open!

Capital Project Update

Thanks so much for those of you who were able to attend the grand reopening, here are some photos of the newly renovated playground. We can not do these renovations without your support.

Attached are a few pictures of the completed playground, just prior t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 23, 2021

Merced Heights - Our design team is moving along with construction document production!

Capital Project Update

As we work on that, we’re reaching back out to solicit input from the community.

As discussed during an online community meeting in February 2021, we are exploring including adult exercise equipment if budget allows. 

If you have preferences on wha...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 23, 2021

The Request for Proposals for Architectural & Engineering Services for the Gene Friend Rec is Live

Capital Project Update

Thank you for helping us to get the word out to folks who may be interested in working on the project.

An online pre-proposal conference will be held on Thursday, August 5, at 1:30 pm.

Proposals are due on Tuesday, August 24, by 5 pm.

For the full RFP as wel...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 22, 2021

Portsmouth Square Draft EIR Publication Date: August 4, 2021!

Capital Project Update

The Portsmouth Square project team has been incredibly busy over the past several months, pushing forward both the detailed design and the environmental review for the project. On August 4th, the Draft EIR will be published and available for public commen...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 22, 2021

South Sunset Fields Construction Update 7/22/21!

Capital Project Update

The construction contract has been awarded to OBS Engineering Inc. and construction activities will start on site in early August. We expect the project to be complete by this winter.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 19, 2021

Golden Gate Heights Playground Final Construction Update 7/16!

Capital Project Update

Hi everyone! We are thrilled to share that construction is wrapping up at Golden Gate Heights and we are opening on July 20th at 11:30. Join us to celebrate the completion of this project! Thank you to all the community members who helped make this projec...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 19, 2021

Rossi Pool Project Update 7/19!

Capital Project Update

Project progress is moving along well, and the construction team is working diligently despite some delays due to unforeseen site conditions. Current construction activities include:

Building Envelope – Concrete scope complete. Painting subcontractor is on...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 19, 2021

Herz Playground Project Update 7/19!

Capital Project Update

Hi everybody, We are continuing work on the construction documents for the project. We are happy to share that we will be including an ADA accessible swing in the younger children’s playground. Other playground elements include bucket swings, belt swings,...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 19, 2021

Herz Recreation Center Project Update 7/19!

Capital Project Update

Hi folks,  We continue to develop the construction documents for the new Recreation Center and the outdoor spaces. We are updating our drawings to incorporate comments from the Department of Building Inspection and our Structural Maintenance Yard...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 7, 2021

Golden Gate Heights Playground is Opening 7/20!

Capital Project Update

Hi everyone- We are thrilled to announce the opening celebration of the Golden Gate Heights Playground and Renovation Project! See the attached invitation for details about the event.

Thank you to everyone who helped make this project happen!

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: July 7, 2021

Stern Grove Playground Virtual Community Meeting #2 (7/21 at 5pm)

Capital Project Update

Join us for the second community meeting for the Stern Grove Playground Renovation Project. We invite you to share input and feedback on proposed playground design options. The playground is part of the Let’sPlaySF! Initiative, a partnership between the R...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 30, 2021

Gene Friend Rec Center Project Update 6/21/21!

Capital Project Update

We are pushing to advertise an RFP (request for proposals) for a design team (architecture and engineering) this July, with the goal of selecting a team and having them start work by right after the New Year 2022. If you know of any firms that might be in...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 22, 2021

Lake Merced Boat Dock Replacement Update 6/22!

Capital Project Update

We are making great construction progress and nearing the finish line! The prefabricated dock and gangway were installed in late May, and the contractor is currently making minor adjustments before it is ready for use. Other ongoing site work includes irr...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 22, 2021

Victoria Manalo Draves Park - Construction begins at VMD on Monday, June 28!

Capital Project Update

Your Victoria Manalo Draves lighting upgrades and park improvements are coming soon! Rec and Park has been working on final preparations with our contractor Cazadoro Construction, Inc. for the past month, and the builders will take control of the park and...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 22, 2021

Bay View Playground Renovation, update 6/21!

Capital Project Update

The fence poles, those silver vertical sticks, are 80% installed awaiting the black finish and mesh. Grading, almost complete on the ballfield, is preparing for sod installation next month. Then we’ll move to the areas outside the field. The fitness equip...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 22, 2021

Golden Gate Heights Playground Construction Update 6/21!

Capital Project Update

Hi all, We are nearing completion of construction at Golden Gate Heights. The contractor is installing the finishing touches. Please stay tuned for information on an opening celebration later this summer! For questions please contact Project Manager, Alex...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 22, 2021

Herz Recreation Center Project Update 6/21!

Capital Project Update

Hi everybody, Our design team is working on the construction documents for the project and we are going through the permitting process with the Department of Building Inspection. Please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org with a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 22, 2021

Herz Playground Project Update 6/21!

Capital Project Update

Hi all, We are wrapping up our cost estimating and we will be moving into construction documents for the playground renovation. For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 14, 2021

Esprit park Project News 6/14!

Capital Project Update

We are happy to report that the Board of Supervisors has approved the grants that support the project. This renovation was made possible thanks to a generous $5 million funding commitment from UCSF, who committed this grant through their Dogpatch Communit...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 14, 2021

Merced heights Lower Lawn Project Update 6/15/21!

Capital Project Update

The Arts Commission Civic Design Review Committee approved the design in April, under their “Small Project Review” category.

Our team is moving forward to flesh out details of the approved concept design. We are expecting a 50% construction document submit...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 8, 2021

Juri Commons Construction Update 6/7!

Capital Project Update

We’re excited to share that planting is nearing completion, embedded rails are installed in the pathway and the team is about to lay down play surfacing in the playground. We look forward to opening the park to the public! By August we expect the sod to h...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: June 1, 2021

Construction starting soon at Victoria Manalo Draves Park in SOMA

Capital Project Update

The Recreation and Parks Department has executed a construction contract with Cazadoro Construction, Inc. for a summer renovation of Victoria Manalo Draves Park in SOMA. The work includes the addition of sports lighting at the ballfield and basketball cou...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 28, 2021

Save the Date: India Basin Groundbreaking Event on June 17!

Capital Project Update

Mark your calendars! A groundbreaking event marking the beginning of remediation work on the India Basin project is scheduled for Thursday, June 17 from 3 to 4:30 p.m. at India Basin Shoreline Park (Hunters Point Boulevard and Hawes Street). Join us for t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 21, 2021

Golden Gate Heights Playground Construction Update 5/21!

Capital Project Update

Hi everyone, The contractor has installed the sod and they are working on the remainder of the landscaping and site furnishings. We are looking forward to opening this summer! For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 21, 2021

Herz Playground Project Update 5/21!

Capital Project Update

Hi all, Our design has completed the detailed design phase and we are currently cost estimating the project and doing regulatory reviews. Later this summer we will begin construction documents. For questions please contact Project Manager, Alexis Ward, at...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 21, 2021

Herz Recreation Center Project Update 5/21!

Capital Project Update

Hi folks, We are performing a cost estimate for the project and then, we will begin construction documents. The project has been submitted to the Department of Building Inspection for permitting. Please contact Project Manager, Alexis Ward, at alexis.ward...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 18, 2021

Esprit Park Poised for Robust Renovation

Capital Project Update

FOR IMMEDIATE RELEASEMay 18, 2021

Contact:San Francisco Recreation and Park Department

RPDcommunications@sfgov.org

SAN FRANCISCO, CA – Esprit Park is one step closer to a $7.7 million renovation designed to balance the needs of its growing ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 17, 2021

Bay View Playground Renovation, update 5/17!

Capital Project Update

Playground fixtures are in! AND the field is finally taking shape. Much of the work since the start has been centered around everything underground: the field fencing foundation, the retaining walls for the bio retention planting, the drainage, irrigation...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 3, 2021

Japantown Peace Plaza project Update 5/3!

Capital Project Update

The design started this spring with our team taking a deep ‘technical’ dive into the existing structure and elements to inform each feature of the vision/concept plan. In addition, we are meeting all regulatory departments to confirm compliance processes,...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 3, 2021

Francisco Park Construction Update 5/3!

Capital Project Update

The elevated walkway is complete connecting the lower part of the park along Bay Street with the upper level and future great lawn. All flatwork has been complete thorough the park: the Bay Street entrance, upper plazas and Bay Street  and Larkin...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 28, 2021

Rossi Pool Project Update 4/28!

Capital Project Update

Project progress is moving along well. Current construction activities include: 

  • Sitework/Landscaping – The site utility subcontractor is currently working on the side sewer scope from Arguello East towards the property.  
  • Structural Steel...
Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 28, 2021

Lake Merced Boat Dock Replacement Update 4/28!

Capital Project Update

Construction progress at the Lake Merced Boat Dock project is moving along well. Current ongoing work includes roadway paving, lighting installation, shipping container delivery and irrigation. See construction in progress below.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 26, 2021

George Christopher Playground Reopening 4/29/21!

Capital Project Update

The long-awaited date has been appointed! George Christopher Playground is scheduled to reopen to the public on Thursday, April 29th!

Our contractor put on the finishing touches this past month, installing benches, signs, and the drinking fountain, making ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 26, 2021

Middle Lake Rehabilitation Project Update 4/26!

Capital Project Update

The design is progressing and the Middle Lake Rehabilitation project is moving forward! We anticipate construction drawings to be complete by the summer, to begin construction by fall of this year. Assuming no significant project delays, Middle Lake is st...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 26, 2021

Juri Commons Construction Update 4/23!

Capital Project Update

We’re excited to share that the pathways and walls are nearly complete, the play equipment is installed, planting has begun, and the space is starting to feel like a cohesive park! We hope to have Juri Commons open to the public by June so that the neighb...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 26, 2021

Richmond Playground Project Update 4/26!!

Capital Project Update

Design work on the Richmond Playground renovation is temporarily halted but we are hopeful that the project can resume shortly. This snag will likely push the project schedule back at least one month. Many thanks to everyone who has contributed to the ren...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 23, 2021

Esprit park Project News 4/23/21!!

Capital Project Update

Rec and Park staff will be presenting two related Accept and Expend resolutions to the Board of Supervisors Budget & Finance Subcommittee on Wednesday, April 28. This is part of the process for approving grants. This renovation was made possible thank...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 20, 2021

Herz Playground Project Update 4/20!

Capital Project Update

Hi everyone, Thank you so much for your support at the Recreation and Park Commission and for participating in all our community outreach for this project. The project’s concept design has been approved by our Commission. Now, the project team is working ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 20, 2021

Golden Gate Heights Playground Construction Update 4/20!

Capital Project Update

Hi folks- The contractor is working on flatwork around the playground including pouring concrete and asphalt for the paths and picnic area. For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org..

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 20, 2021

Herz Recreation Center Project Update 4/20!

Capital Project Update

Hi all, Thank you to all the community members who helped make this project a reality! The concept design for the new Recreation Center was approved by our Rec Park Commission in March. The architecture and engineering team is now in detailed design and t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 16, 2021

Arts Commission Review and Design Coordination for Merced Heights Lawn Terrace Project!

Capital Project Update

Following Rec and Park Commission of concept design in March, we are moving forward! The Arts Commission Civic Design Review Committee will be reviewing the project this Monday, April 19, under their “Small Project Review” category.

Members of the public w...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 16, 2021

Gene Friend Rec Center Project Update 4/16/21!

Capital Project Update

Dear Friends and Neighbors of the Gene Friend Rec Center,

As you have likely heard by now, Prop A passed in November, and the Health and Recovery General Obligation Bond is a go. We are expecting to have this bond funding for the Gene Friend Rec Center Pro...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 16, 2021

Temporary Playground Closure Apr 26-27 and Donor Recognition Tile Installation Complete

Capital Project Update

The West Portal Playground (Children’s Play Area Only) will be temporarily closed April 26 through sometime on April 27 as we do some safety surfacing repairs. The playground is being fenced to allow the surfacing repairs to cure properly. Please consider...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 9, 2021

Bay View Playground Project Update 3/29/21

Capital Project Update

The entire site has been graded and fence footing installed—so that the boundaries of the field (such as,… home plate, backstop foul lines etc) are easier to see. Notice the white (layout) lines throughout were replaced with pipe sleeves embedded into the...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: April 9, 2021

Fillmore Turk Mini Park Project Update 3/29/21

Capital Project Update

Target bid advertisement will be mid-Spring 2021. COVID has impacted the bid advertisement of the project, but it gives us additional time to tighten the construction documents to achieve better bid results.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 29, 2021

Esprit Park Renovation Update MAR '21

Capital Project Update

Now that the Rec and Park Commission has approved a final concept design, the team is working to build a detailed schedule and project plan.  Rec and Park is also transitioning project managers from Alexis Ward to Melinda Sullivan, who worked on ...

Read on...

Back to the project page RPD Park Improvements | All Project Updates
Posted on: March 19, 2021

Merced heights Lower Lawn Project Update 3/19/21!

Capital Project Update

The Recreation and Park Commission approved a concept design for the Merced Heights Playground Lower Lawn Terrace Renovation on March 18, 2021. Please see the final design here. You can view more background information in the staff report, as well as the ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 19, 2021

West Portal Playground Project Update 3/19/21!!

Capital Project Update

We hope you are enjoying the recently renovated West Portal Playground! We have received some concerns about the functioning of the merry-go-round at the playground. Our contractor and subcontractors have visited the site to check the merry-go-round and w...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 16, 2021

Golden Gate Heights Playground Construction Update 3/16!

Capital Project Update

Hi folks- The playground equipment is installed and the contractor is working on grading the upper field and installing the new irrigation system. For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org..

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 16, 2021

Herz Playground Project is Going Before the Commission for Approval!!

Capital Project Update

Hi all, This Thursday, March 18th at 10am, we will be presenting the playground concept plan to the Rec Park Commission for approval. The Commission agenda and call-in information can be seen here. If you are not able to call-in to the meeting, you can em...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 15, 2021

Merced Heights Lower Lawn Terrace Project Headed to Commission for Approval!

Capital Project Update

Staff will be presenting the proposed concept design to the Full Recreation and Park Commission this week. Please find details below:

Full Recreation and Park Commission Hearing

Thursday, March 18, 10 am

Call in number for members of the public:

1.415.655.000...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 12, 2021

Ocean Beach Climate Change Adaptation Project Update 3/11!

Capital Project Update

There are two upcoming opportunities to provide public comment on this project.  We will be presenting the overall concept plan for this project for Civic Design Review of the San Francisco Arts Commission on Monday, March 15th at 2 pm. ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 9, 2021

Rossi Pool Project Update 3/9/21!

Capital Project Update

Project progress is moving along well, despite some recent construction delays due to unforeseen site conditions. Current construction activities include: Exterior window and doors installation, interior tiling, epoxy flooring, painting. Pool and mechanic...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 9, 2021

Garfield Pool Project Update 3/9/21!

Capital Project Update

We are thrilled that the construction fencing is down, and the Garfield site is now open to the public. The Clubhouse and Community Center are scheduled to open in mid/late March for select activities, and the pool will remain closed per current SF Health...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 8, 2021

POSTPONED - Stern Grove Virtual Community Meeting 3/25 at 5 pm!

Capital Project Update

Join us for the second community meeting for the Stern Grove Playground Renovation Project. We invite you to share input and feedback on proposed playground design options. The playground is part of the Let’sPlaySF! Initiative, a partnership between the R...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 1, 2021

Merced Heights Lower Lawn Terrace Project Update 3/1!

Capital Project Update

We have received great input to help us finalize a proposed concept design for the Merced Heights Playground Lower Lawn Terrace Renovation Project, during an online community meeting on Thursday, February 18 with over 20 members of the public attending, a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 1, 2021

Construction in the final stretch at Shoreview Park (3/2/21)

Capital Project Update

The project has experienced significant delays due to COVID-19, winter rain, and subcontractor scheduling challenges, but construction is over three quarters complete at Shoreview Park and there is a solid plan for finishing work in early spring.

Exciting ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 1, 2021

Plants, paths, sculptures, and turf installed at George Christopher

Capital Project Update

The project suffered COVID-19, weather, and subcontractor scheduling delays around the turn of the year, still, construction has moved steadily forward at George Christopher Playground. Our contractor achieved an important milestone at the end of January:...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 26, 2021

The Lisa and Douglas Goldman Tennis Center will open on March 3rd!

Capital Project Update

Wednesday, March 3, 2021, the Lisa and Douglas Goldman Tennis Center will open to the public.  

Note that when the Tennis Center opens court reservations will be required for play due to COVID.

Check out the press release here: https://sfrecpark.or...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 23, 2021

News about the Herz Projects!

Capital Project Update

We are excited to share that Rec Park staff will be presenting the concept design for the Herz Playground Renovation and the concept design, grant acceptance and donor recognition plan for the Herz Playground Recreation Center to the Recreation and Park C...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 23, 2021

Esprit park Project News 2/23!

Capital Project Update

Hi everyone- At long last, we have an approved conceptual design for the project! Thank you so much to everyone who has participated in this project. The next phase will be focused on developing the construction documents. We will update this blog monthly...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 23, 2021

Golden Gate Heights Playground Construction Update 2/23!

Capital Project Update

Hi everyone! The playground equipment is being installed at Golden Gate Heights! Next week, the contractor will be moving the construction fencing back to enclose the upper field as they start grading the field. For questions please contact Project Manage...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 22, 2021

India Basin Shoreline Park Meeting to Discuss the Playground 3/2/21!

Capital Project Update

Join us for a virtual community meeting!

We need your feedback! The India Basin Project partners are looking for inspiration to design the new children’s play area at India Basin Shoreline Park. We want to hear from families, including children, about what...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 18, 2021

Ocean Beach Climate Change Adaptation Project Update 2/18!

Capital Project Update

Thank you to the 90+ community members who joined us for the December 2020 Virtual Community Meeting, and contributed comments and questions! 

Click  here for the 12/3/2020 Virtual Community Meeting Notes, including a summary of all quest...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 18, 2021

Willie "Woo Woo" Wong Playground is Now Open!

Capital Project Update

We’re excited to have opened the Willie “Woo Woo” Wong Playground on February 12, 2021 to help kick-off the Year of the Ox!  Thank you to everyone who made this renovation possible. We sincerely hope you enjoy this unique park as much as we do - ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 9, 2021

Juri Commons Construction Update 2/9!

Capital Project Update

Juri Commons is moving forward in construction and hitting a good stride. The crew discovered some faulty utility infrastructure during demolition which caused some delays, which pushed our new anticipated completion date out to April of this year. We’re ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 9, 2021

Richmond playground Project Update 2/9!

Capital Project Update

The concept design for Richmond Playground is complete! The concept has been granted all of the necessary approvals to move into the next phase, during which the design team will get into more detail on how exactly this amazing new playground will be buil...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 9, 2021

Middle Lake Rehabilitation Project Update

Capital Project Update

The Middle Lake Rehabilitation is moving forward! With 50% construction drawings now complete, we anticipate construction to begin this summer. Assuming no significant project delays, Middle Lake will be complete and open to the public by mid-2022.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: February 5, 2021

Merced Heights Lower Lawn Terrace Project Community Meeting!

Capital Project Update

Dear Community Member,

Thank you for your patience as some important preparations were made over the last several months since my last update to you.

I’m excited to report that we will be convening an online community meeting for 2 weeks from today:

Merced H...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 29, 2021

Bayview Playground Project Update 1/29!

Capital Project Update

With sadness we honor the namesake of this athletic field, K.C. Jones, who left us on December 25, 2020.

Jones played college basketball for the University of San Francisco Dons and led them to the 1955 and 1956 NCAA championships. He was also part of the ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 29, 2021

Complete the survey to refine the design of an all-ages play area in Buchanan Street Mall

Capital Project Update

Thanks to everyone who participated in the Virtual Community Meeting on Tuesday, January 19th, and for your engagement and feedback to help refine the design. You can review the presentation slides here and meeting notes here.

 The Western Additio...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 29, 2021

Fillmore Turk Mini Park Project Update 1/29/21

Capital Project Update

We just received notice that the building permit has been approved! Our next step is to bid advertise again in February. The first bids received late last year were beyond our budget. So our team rolled up sleeves and tighten the construction documents to...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 25, 2021

Construction almost complete at GGP Dog Training Area

Capital Project Update

The work at the historic Golden Gate Park Dog Training Area is SO CLOSE to being finished… and many humans and dogs are eager to return!

Please be patient with our contractor. Some final items, important to user safety and the effectiveness of long term ma...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 25, 2021

Stern Grove Virtual Community Meeting 2/18 at 5 pm!

Capital Project Update

We hope you can join us for the first of many virtual meetings to discuss the renovation of the playground at Stern Grove. The playground is part of the Let’sPlaySF! Initiative, a partnership between the Recreation and Park Department and the San Francisc...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 22, 2021

Golden Gate Heights Playground Project Update 1/22/21

Capital Project Update

Hi everyone! Construction is continuing at Golden Gate Heights. The contractor is currently working on the footings for the playground equipment.  For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 22, 2021

Esprit park Project Update 1/22!

Capital Project Update

Hi folks- We have exciting news! We will be presenting a concept plan for approval at the Rec Park Commission in February! Thank you everyone who has participated in our many meetings, discussions, and our most recent online survey about this park renovat...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 22, 2021

Herz Playground Project Update 1/22!

Capital Project Update

Hi everyone, We are very close to finalizing our concept plan based on feedback from the Historic Preservation team at the Planning Department. We will be sharing the concept plan on our website and we are planning to present it to the Rec Park Commission...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 20, 2021

Herz Rec Center Virtual Community Meeting 2/3/21

Capital Project Update

SF Rec & Park, Mercy Housing and Related CA are pleased to share the final concept plan for the Herz Recreation Center Project (com-munity gym).The discussion will include a presentation about including public art at the site and we will be sharing op...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: January 19, 2021

Stern Grove Playground Survey is Now Closed Thank you!

Capital Project Update

The Stern Grove Playground Community Survey is now open!

 

The San Francisco Recreation and Parks Department (RPD) is pleased to kick-off the Stern Grove Playground Renovation Project. The play area at Stern Grove is about to undergo a renovation, ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 19, 2021

Virtual Meeting and Survey to Refine the Design for Buchanan Street Mall

Capital Project Update

The Western Addition community has been driving a new vision for Buchanan Mall since 2014. A Vision Plan was published in March 2017 and the conceptual design for all five blocks was approved in April 2020. With the passing of the Health and Recovery Bond...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 14, 2021

Willie "Woo Woo" Wong is Almost Complete!

Capital Project Update

We are very close to finishing construction and opening the park again! The pagoda has a fresh coat of paint, the clubhouse’s wood bleachers are sparkling, and the hummingbirds are loving the new plants. There are only minor details left to complete and t...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: December 29, 2020

GGP Dog Training Area December Update

Document

The historic Dog Training Area is very close to completion, however project opening has been delayed until late January. We have had some December delays due to the COVID-19 pandemic and the timelines for additional improvements that will support the ease...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 28, 2020

Golden Gate Park Tennis Center December Update

Document

The Tennis Center is making great progress towards completion in early 2021. The courts are now fully color coated, fences are installed, and planting is nearing completion. Flat work at the Nancy Pelosi Drive entrance and along the west side of the clubh...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 24, 2020

Bay View Playground Renovation Holiday Update

Document

The park is beginning to take shape as some of the boundaries are being set. Construction excavation continues with foundation installation and a few deep pits. See the recent images below.  Can you tell which amenity it is?

On behalf of Recreatio...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 23, 2020

Golden Gate Heights Update Dec '20

Capital Project Update

Hi folks- The contractor will be working on the retaining wall on the north side of the playground. Then, they will be laying out the play equipment.  For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org.&a...

Read on...

Back to the project page RPD Park Improvements | All Project Updates
Posted on: December 23, 2020

Esprit Park Renovation Update Dec '20

Capital Project Update

Hi everyone- Thank you to those who attended our virtual community meeting! We are currently conducting an online survey for the project. The survey will close on December 28th. Click here to access the survey. If you would like to be on the proj...

Read on...

Back to the project page RPD Park Improvements | All Project Updates
Posted on: December 23, 2020

Herz Playground Project Update Dec '20

Capital Project Update

Hi everyone, We are working with the Historic Preservation team at the Planning Department to review the playground design. Once this is complete, we will present the design to the Rec Park Commission for approval and then begin construction documents. To...

Read on...

Back to the project page RPD Park Improvements | All Project Updates
Posted on: December 23, 2020

Herz Recreation Center Project Update Dec '20

Capital Project Update

Hi folks- We are thrilled that Prop A passed! This will provide $10 million of funding towards this project. We are planning to return to the community early in 2021 for a final virtual community meeting to share the design. For questions please email Pro...

Read on...

Back to the project page RPD Park Improvements | All Project Updates
Posted on: December 22, 2020

Francisco Park Construction Update DEC '20

Capital Project Update

Construction at Francisco Park continues to move along smoothly.  The elevated pathway structure has been painted and the crew is starting to install the boardwalk.  Form work for the concrete at the Bay Street entrance is installed and ...

Read on...

Back to the project page RPD Park Improvements | All Project Updates
Posted on: December 3, 2020

West Portal Playground: Update on Temporary Closure of Children’s Play Area This Week

Capital Project Update

The West Portal Playground (Children’s Play Area Only) was temporarily closed today (Thursday, December 3) for some work on the perimeter fencing.

 

The playground will re-open by 5 pm today.  Contractor staff will be on site on Friday, De...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 2, 2020

West Portal Playground: Temporary Closure of Children’s Play Area This Week

Capital Project Update

The West Portal Playground (Children’s Play Area Only) will be temporarily closed this week as we do some work on the perimeter fencing. Please consider using this alternative playground: Larsen Playground (850 Vicente St) 

 

The playgroun...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 19, 2020

Margaret Hayward Project Update 11/18!

Capital Project Update

The tennis courts reopened early November, ahead of schedule .

During the park renovation, the tennis courts received an entirely new southern edge: a new foundation, new drainage and new fencing, new gate and accessible path to the rest of the park, new d...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 19, 2020

Please Join us for Virtual Community Meeting on Upcoming Ocean Beach Project

Capital Project Update

Please join the City’s multi-agency virtual community meeting to learn more about the proposed South Ocean Beach Multi-Use Trail Project!

Together with the SF Public Utility Commission, this proposed Recreation and Parks project will replace the Great High...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 19, 2020

McLaren Trails - Native Plant Garden meeting this evening and pathway work upcoming

Capital Project Update

Parks Alliance is hosting a virtual meeting this evening at 6pm to review the scope of a Native Plant Garden, just south of the Leland community garden and adjacent to the proposed new trail along Visitacion Avenue.

Growing Outdoors and Learning (...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 12, 2020

Francisco Park Construction Update 11/12!

Capital Project Update

Recent construction activities at Francisco Park include install of the footings and piers for the elevated walkway, flat work on pathways around the main lawn, and construction of the new Maria Manetti Shrem Community Garden (click here to enter...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 12, 2020

Construction wrapping up at the GGP Dog Training Area!

Capital Project Update

We are in the final phases of construction at the historic Golden Gate Park Dog Training Area. All of the site grading and drainage is completed, as is the electrical work to connect the irrigation timer to power source at the Senior Center. The large and...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 10, 2020

McLaren Group Picnic Area and Playground Project Update 11/10!

Capital Project Update

We will be removing two additional trees that are on the path south of the playground. These trees have been recommended for removal by an independent arborist. The trees will be re-planted at a 2:1 ratio. Let us know if you have any questions! Alexis.war...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 6, 2020

George Christopher schedule update 11/5!

Capital Project Update

The ball field fence repairs are complete and look fantastic! Construction in the playground area continues with the lower planting areas and wood stepper borders almost complete and final concrete “riverbed” and curbs soon to be poured.

 The cont...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 5, 2020

Bay View Playground Renovation, update 11/02!

Capital Project Update

Demolition is in full force as most of the structures have been removed….clearing the path for new work….See the current photos.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 4, 2020

Golden Gate Park Tennis Center Project Update 11/4!

Capital Project Update

We are very excited to announce that the Tennis Center is nearing completion. Check out this great article with more details, by clicking here.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: November 4, 2020

Check out the Discussion on South Ocean Beach Project with SPUR

Capital Project Update

Thanks for your interest in the project. This panel discussion will give you more information, click here to read more and view.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

Golden Gate Heights Playground Construction Update 10/29!

Capital Project Update

Hi everyone- The construction fences are going up at Golden Gate Heights. The playground and picnic area are currently fenced off. Later in the project, the upper lawn will be fenced as well. The first step will be removing four trees and installing a new...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

Golden Gate Park Golf Clubhouse Project Update 10/29!

Capital Project Update

Planning and Design for the Golden Gate Park Golf Clubhouse Project is moving along nicely and  the design team is working hard to complete the construction documentation. We intend to put the project out to bid in early 2021. 

Anticipate...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

Herz Playground Project Update 10/29!

Capital Project Update

Thank you so much to those who joined us for our final community meeting. To see the presentation please see our project webpage under Documents & Materials tab or click here. We also passed an important milestone, which was presenting the project to ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

Herz Recreation Center Project Update 10/29!

Capital Project Update

Hi everyone- We have been busy working with the project architects to develop the technical side of the design and begin the various regulatory reviews. We hope to return to the community soon for a final virtual community meeting to review the concept de...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

Rossi Pool Project Update 10/28!

Capital Project Update

Much progress has been made over the past couple months on the utilities, sitework and interiors. Highlights include formwork for the new North Stairs, Mechanical Enclosure steel columns, and Boiler System connections in the basement.

On the interiors, wal...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

Esprit park Project Update 10/29!

Capital Project Update

Hi everyone - We are getting organized for a virtual community workshop. Stay tuned for an announcement on the date/time. If you would like to be on the project contact list, please send an email to Project Manager, Alexis Ward, at alexis.ward@sfgov.org.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

McLaren Park Redwood Grove Playground is Open for Play!!!

Capital Project Update

Hi everyone- We are officially open for play! Woohooo! Please continue to adhere to posted signage and local health orders. Once the picnic site is available for permitting, it will be available to reserve on our website. https://sfrecpark.org/426/Picnic-...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 29, 2020

Jackson Playground Planning Update 10/29!

Capital Project Update

The project team is working on developing an overall project budget and securing agency approvals. We will re-engage with the community in the coming months to get additional input on the design of the building and park improvements. Send your questions a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 27, 2020

Garfield pool Renovation Update 10/27!

Capital Project Update

The major construction activities have been completed and we are near the finish line on this much anticipated addition to the neighborhood! The Design and Construction teams have been working hard, and much progress has been made over the past couple of ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 22, 2020

Margaret Hayward Project Update 10/20!

Capital Project Update

We still have many utility inspections to go; however, to round off the Margaret S. Hayward Playground Renovation, tennis courts will be CLOSED for resurfacing from10/26 through mid-November 2020.

 Over the last two years, tennis courts r...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 14, 2020

Jerry Garcia Amp - Construction Slated to Begin November 2020!

Capital Project Update

The project has been advertised and we plan to award the contract this month, with construction to start in November. We intend to phase the work as much as possible to allow access to the overall amphitheater area during construction.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 14, 2020

Children’s Play Area Now Open at West Portal Playground!

Capital Project Update

The contractor has a few minor items remaining, including some work around the playground fencing. This may require closure of the children’s play area for 1-2 days, which we’re targeting for the last week in October. Thanks for your patience as parts com...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 13, 2020

We are excited to report that Bay View Playground Renovation has started - 10/13!

Capital Project Update

Construction fences were installed last week to prepare for demolition next week. The long-awaited renovation features a new ballfield, new playground, fitness equipment, new lawn for gathering and accessible pathways throughout the park. 

&nb...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 13, 2020

Fillmore/Turk Mini Park Project Update 10/13!

Capital Project Update

So much to report!

Building permit application was submitted to DBI this week. Bid advertisement target will be late October/early November. 

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 13, 2020

George Christopher play equipment installed, fence work underway, and planting!

Capital Project Update

The play equipment is now installed at George Christopher! As are most of the new light posts. The project has really taken shape over the last month, as you can see from the photos. You’ll see people repainting the posts and installing new chain link at ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 13, 2020

Sergeant John Macaulay Playground ready for opening!

Capital Project Update

The site is getting final touches to be ready for opening. The community can look forward to a brand-new site, including new swings, a ship-themed play structure, new plantings, seating and art throughout! Thank you to all who have participated in the dev...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 13, 2020

Portsmouth Square Schematic Design Complete! (10/13)

Capital Project Update

The project has reached an important milestone as schematic design wraps up. The team has maintained all aspects from the concept design while integrating much more technical information into the project, as well as meeting with various committees and reg...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 9, 2020

Gene Friend Rec Project Update 10/9!

Capital Project Update

Gene Friend Recreation Center has been included as a project that would receive funding through the Health and Recovery General Obligation Bond, which is included on the November 2020 ballot. For more information, please click here. The project team is cu...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 9, 2020

Geneva Powerhouse Project Update 10/9!

Capital Project Update

We are excited to announce that our tenant, the Performing Arts Workshop, is in the process of moving into the Powerhouse. The site is also being considered for the City’s learning hubs program. Thank you to our project architect, Aidlin Darling Design, a...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 9, 2020

Merced Heights Playground Lower Lawn Terrace Project Update 10/9!

Capital Project Update

A community meeting was held in November 2019 to review preliminary designs for a transformation of the lowest terrace of Merced Heights Playground. A second community meeting was planned for March 2020 but was cancelled due to the onset of COVID 19 virus...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 9, 2020

Merced Heights Lower Lawn Terrace Project Update 10/9!

Capital Project Update

A community meeting was held in November 2019 to review preliminary designs for a transformation of the lowest terrace of Merced Heights Playground. A second community meeting was planned for March 2020 but was cancelled due to the onset of COVID 19 virus...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 9, 2020

West Portal Playground Project Update 10/8!

Capital Project Update

The restored field, as well as the nature exploration area, picnic area, and clubhouse restrooms, are now open (as of September 17)!  The children’s play area will be opened to the public pending confirmation with public health officials (anticip...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 7, 2020

Ocean Beach Climate Adaptation Project Update 10/7!

Capital Project Update

Planning and design is ongoing for this project and we are planning on holding a community meeting in December.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 7, 2020

Visitacion Avenue Crossing Project Update 10/7!

Capital Project Update

We are awaiting bid results for this project and hope to be in construction by the end of the year.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 7, 2020

Francisco Park Construction Update 10/7!

Capital Project Update

Francisco Park construction is moving along at a rapid pace while the contractor continues to carefully adhere to the City’s required COVID-19 health and safety guidelines for construction sites. As you can see in the photos, the above ground work is real...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 7, 2020

Buena Vista Park Needs Assessment and Cost Estimate Update 10/7!

Capital Project Update

A presentation of the Needs Assessment and Cost Estimate report was made to the Rec Park Commission in October.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 7, 2020

Golden Gate Park Stanyan Edge Project Update 10/7!

Capital Project Update

Hello Park Advocates, 

Wanted to give a quick update on the this project. As mentioned in our last post, the contractor will be working on a few outstanding improvement items. This includes adding chains between all the new bollards, minor irrigat...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 7, 2020

Golden Gate Park Tennis Center Project Update 10/7!

Capital Project Update

The Tennis Center construction continues to move forward with finishes and technology in the building and site work on the exterior that shows what the facility will look like when it is complete. The contractor has been busy with finishes inside the buil...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 5, 2020

Bay View Playground Construction is just about to start!

Capital Project Update

The perimeter fences were installed last week and pre construction preparations are in place for demolition. Stay tuned for the start of this transformation.

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 5, 2020

Margaret Hayward Project Update 10/5!

Capital Project Update

The construction completion getting closer, but not quite ready yet…..inspections are half way through and systems testing starts next week.

See the finishing touches in these photos that speak for themselves…..

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 2, 2020

Herz Playground Project Final Community Meeting!

Capital Project Update

Since we cannot meet in person, join us virtually via Zoom. Please help us spread the word that there will be Chinese and Spanish translation available.

Time: Oct 13, 2020 06:30 PM 

Join Zoom Meeting

https://sfrpd.zoom.us/j/98363855194

Meeting ID: 98...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 21, 2020

Middle Lake Design Pushing Forward 9/21!

Capital Project Update

The talented design team for the Middle Lake Rehabilitation is nearing completion of the 50% design phase. This will include detailed information about planting, layout and the inner workings of this artificial wetland system. As we narrow in on a complet...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 21, 2020

Juri Commons Construction continues 9/21!

Capital Project Update

Demolition is nearing completion and the Juri Commons Renovation is underway. During the course of site demolition several faulty utilities were discovered, and although replacing them will add some weeks to the overall schedule we are still hoping to hav...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 21, 2020

Richmond Playground Concept Design Moving Forward 9/21!

Capital Project Update

Thank you so much to all who attended the third and final community workshop and to all who have contributed feedback along the way. On August 13th we held a final community workshop to celebrate and gather feedback on the final concept design for Richmon...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 18, 2020

McLaren Group Picnic Area and Playground Project Update 9/18!

Capital Project Update

Hi folks- We have completed installing the new table tops and barbecues. We are currently wrapping up the landscaping and irrigation near the restroom. The final step will be to get sign off on our building permit. Once this is done and when local health ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 18, 2020

Willie "Woo Woo" Wong Playground Update 9/18!

Capital Project Update

The Willie “Woo Woo” Wong project is quickly approaching completion! Here are a few recent photographs from the site. If you are in the neighborhood, peek through the windows on Waverly to see inside the clubhouse, the beautiful new mural, and all the way...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 18, 2020

Golden Gate Heights Playground Construction Has Begun!

Capital Project Update

Hi folks- Construction has officially begun on the project! The contractor will start with paperwork. The fences will go up on-site in October. As a reminder, the upper field and playground will be closed to the public during construction. For questions p...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 18, 2020

Herz Recreation Center Project Update 9/18!

Capital Project Update

Hi folks- The project team has been working to incorporate all the community feedback that we heard this summer. We hope to organize a final community meeting this Fall. For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org.

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 18, 2020

Esprit park Project Update 9/18!

Capital Project Update

Hi all- We are planning for additional community outreach this Fall. If you would like to be on the project contact list, please send an email to Project Manager, Alexis Ward, at alexis.ward@sfgov.org. Current project graphics are available under the Docu...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 18, 2020

Construction is Completed for the Stanyan Street Edge of Golden Gate Park!

Capital Project Update

Hello,

If you haven’t noticed yet, all the construction fencing has been removed on the project that the public should have full access to the east edge of the park. Over the next couple of weeks, you will most likely see small construction crews completin...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 18, 2020

Herz Playground Project Update 9/18!

Capital Project Update

Hi all- Our project designers have been updating the playground design to reflect the survey results on the play equipment. We are also starting to plan a virtual community workshop for October. To receive notifications about the meeting please e-mail Pro...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 21, 2020

Guy Place Project Update 8/21!

Capital Project Update

Hi all- This will be our last blog update for the project. The park is open and we hope you all are enjoying it! We are wrapping up a small amount of finishing touches on-site and we are completing all the paperwork to official close the project. Thanks a...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 21, 2020

George Christopher Playground project Update 8/21!

Capital Project Update

Cheers George Christopher Community,

There has been tremendous progress on George Christopher Playground Renovation this summer. The irrigation mainline piping has been installed, the concrete and CMU walls around the plaza and ramp area are almost complet...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 21, 2020

Golden Gate Heights Construction Starting Soon!

Capital Project Update

Hi everyone- We are getting close to the official start of construction! We will notify neighbors prior to the construction fences going up. We recently posted four trees nearly the park entrance that will be removed due to their condition. We will be rep...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 21, 2020

Herz Rec Center Project Update 8/21!

Capital Project Update

Hi everyone! Thanks to those who participated in our focus group meetings. We have uploaded the presentation on our website under the Documents tab. The next step is for the project team to continue work on the design of the building and park. We will ret...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 21, 2020

McLaren Group Picnic Area and Playground Project Update 8/21!

Capital Project Update

Hi all- We are close to wrapping up work at the new Redwood Grove Playground! Our next step is replacing the table tops and benches and a small amount landscaping near the restroom. We hope to open soon if local health orders permit us. For questions plea...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 21, 2020

Herz Playground Project Update 8/21!

Capital Project Update

Hi all- Thank you so much to everyone who participated in our online survey! We had a great response with over 150+ respondents. The Parks Alliance will be helping to raffle off the Safeway gift card to one lucky participant! The next step will be for the...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 21, 2020

Esprit Park Project Update 8/21!

Capital Project Update

Hi all- We are working on details for additional community outreach in the next few weeks. Once we have finalized our plans we will share them here and send out updates to everyone on our project contact list. If you would like to be included, please send...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 19, 2020

Bay View Playground Renovation Pre-Construction Preparations

Capital Project Update

The awarded contractor is in the final stages of certification (meaning the back ground check and paperwork has been completed) and we are expected to give them the go ahead “notice to proceed” with construction next month!

In preparation, we are clarifyin...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 10, 2020

Buena Vista Community Meeting 6/2/20 Notes and Presentation

Capital Project Update

Thank you to the 80 community members who stepped into the unknown with the Project Team for our June virtual community meeting! Thanks for your comments and questions and for bearing with us as we worked with the new technology.

Click here for the 6/2/20 ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 6, 2020

Jackson Playground Meeting Follow-Up

Capital Project Update

Thank you for joining us for the Virtual Meeting and for your patience as we navigate this new medium. We appreciate you taking the time to participate.

If you would like to listen to the meeting please click here and be sure to use this password 1Q+=@4e7....

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 6, 2020

Juri Commons Construction is Underway!

Capital Project Update

We have broken ground! Renovation of Juri Commons Park is underway and major demolition activities are nearly complete. Notice to Proceed was received on the 14th of July and we expect six months of construction after which this wonderful new park will be...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 6, 2020

Join us to discuss the final concept design for Richmond Playground!

Capital Project Update

Please join us for a final community meeting to celebrate and discuss the final concept design for the upcoming renovation of the play area at Richmond Playground. This virtual meeting will be the final of three community events hosted by SF Rec and Parks...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 31, 2020

Margaret Hayward Project Update 7/31!

Capital Project Update

The construction continues revealing the vision and beauty of this park! See the recent photos.

The building is enclosed! The interior furnishings have arrived and interior detailing truly expresses warmth of the wood, durability of concrete and steel, cla...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 29, 2020

Buena Vista Park Needs Assessment and Cost Analysis Final Report is Published!

Capital Project Update

Thanks to the community and the project team, we are proud to present the Buena Vista Park Needs Assessment and Cost Analysis Final Report and Appendix. This was a tremendous effort and we are pleased with the comprehensive fina...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 27, 2020

Golden Gate Heights Playground Project - Construction Starting Soon!

Capital Project Update

Hi all-

The contracts are getting signed and we are looking forward to starting construction very soon! As soon as we know when the construction fences will be installed, we will update this page. Thank you to all the community members who helped make this...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 27, 2020

Guy Place Mini Park is Officially Open!

Capital Project Update

Hi everyone- We are officially open! Thank you to all the community members and City staff that have helped make this project a reality! We hope you can get out and enjoy the park.

Thank you and take care!

RPD Park Improvements | All Project Updates
Posted on: July 27, 2020

McLaren Group Picnic and Playground Project Update 7/27!

Capital Project Update

Hi everyone- We are continuing to finalize the entrance area at the new playground and restroom. Our next step will be replacing all the table tops and benches on the picnic tables. We are hoping to wrap up in August. Send questions to Project Manager, Al...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 27, 2020

Herz Rec Center Project Update 7/27!

Capital Project Update

Hi all- Thank you so much to those who participated in our virtual community meeting! We will be uploading the design presentation and meeting notes next week. Our next step is to conduct focus groups. If you would like to included or have a suggestion fo...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 27, 2020

Herz Playground Project Survey Still Open!

Capital Project Update

Hi everyone- We have had a great response to our survey and we are going to keep it open a little longer to make sure all neighbors have a chance to participate!

Click here to take the survey in English: Herz Survey

Haga clic aquí para realizar la encuesta ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 24, 2020

Esprit Park Project Update 7/24!

Capital Project Update

Hi Everyone,

We had a meeting of the Esprit Park Advisory Group and associated meeting materials are available under the Documents & Materials Link on our website. The meeting was also recorded and is available by clicking here (Access Password is: EBa...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 23, 2020

Garfield Pool Project Update 7/22!

Capital Project Update

Much progress has been made over the past couple months on the utility and sitework, including concrete curbs, walls, paving and ramps, regrading, as well as installation of irrigation systems, water service, PG&E power, and gas service. The multi-pur...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 21, 2020

Esprit Community Advisory Group Meeting 7/23/2020!

Capital Project Update

The next ECAG meeting will take place on Thursday, July 23 from 3-4:30. If you would like to attend please RSVP here: https://tinyurl.com/ECAG723.

RSVP is encouraged but not required. Thank you! Send question to Alexis.Ward@sfgov.org.

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 10, 2020

Herz Recreation Center Virtual Community Meeting 7/18!

Capital Project Update

Hi everyone-

We are excited to announce that we will be hosting a virtual community workshop in partnership with Mercy Housing and Related CA. The meeting will be held on Saturday, July 18 from 11am-12pm on zoom. We will be updating the community on the cu...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 26, 2020

Golden Gate Heights Project is about to start Construction!

Capital Project Update

Hi folks-

We have great news to share! Yesterday, the San Francisco Recreation and Park Commission approved the construction contract award for the Golden Gate Heights Playground and Field Renovation Project!

The next step is for the contract and other pape...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 26, 2020

McLaren Group Picnic and Playground Project Update 6/25!

Capital Project Update

Hi everyone, the construction team has been working hard at McLaren. The playground work is nearly complete and the restroom was installed yesterday!!For questions contact, Alexis Ward, at alexis.ward@sfgov.org.

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 26, 2020

Take a Brief Survey to Help Us with the Herz Playground Renovation!

Capital Project Update

Hi everyone-

During these times of civil unrest, we hope that parks can provide essential spaces for gathering, recreating and connecting to nature. We would like to hear from you, the community in Visitacion Valley and Sunnydale, to make sure we are build...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 15, 2020

GGP Dog Training Area: Construction Underway!

Capital Project Update

Construction is underway at the Golden Gate Park Dog Training Area!

Our contractor has quickly demolished the existing fencing and scraped away the top surface of sand, removed the asphalt parking lot, and removed stumps from last fall’s tree removals. Exi...

Read on...

Return to the project page RPD Park Improvements | All Project Updates
Posted on: June 15, 2020

George Christopher Update: Construction Moving Quickly

Capital Project Update

Construction is moving apace at George Christopher! The focus of late has been shaping the various walls for the new plaza, planters, and ramps between the clubhouse and the playgrounds. You can see how the removal of several courses of concrete masonry u...

Read on...

Return to the project page RPD Park Improvements | All Project Updates
Posted on: June 12, 2020

GGP Tennis Center Construction Update June 2020

Capital Project Update

The Tennis Center construction is moving along on schedule and despite some delays due to COVID-19 the Tennis Center is still on track for a late fall opening. 

The contractor has completed all behind the walls and ceiling utility infrastructure a...

Read on...

Back to the project page RPD Park Improvements | All Project Updates
Posted on: June 8, 2020

Esprit Park Project Update June 2020

Capital Project Update

Hi everyone-

The project team is scheduling the next ECAG meeting and broad community outreach will follow. Anyone that would like to receive project specific updates should email Project Manager, Alexis Ward, at alexis.ward@sfgov.org. Thank you a...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 8, 2020

Margaret Hayward Project Update June 2020

Capital Project Update

Exciting progress! The athletic field and playground are 95% completed, the building is 85% completed, and the entrances and plaza are 75% completed. Once utilities are installed, connected and tested…the finishing touches will seal the deal!

We are thrill...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 3, 2020

Follow Up from 5/20/20 Virtual Community Meeting

Capital Project Update

Thank you to the 40 community members who stepped into the unknown with the Project Team for Rec and Parks first virtual community meeting! Thanks for your comments and questions and for bearing with us as we worked with the new technology.

Click here for ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 28, 2020

Merced Heights Project Update 5/28!

Capital Project Update

Merced Heights Playground Renovation scope of work includes a new children’s play area, upgrades to the clubhouse restrooms and utility/mechanical room for code requirements and accessibility compliance, clubhouse exterior painting, sport courts new light...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 28, 2020

Shoreview Park Project Update 5/28!

Capital Project Update

The $1,784,000 contract awarded to JDB & Sons Construction for Shoreview Park Renovation Project started construction on November 18, 2019 and is currently 45% complete. The original substantial completion date of June 14, 2020 is extended to October ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 22, 2020

Herz Playground Project Update 5/22

Capital Project Update

Hi everyone-

We are putting finishing touches on our playground survey and getting it translated into multiple languages.

Check back soon for a link to the survey or email Project Manager, Alexis Ward, at alexis.ward@sfgov.org to receive project updates.

Tha...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 22, 2020

Golden Gate Heights Playground Project Update 5/22!

Capital Project Update

Hi everyone-

We are moving forward with awarding the construction contract on the project next month! We will be presenting the project to the Recreation and Park Department Commission, Capital Committee on June 3rd for contract award. Construction is plan...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 22, 2020

Guy Place Project Update 5/22!

Capital Project Update

Hi everyone-

The contractor on Guy Place Mini Park has been busy finalizing details on-site such as installing wire mesh around the columns and installing planter railings. Work will be complete very soon and we appreciate everyone’s support and patience w...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 22, 2020

Esprit Park Project Update 5/22

Capital Project Update

Hi all- The project team is completing the design updates and we are looking forward to sharing them with the community this summer. For any questions please contact project manager, Alexis Ward, at alexis.ward@sfgov.org. Take care!

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 22, 2020

Herz Recreation Center Project Update!

Capital Project Update

Hi all! The Herz Recreation Center Project has been placed on the 2020 Health & Recovery Bond. The project team will be continuing to develop the design in the coming months and we are looking forward to connecting with community members to get their ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 21, 2020

Buena Vista Park Needs Assessment and Cost Analysis Virtual Meeting #3

Capital Project Update

With current social distancing due to the COVID-19 pandemic, Rec and Park is continuing community engagement virtually. Please join us online for a presentation and question and answer forum for the third and final community meeting for the Buena Vista Pa...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: May 20, 2020

McLaren Trails Virtual Community Meeting TODAY 4pm

Capital Project Update

The next community meeting for the McLaren Trails Priority Improvements Project will be online TODAY at 4pm.

Please follow this link to join: https://bit.ly/mclarentrailsvirtualevent1

Please note that the meeting is accessible in Spanish, Traditional Chines...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 15, 2020

Francisco Park construction has restarted!

Capital Project Update

Francisco Park construction has restarted after being paused under the City’s shelter-in-place order. The contractor is adhering to the City’s required COVID-19 health and safety guidelines as they are getting back up and running. The contractor is contin...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 13, 2020

Garfield Pool Project Update 5/13!

Capital Project Update

Construction has continued through Shelter In Place, albeit at a reduced pace. The glass installation is nearly complete, of which the art-glass mural is now completely installed on the west face of the pool building (photos enclosed). The sitework around...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 13, 2020

Golden Gate Park Tennis Center Construction Update 5/13!

Capital Project Update

The Tennis Center construction team continues to move forward with construction as they adhere to all safety protocols for workers during COVID-19 shelter in place. This is great news for the construction schedule and opening the courts this fall.

The boar...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 12, 2020

Construction continues on Stanyan Edge Project

Capital Project Update

Hello Park Advocates,

After a months long pause on our project, we have finally given the green light for the contractor to begin work again. Over the next 4-6 weeks you will the contractor wrapping up work in the Oak Woodland, Haight Street and Page Stree...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 6, 2020

West Portal Playground Project is Nearing Completion!

Capital Project Update

We are excited to report that the renovation of the West Portal Playground is nearing completion. Please stay tuned as we work to figure out what that means while we are still under Stay at Home public health directive. Here are some specifics:

  • Playground ...
Read on...

RPD Park Improvements | All Project Updates
Posted on: May 4, 2020

George Christopher Playground Construction to Resume after Pause for COVID-19 Social Distancing

Capital Project Update

I hope you are well and finding opportunities to connect with nature and virtually connect with community during this time of sheltering in place.

Construction proceeded off and on through the winter and early spring, when COVID 19 public health orders put...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 4, 2020

Conceptual Design Process Continues for McLaren Trails Priority Projects

Capital Project Update

I hope you are well and finding opportunities to connect with nature and virtually connect with community during this time of sheltering in place.

I’m posting this blog with immense gratitude for our urban parks: the home these lands provide for myriad spe...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 4, 2020

Geneva Car Barn Phase I construction is nearly complete!

Capital Project Update

We are happy to report that construction has reached substantial completion as of April 15, 2020. The project is expected to reach final completion by the second half of June; however, a couple items have been impacted by the COVID-19 situation so please ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 4, 2020

Bay View Playground Renovation – Bid/Award Update

Capital Project Update

Four bids were opened on April 15, 2020 after an extended bid advertisement. The result will be presented at the Recreation and Park Commission -Capital Committee with recommendation for award on May 6, 2020, 2PM.

The Capital Committee will be a ‘phone in’...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 4, 2020

Construction at the Golden Gate Park Dog Training Area Starting Soon!

Capital Project Update

I hope you are well and finding opportunities to connect with nature and virtually connect with community during this time of sheltering in place.

It’s been a whirlwind since taking over Golden Gate Park Dog Training Area project from previous Project Mana...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 1, 2020

Guy Place Project Update 5/1!

Capital Project Update

Please see the photograph of the artist fence and the metal columns that have been installed at Guy Place Mini Park. For questions please contact Project Manager, Alexis Ward, alexis.ward@sfgov.org.

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 1, 2020

Margaret Hayward Project Update 5/1!

Capital Project Update

Warm weather has arrived an allowed us to keep moving. Check out the real progress.

Looking sharp….50% of the glass is in!

Public restroom is almost completely sealed

From the bleachers, “Play Ball!....well, not quite, but almost.

These tiers will showcase pl...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 1, 2020

Willie "Woo Woo" Wong Play Equipment Installed!

Capital Project Update

The custom play equipment has been installed and looks incredible.  We hope you enjoy these "sneak peeks" of the future children’s play area.

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 17, 2020

Golden Gate Heights Playground Project Update April 17

Capital Project Update

Hi all, we are continuing to work closely with the Public Works Contract Administration team to review the contractors’ bids and qualifications. We are hoping to award the contract at the Rec & Park Commission in the coming months and start work on-si...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 17, 2020

McLaren Group Picnic Area Playground and Restroom Update 4/17

Capital Project Update

The updated Shelter-in-Place Order has place additional restrictions on construction projects and we are required to pause work on-site at this time.

We are getting close to the end of construction and we are looking forward to resuming once it is safe to ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 17, 2020

Bernal Trails Construction Update 4/17

Capital Project Update

Construction work activities at Bernal Heights have been suspended through the duration of the Shelter in Place order.  Fortunately, all trails are now open and while there is still some finishing work to do, we expect it to be wrapped up within ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 17, 2020

Willie “Woo Woo” Wong Playground – Play Equipment Delivery

Capital Project Update

The playground construction is continuing, with an exciting feature arriving next week – the custom play equipment! Here’s a sneak peak of the equipment being loaded onto the delivery truck.

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 17, 2020

Esprit Park Project Update 4/17

Capital Project Update

Hi everyone- The project is team is developing a plan for continuing community engagement digitally. We are looking forward to reaching out to the community soon with updates on the design and the outreach process. Please send an email with any questions ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 17, 2020

Herz Playground Project Update 4/17

Capital Project Update

Hi all- The project team is has developed three different options for the large play structures. We will be presenting this information to the community in an online survey, which we will share in the coming weeks. To receive notifications about upcoming ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 14, 2020

Francisco Park COVID-19 Project Update

Capital Project Update

COVID-19 UPDATE:

In consultation with the City’s health officer and the City Administrator, on-going projects were evaluated, and a determination was made on each of our current construction projects based on criteria described within the most recent healt...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 31, 2020

Sergeant J Macaulay Park Construction is Nearing Completion!

Capital Project Update

Sergeant J Macaulay Park is getting the final touches as we look towards the end of construction. If you’ve passed by recently, you will have noticed the bright red, ship-inspired playset that adorns the corner of the park. Within the past week, and looki...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 31, 2020

Japantown Peace Plaza Project Update 3/31!

Capital Project Update

You may have seen some scaffolding erected around the pagoda over the last month. This is one part of a larger seismic study we are conducting for the Pagoda. This is an important step to take to ensure public safety as we plan for future improvements to ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 31, 2020

Lake Merced Project Update 3/31!

Capital Project Update

Over the last month, we removed and pruned approximately 120 trees and trimmed overgrown shrubs primarily around the northern portions of the Lake to make for a safer pedestrian environment and provision for future improvements. To answer some questions f...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 31, 2020

Portsmouth Square Project Update 3/31!

Capital Project Update

We are excited to move towards our next phase for the Portsmouth Square improvement project! Over the last month, our design team began working on the schematic design phase. They are working to integrate the community’s feedback to ensure we provide a su...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 26, 2020

Margaret Hayward Playground Renovation Update 3/26!

Capital Project Update

The building’s ceiling sprinkler system is being installed in this photo.

The small field got turf this week! See the cork ballast being installed.

The large field, one city block in size, has almost completed the irrigation system; see photo.

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 26, 2020

Golden Gate Heights Playground Project Update March 26

Capital Project Update

Hi everyone- We have an exciting update on the Golden Gate Heights Playground & Renovation Project. Earlier this month, we received 5 bids from prospective contractors, and many of the bids were within budget! Thank you so much to those of you who hav...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 24, 2020

Bernal Heights Trail Construction Nearing Completion!

Capital Project Update

Construction work on the Bernal Trails Project is ongoing and nearing completion.  We expect to have all the newly restored trails open by early April. 

The only trail that currently has a detour is on the eastern end where the completion...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 24, 2020

McLaren Park Group Picnic and Playground Construction Update 3/24

Capital Project Update

Hi all,  work on public projects such as this one is continuing at this time. The contractor has recently installed the sod and completed installing utilities for the new restroom along John F. Shelley Drive. The focus will mostly be on restroom ...

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 23, 2020

Esprit Park Project Update

Capital Project Update

Hi everyone-

The project team has been updating the project design based on feedback from the community workshop. We are also re-grouping to determine if it is possible to continue outreach digitally during this time. Please send an email with any question...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 23, 2020

Guy Place Construction Update

Capital Project Update

Hi all-

Work on public projects such as Guy Place will continue at this time. The contractor has been focusing on installing the pavers and cobbles at the site.

We hope everyone is safe and healthy.

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: March 12, 2020

Margaret Hayward Playground is Taking Shape!

Capital Project Update

Roof is on and sealed! The building mass takes shape. The playground equipment has just arrived and is being installed. Check out the concrete slide in the distance.

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 11, 2020

McLaren Park 3/7 Trails Walk Recap

Capital Project Update

Thanks to the 25 passionate and dedicated park users who showed up for our trails walk on Saturday despite social distancing and rain! This post includes some highlights from the walk.

We opened with RPD staff sharing a summary of the McLaren Trails Priori...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 5, 2020

SGT MACAULAY PARK NEARING COMPLETION

Capital Project Update

The park is quickly headed toward completion as the play features are currently being installed. The most exciting of which is the custom ship play component! Within the next month, final paving will be installed, in addition to play surfacing and landsca...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 2, 2020

TURK-HYDE MINI PARK REOPENS!

Capital Project Update

Turk-Hyde Mini Park looks forward to it’s grand reopening! The Park will be open to the public after the grand opening celebration on Monday, 3/2/20. The newly renovated space includes beautiful plantings, boulder terrace, new play equipment, seating and ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 27, 2020

BUCHANAN STREET MALL FINAL CONCEPTUAL DESIGN COMPLETE!

Capital Project Update

The Fillmore community has been reimagining Buchanan Street Mall since late 2014, to design a safer more inclusive neighborhood space. The Vision Plan, published in 2017, offered four goals to guide design priorities for the neighborhood: connecting all b...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 27, 2020

GGP GOLF CLUBHOUSE PROJECT COMMUNITY PARTICIPATION EVENT

Capital Project Update

Join us! Meet the Designers! Please join us for an informal discussion and visioning session to rebuild the Golden Gate Park Golf Clubhouse. Give your input and learn more about this exciting project!

Date/Time:

February 29, 2020

Open House: 10:00am - 12:00p...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 26, 2020

CANCELLED: Merced Heights Community Meeting #2 on March 7

Capital Project Update

Merced Heights Playground Multi-Purpose Field Improvements Open House and Public Meeting #2 for Saturday, March 7 has been cancelled per temporary closing of the IT Bookman Community Center due to the recent City directive to cancel non-essential programs...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 21, 2020

MCLAREN PLAYGROUND & RESTROOM PROJECT UPDATE FEB 2020

Capital Project Update

Hi everyone! Work is continuing on-site with the installation of the new pathways which connect to the playground and the picnic areas. The contractor is currently installing the swings in the playground and next week they will begin to trench down John F...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 21, 2020

GOLDEN GATE HEIGHTS PROJECT OUT TO BID FEB 2020

Capital Project Update

Hi all- The project is currently out to bid, which means that potential contractors are reviewing the construction documents and pricing the work. The bids are due in early March. Stay tuned for more updates next month!

Alexis Ward, Project Manager

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 21, 2020

ESPRIT PARK RENOVATION - POP-IN WORKSHOP SUMMARY FEB 2020

Capital Project Update

Hi everyone! Thank you so much to those who attended this month’s Pop-In Workshop! We got some great feedback on the design alternatives, which are currently reviewing. In case you missed the workshop, the meeting materials are available on our website.

We...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 21, 2020

GUY PLACE PROJECT UPDATE FEB 21 2020

Capital Project Update

Hi everyone- Earlier this week, the contractor installed the new sidewalk in front of the park. Please note that this weekend, the contractor is planning to work on Saturday, Feb. 22 in order to lay out the new pavers inside the park. We apologize for any...

Read on...

Project Page RPD Park Improvements | All Project Updates
Posted on: February 21, 2020

GENE FRIEND REC CENTER PROJECT UPDATE FEB 2020

Capital Project Update

Thanks to the large group of representatives from community organizations who came out for the Recreation and Park Commission Capital Committee hearing on September 4, 2019 to support the concept design for a new Gene Friend Recreation Center. Our item wa...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 19, 2020

GUY PLACE ROAD CLOSURE FEB 19 2020

Capital Project Update

Thank you to Sup. Haney and neighbors for organizing the community meeting in early February. FYI on traffic impacts:

The contractor for Guy Place Park, may need to close a portion of the road in front of the park on Wednesday, February 19, from 10:00am-3:...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 18, 2020

TEMPORARY WALKWAY CLOSURE AT LAKE MERCED FEB 2020

Capital Project Update

Trees will be removed as part of the trail and restroom project at Lake Merced beginning Monday, February 17, 2020. During this time, the northwest pedestrian walkway will be intermittently closed to accommodate work. Please use the alternate route throug...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 11, 2020

CONSTRUCTION UPDATE FEB 2020

Capital Project Update

Construction is well underway for the Garfield Pool renovation project. The glass installation has begun, the sitework around the buildings has begun, and the interiors are fully framed. Utility work, pool equipment installation and mechanical/electrical/...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 10, 2020

GEORGE CHRISTOPHER: PROGRESS DURING THE WET WINTER MONTHS

Capital Project Update

Construction is moving along at George Christopher Playground!

The playground demo progressed quickly in the fall, and the site has been a little more quiet this winter due to rain. Until this past Friday, the soil was too wet to pour concrete due to Janua...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 10, 2020

BUENA VISTA PARK- 2ND COMMUNITY MEETING ON FEB 24

Capital Project Update

The second community meeting for the Buena Vista Park Needs Assessment and Cost Analysis project will be held on Monday, February 24th, 2020 at 7pm in the Randall Museum Theater Room, located at 199 Museum Way.

Please join us to learn about the initial pla...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 7, 2020

WASHINGTON SQUARE UPDATE- FEB 2020

Capital Project Update

What’s going on with the grass at Washington Square? 

You may have noticed areas of grass are sometimes cordoned off at Washington Square this winter. Here’s the good news: It is temporary and normal while the sod is in its root establishment peri...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 6, 2020

MCLAREN PLAYGROUND/GROUP PICNIC PROJECT UPDATE FEB 2020

Capital Project Update

Hi everyone-

The contractor continues to make progress on-site. The boulders are in and they are currently working on the playground entrances. Next steps include irrigation, landscaping and asphalt paths!

-Alexis

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 6, 2020

GOLDEN GATE HEIGHTS PROJECT UPDATE FEB 2020

Capital Project Update

Hi everyone-

We have exciting news to share! We have completed the design phase of the project, and the Golden Gate Heights Playground & Field Renovation Project is officially posted on City websites for contractors! We will have a meeting at the park ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 6, 2020

GUY PLACE CONSTRUCTION UPDATE FEB 2020

Capital Project Update

Hi everyone-

We are making some good progress on-site and the contractor has installed the granite stone, which is a focal point in the new park. We are also busy planting trees and working on the new irrigation system. Next steps will include installing t...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 5, 2020

NEXT TRAIL WALK SCHEDULED FOR MARCH 7

Capital Project Update

We will have our second trails walk in the concept design process on Saturday, March 7th from 10 a.m. to 12 p.m.

Meet at the upper reservoir parking lot, across from the water tower on John F. Shelley Dr.

We’ll be reviewing the trail and restoration work pr...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 3, 2020

CONSTRUCTION UPDATE- FEB 2020

Capital Project Update

Construction is nearing completion on the Geneva Car Barn & Powerhouse Phase 1 improvements. Street trees and plants went in the ground in early 2020. The site received power, thanks to PG&E and PUC staff, on January 31st. The contractor is workin...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 31, 2020

ESPRIT PARK WORKSHOP- CONCEPT PLAN

Capital Project Update

Hi all-

We are excited to announce an upcoming workshop to help finalize the concept plan for the renovation of Esprit Park on February 1 from 11 a.m. to 2 p.m. at Piccino Coffee Bar in San Francisco.

Please see the attached flyer for meeting information. F...

Read on...

Event Flyer RPD Park Improvements | All Project Updates
Posted on: January 29, 2020

Lafayette Park Lighting - Project Update- JAN 2020

Capital Project Update

The Rec and Park project manager is working with colleagues in various divisions and with the Friends of Lafayette Park to finalize the scope of lighting improvements. Considerations for finalizing scope include cost and product durability. We’re also wor...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 29, 2020

Alice Chalmers Playground Construction Update | JAN 2020

Capital Project Update

Dear Playground Advocates,

Construction activities continue at the Alice Chalmers Playground.

The contractor, Azul Works, Inc., has completed the installation of most of the playground equipment, including the Cubic Fort (tower), the slide, swing set, and n...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 29, 2020

West Portal Playground Renovation - Playground Equipment Installation

Capital Project Update

The playground is looking colorful, as the contractor has begun installing playground equipment! Once they complete playground equipment installation, they will be starting on the nature exploration area. Stay tuned for more updates.

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 29, 2020

Juri Commons Renovation Moving Forward!

Capital Project Update

Construction documents are complete and we expect to receive contractor bids by early February, putting us on track to begin construction this summer. Because the site is uniquely narrow we expect the whole park to be closed for six months through the dur...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 27, 2020

Richmond Playground Open House and Design Workshop

Capital Project Update

Please join us for an Open House and informal design workshop!

Give your input on concept designs for the upcoming renovation of the play area at Richmond Playground. The Open House will be an opportunity to express your priorities regarding playground the...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 6, 2020

Construction Update JAN 2020 | Youngblood Coleman Synthetic Turf Replacement Project

Capital Project Update

Contractors have begun removing the old synthetic turf and infill at the soccer field.  Other improvements around the soccer field include replacing the fencing, installing new lights, repairing the bleachers and repainting the restroom.

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 6, 2020

Jerry Garcia Amphitheater - CONSTRUCTION DOCUMENTS AT 60%

Capital Project Update

The concept design was approved by the Rec Park Commission and we are currently reviewing the 60% drawing set. 

By: Monica Scott 

RPD Park Improvements | All Project Updates
Posted on: January 6, 2020

ROSSI POOL RENOVATION PROJECT UPDATE

Capital Project Update

Rossi Pool Renovation Project is moving forward as scheduled.   Work has included demolition of old infrastructure and equipment and the contractor is starting on new structural improvement work.  All going as planned.

By: Dan Mauer

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 6, 2020

Bernal Heights - CONSTRUCTION ONGOING

Capital Project Update

Trail improvements southern trail (across from Ellsworth Street) have been completed with new box steps and seeding.  The western trail (starting across from the Esmeralda Stairs) is nearing completion with the final run of stairs installed and b...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 4, 2020

GENE FRIEND REC CENTER PROJECT UPDATES

Capital Project Update

We have our final concept design for the new rec center and are just wrapping up environmental review with SF Planning. We now anticipate going to the Rec and Park Commission in April 2019.  Please stay tuned for confirmation of this and details ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 31, 2019

Fillmore Turk Mini Park Community Meeting

Capital Project Update

Join the New Community Leadership Foundation and San Francisco Beautiful to review the scope of work, schedule and budget for potential for improvements to the Fillmore Turk Mini Park. The second meeting will take place on Monday, May 13 from 6 to 7:30 p....

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 18, 2019

HERZ PLAYGROUND

Capital Project Update

Hi everyone- The project team is refining the draft concept plan for the playground and getting a preliminary concept estimate done. We are looking forward to going back to the community with the overall design and options for different play equipment. To...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 18, 2019

ESPRIT PARK COMMUNITY OUTREACH UPDATE

Capital Project Update

Hi everyone! We had a great time at the Pop-Up Playdate in November! We are looking forward to continuing outreach efforts in the New Year. Check back for updates on the schedule for a community workshop! 

By: Alexis Ward 

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 11, 2019

WASHINGTON SQUARE REOPENS- DEC 2019

Capital Project Update

Washington Square Park is now open!  And thank you to all of the partners that helped to make this a great project. See the piece John King wrote about it in the Chronicle here.

Thanks to all who came to the ribbon cutting ceremony and cel...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 11, 2019

Richmond Playground Open House- Thank You!

Capital Project Update

We had a wonderful Public Open House on November 2nd! About 50 people stopped by on a sunny Saturday morning to participate in the project by learning about the scope, making suggestions for park design and programming, voting on site elements, and engagi...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 4, 2019

Sgt. John Macaulay Park Renovation - Construction Photos DEC 2019

Capital Project Update

Some exciting updates; see below: 

Formwork for curved concrete seatwalls. The area in between will be the sloped walkway to the upper play area. 

Concrete retaining wall which will contain the upper play area. 

Concrete seatwalls ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 4, 2019

TURK-HYDE CONSTRUCTION UPDATE

Capital Project Update

A view of the boulder terrace. It will be surrounded by shade trees once complete. 

New concrete seat wall and boulder terrace. 

Footings for the shade structure with hanging benches. 

Concrete seatwall formwork. The area in the fo...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 2, 2019

TRAIL WALK #1 – VISITACION AVENUE CORRIDOR

Capital Project Update

Thanks to everyone who came out on Saturday 11/16/19 for our 1st Trail Walk in the concept design process! This was the first of several opportunities for the McLaren Park community to provide input into trail design in the four priority areas identified ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 21, 2019

SF REC AND PARK COMMISSION GREENLIGHTS OPERATOR OF GOLDEN GATE PARK TENNIS CENTER

Capital Project Update

SAN FRANCISCO – Lifetime Activities, a company that runs municipal tennis centers in five Bay Area cities, has been chosen to operate the Golden Gate Park Tennis Center when it opens next year.

San Francisco Recreation and Park commissioners voted unanimou...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 21, 2019

West Portal Playground Renovation - Tennis Court Lighting Restored

Capital Project Update

Tennis court lighting has been restored at West Portal Playground, covering both night time and morning hours. Thank you for your patience and please reach out with any questions regarding playground renovation construction to Melinda.Sullivan@sfgov.org o...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 20, 2019

CONSTRUCTION UPDATE: MCLAREN GROUP PICNIC AREA PLAYGROUND & RESTROOM

Capital Project Update

Hi folks- Work is continuing at the Group Picnic Area. The curb walls are being finished this week and the play equipment footings will start to be poured. The layout of the new paths is also taking shape. Check out our construction photos! &...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 20, 2019

Merced Heights Playground Community Meeting on November 20

Capital Project Update

In June of this year, Assemblymember Phil Ting secured a $1,370,000 State Local Assistance Grant for Merced Heights Playground to support park improvements requested by the community. Join us for a meeting to discuss the proposed scope of the Merced Heigh...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 20, 2019

HERZ- CHILDREN’S PLAYGROUND RENOVATION

Capital Project Update

Hi folks- Rec Park is working with our project landscape architect to consolidate the community feedback into one design for the playground renovation. Once this is complete, we will hold an additional community meeting to confirm that we are on the right...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 18, 2019

POP-UP PLAYDATE AT ESPRIT PARK!

Capital Project Update

Hi everyone! Join us for a fun day of play for kids of all ages at Esprit Park. Game will include a nature cart, disc golf and corn hole! Staff will be on hand to share updates on the upcoming park renovation.  We hope to see you there! Saturday,...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 15, 2019

GGP DOG TRAINING AREA – TREE WORK COMPLETE

Capital Project Update

Tree maintenance and removals are now complete at the Golden Gate Park Dog Training Area. Thank you for your patience during the temporary closure. The construction project will be advertised to prospective contractors soon and updates will be posted to t...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 15, 2019

GUY PLACE STREET UTILITIES

Capital Project Update

Construction progress has been intermittent over the past few weeks due to a unexpected conflict with street utilities in the area of the new bulb out. This issue affects both the Guy Place Mini Park project as well as the streetscape project, managed by ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 8, 2019

ALICE CHALMERS PLAYGROUND CONSTRUCTION PROGRESS UPDATE

Capital Project Update

Construction work continues at the Alice Chalmers Playground. Azul Works, Inc. has completed the installation of all site walls, retaining curbs, and the two sloped ADA walkways. Utilities, including drainage and irrigation lines have been installed below...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 8, 2019

MCLAREN PARK TRAILS AND PATHS PROJECT – SITE WALK

Capital Project Update

We are all set to have a site walk to discuss the trails and paths portion of the McLaren Park Project.

The first site walk will be of the Visitacion Avenue trail.

Meet Saturday 11/16/2019 at 9:30am at the McLaren Community Garden on Visitacion Ave.

For more...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 8, 2019

BUENA VISTA PARK – COMMUNITY SITE WALK!

Capital Project Update

Please join us for a community site walk as part of the Buena Vista Park Needs Assessment and Cost Analysis project. This walk will be led by the project team to look at areas of the park that require renovation and improvements that may be included as pa...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 7, 2019

TWIN PEAKS FIGURE 8 REDESIGN PEDESTRIAN WALKWAY UPDATES

Capital Project Update

Here are a few updates regarding the Twin Peaks Figure 8 Redesign / Pedestrian Walkway Project:

Rec and Park, in partnership with SFMTA, is supporting the SF Police Department to move the concrete barriers between the two peaks with the goal of reducing th...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 6, 2019

ESPRIT PARK RENOVATION

Capital Project Update

Hi everyone- The contract with the project landscape architect is getting wrapped up and we are looking forward to hosting a community workshop about the park renovation. Hope to see you soon! 

By: Alexis Ward 

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 2, 2019

Richmond Playground Open House

Capital Project Update

Recreation and Parks hosted an Open House regarding the upcoming renovation of the play area at Richmond Playground. The event included activities and information about the project, followed by a discussion about what you would like to see happen with the...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 1, 2019

HABITAT CONSERVATION FUND GRANT SOUGHT FOR MCLAREN PARK TRAIL IMPROVEMENTS AT VISITACION AVE

Capital Project Update

The McLaren Park Trails Improvement Project team has applied for another grant in an effort to leverage already committed 2012 Bond funding. Staff will present this grant opportunity to the Recreation and Park Commission Capital Committee on Wednesday, No...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 28, 2019

CONSTRUCTION BEGINNING SOON AT GEORGE CHRISTOPHER PLAYGROUND

Capital Project Update

After many years of community process and design, construction on the George Christopher Playground renovation will begin in early November 2019!

Starting next week, the construction team will begin installing fencing to protect trees and temporary fencing...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 28, 2019

HERZ PLAYGROUND- WORKING ON THE CONCEPT DESIGN

Capital Project Update

Hi everyone, Thank you so much to those who have provided feedback on our different design options for the Herz Playground Renovation. The design team has incorporated the feedback into one overall design for the site. We will continue to do additional ou...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 28, 2019

MCLAREN PARK GROUP PICNIC PLAYGROUND + RESTROOM

Capital Project Update

Hi everyone! We have exciting news to share. Earlier this month, the Rec Park Commission approved increasing the construction contract amount, which will allow us to add a new swing area to the playground design. This request was made by park neighbors an...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 25, 2019

GOLDEN GATE PARK TENNIS CONSTRUCTION UPDATE

Capital Project Update

The Tennis Center team is taking advantage of this great weather by moving quickly through construction. The team is shaping the building foundation in the picture below!   

By: Reem Assaf

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 24, 2019

West Portal Playground Renovation - Tennis Court Lighting Out of Service

Capital Project Update

Due to construction activities, including the need to get waterproofing work done as soon as possible, tennis court lighting is temporarily out of service. We are working to reinstate lighting as quickly as we can, anticipated sometime in November 2019.

We...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 23, 2019

NEW GUY PLACE SIDEWALK BULB-OUT COMING SOON!

Capital Project Update

A new sidewalk bulb-out (a widened area of sidewalk) is under construction in front of Guy Place Mini Park. The bulb-out will feature a new pet relief area with permeable paving and a pet drinking fountain.

By:  Brett Desmarais

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 22, 2019

GGP DOG TRAINING AREA – TEMPORARY CLOSURE WEEK OF 10/28

Capital Project Update

Please be advised that the Golden Gate Park Dog Training Area will be fully closed from Monday, October 28 through Wednesday, October 30 for tree pruning and removals.

The parking lot will also have reduced capacity on Thursday, October 31 and Friday, Nove...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 22, 2019

West Portal Playground Renovation - Construction Update

Capital Project Update

Construction is moving along on West Portal Playground renovation. The contractor is finishing up with demolition work and preparing to pour the first concrete walls and complete waterproofing scope. The Rec and Park and Public Works team has been coordin...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 18, 2019

Sgt. John Macaulay Park Renovation - Construction Update OCT 2019

Capital Project Update

Construction is in “full swing” at the park. Within the next month, much construction activity will be occurring, particularly concrete walls and paving, so you’ll start to see the park really take shape! Here are some photos highlights of the constructio...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 18, 2019

TURK-HYDE CONSTRUCTION UPDATE

Capital Project Update

Construction is in “full swing” at the park. Within the next month, much construction activity will be occurring, particularly concrete walls, paving, and the boulder terrace, so you’ll start to see the park really take shape! Here are some photos highlig...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 16, 2019

Lafayette Park Lighting - Additional Lighting Planned

Capital Project Update

Thanks to those who attended our open house on Thursday, October 3, where we reviewed plans to add lighting per request from the Friends of Lafayette Park.  In addition to the open house, the Friends of Lafayette Park also had project boards on h...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 16, 2019

Shoreview Groundbreaking Event

Capital Project Update

Amid a community celebration,  the San Francisco Recreation and Park Department broke ground today on a project that will transform Shoreview Park in the Bayview into a well-lit, accessible oasis for children to play and families to gather.

The $3...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 11, 2019

FILLMORE TURK MINI PARK – OCTOBER 2019

Capital Project Update

Exciting News!

Late September, Recreation and Park Commission approved design for Fillmore Turk Mini Park. Now, the design team can proceed with construction documents to realize the improvements initiated by Community Opportunity Fund (COF) award in 2016....

Read on...

Additional Info... RPD Park Improvements | All Project Updates
Posted on: October 11, 2019

FILLMORE TURK MINI PARK – OCTOBER 2019

Capital Project Update

Exciting News!

Late September, Recreation and Park Commission approved design for Fillmore Turk Mini Park. Now, the design team can proceed with construction documents to realize the improvements initiated by Community Opportunity Fund (COF) award in 2016....

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 30, 2019

OAK WOODLANDS TRAILS PROJECT TEAM WINS AWARD- SEP 2019

Capital Project Update

Last week, the Golden Gate Park Oak Woodlands Trails Improvement Project team, comprised of staff from Rec and Park and Public Works as well as the contractor, Yerba Buena Engineering & Construction, Inc, was honored with an award for partnering.

Partn...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 28, 2019

Alice Chalmers Playground Receives $30,000 for Makeover

Capital Project Update

SAN FRANCISCO – The San Francisco Recreation and Park Department has been selected to receive a $30,000 play space grant from the National Recreation and Park Association (NRPA) and The Walt Disney Company.

Rec and Parks will use the funding toward the cur...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 27, 2019

BUENA VISTA PARK – COMMUNITY MEETING

Capital Project Update

The first community meeting for the Buena Vista Park Needs Assessment and Cost Analysis project will be held on October 7, 2019 at 7pm in the Randall Museum Theater Room, located at 199 Museum Way.

Please join us to discuss the scope and schedule of the pr...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 26, 2019

Margaret Hayward Playground - Renovation Update

Capital Project Update

It’s been a busy summer….with lots of subsurface work (irrigation, sewer and electrical lines); however, now building is taking shape!

The basement concrete walls and ceiling were installed and now, the building’s steel structure at plaza level is being fr...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 26, 2019

West Portal Playground Renovation - Construction to Start

Capital Project Update

After a successful “Play Day” on Saturday, September 21, we are excited to report that construction will start on the playground renovation this coming week of September 30.  Rec and Park and Public Works project team members met with contractor ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 24, 2019

Lafayette Park Lighting - Project Open House

Capital Project Update

Join us for an informal open house at Lafayette Park on Thursday, October 3 to discuss plans to add lighting for the park. Staff and members of the Friends of Lafayette Park board will be available between 4:30 and 6:30 pm to review the history and scope ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 20, 2019

GGP DOG TRAINING AREA PROJECT UPDATE

Capital Project Update

The design team is putting the finishing touches on the construction drawings for the renovation of the Dog Training Area. The next steps will include a thorough review for code compliance before a building permit is obtained. Following permitting, the pr...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 20, 2019

HERZ REC CENTER PLANNING PHASE UPDATE

Capital Project Update

Hi everyone! The project team is working on developing an overall project budget. This project will be a partnership project with Mercy Housing & Related CA. We will re-engage with the community in the coming months to get additional input on the desi...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 19, 2019

ORNAMENTAL GRANITE WALL ARRIVES AT GUY PLACE MINI PARK

Capital Project Update

A fourteen foot slab of granite arrived at Guy Place Mini Park this week. The contractor is currently preparing to install it in the rear corner of the park where it will serve as an ornamental focal point to the space. Granite paving and boulders as well...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 4, 2019

Bernal Heights - SECTION OF TRAIL CLOSED DURING SEPTEMBER

Capital Project Update

Restoration and construction work will occur in segments throughout Bernal Heights Park from September 2019 through early 2020. Individual trail segments will be closed during work.  However, the overall trail network will remain mostly open and ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 29, 2019

GENE FRIEND REC CENTER CONCEPT DESIGN AT COMMISSION SEPTEMBER 4

Capital Project Update

Thanks to all of our community members who have provided valuable input since early 2015 on the feasibility study and concept design for the Gene Friend Recreation Center. I am happy to report that we will be presenting conceptual design for approval to t...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 22, 2019

JAPANTOWN PEACE PLAZA RECEIVES REC PARK COMMISSION APPROVAL!

Capital Project Update

Community –

On August 14th, the Recreation and Parks Commission unanimously approved the concept design for the Peace Plaza. The Commissioners were incredibly supportive of the entire effort and many pledged to help in any way they can moving forward. Thou...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 20, 2019

BERNAL HEIGHTS CONSTRUCTION UPDATE

Capital Project Update

Here is an overview of the work underway for this project:

Bernal Improvements

Construction crews have removed loose debris from the park road from Bernal Heights Boulevard to the Folsom Street entrance and are installing split rail fence along erosion cont...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 14, 2019

Shoreview Park Renovation Update

Capital Project Update

We are happy to inform on the progress and next steps of the Shoreview Park Renovation Project. After a widespread community outreach and engagement from October 2017 to February 2018 to jointly develop the conceptual design for renovation, the Recreation...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 19, 2019

HERZ RECREATION CENTER PLANNING UPDATE

Capital Project Update

Hi everyone! Thank you to those of you who attended our community meeting on June 22nd. We continue to get valuable input from the community on the design of the new recreation center and outdoor improvements to the park. We are anticipating hosting anoth...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 15, 2019

WASHINGTON SQUARE CONSTRUCTION UPDATE- JUL 2019

Capital Project Update

We are in the third week of construction on the Washington Square project. Azul Works has been making great progress and tree protection fencing was installed during the first week to define the areas where hand excavation is required. In the photo below ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 11, 2019

GENEVA CAR BARN CONSTRUCTION UPDATE

Capital Project Update

We are getting closer to our Fall opening timeline for the Powerhouse portion of the Geneva Car Barn!

I wanted to share some images put together by our project architects, Aidlin Darling Design of progress we’ve made.

Hope you’ve enjoyed, please email me, r...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 11, 2019

JERRY GARCIA AMPHITHEATER – CONCEPT DESIGN STATUS

Capital Project Update

We have wrapped up the community outreach process with our final meeting on June 26, 2019. I will be presenting the concept design to the Rec Park Commission in August and we will be proceeding with design development. Thank you for your feedback on this ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 11, 2019

Construction Award Update | Youngblood Coleman Synthetic Turf Replacement Project

Capital Project Update

The construction contract for this project has been awarded to Robert A. Bothman Construction Corporation and Yerba Buena Engineering. Work will commence in December 2019 and will run approximately 4 months.

Thank you for your patience while we complete th...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 29, 2019

Margaret Hayward Playground - Renovation Update - June 2019

Capital Project Update

The park is taking shape as most demolition is completed and the foundations are being formed. See the new building foundation walls and the bleacher steps after the concrete pour last Thursday! The tennis courts will be reopened on Saturday, June 29! Wel...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 26, 2019

Jerry Garcia Amphitheater Project – Community Meeting 3

Capital Project Update

June 26, 2019 @ 6:30 pm - 7:30 pm

Please join us for a community meeting to discuss improvements to the Jerry Garcia Amphitheater in McLaren Park.

Wednesday, June 26th6:30 – 7:30 PMHerz Clubhouse – (corner of Hahn St. & Visitation Ave....

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 21, 2019

CONSTRUCTION BEGINS ON ALICE CHALMERS PLAYGROUND

Capital Project Update

Just a quick update. On Tuesday, June 18, 2019, the Azul Works Inc. (Contractor) began construction at the Alice Chalmers Playground, a LetsPlaySF! project!  Due to multiple expected construction activities on site, the entire park will ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 21, 2019

India Basin - Design Survey

Capital Project Update

The San Francisco Recreation & Park Department, the Trust for Public Land and San Francisco Parks Alliance are pleased to kick-off the Schematic Design phase for the future park at the 900 Innes Boatyard at India Basin.

We are looking for your input an...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 20, 2019

GGP Middle Lake Rehabilitation Project Community Meeting

Capital Project Update

Join us to discuss future rehabilitation plans for the lake!

Thursday, June 20th6:30 – 8 PMGolden Gate Park Senior Center6101 Fulton St

For more information visit: http://bit.ly/middlelakeproject or contact Dan Mauer, Project Manager dan.mauer@sfgo...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 17, 2019

WASHINGTON SQUARE CLOSURE- JUN 2019

Capital Project Update

Washington Square Water Conservation Project set to begin this week. Construction fencing will be installed around the lawn and pathways for the Washington Square project on June 20.  During construction, the playground and restrooms will remain ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 17, 2019

Sgt. John Macaulay Park Renovation - Construction Begins!

Capital Project Update

We are in the exciting times as work on the ground has officially begun. Demolition will begin with removing the old play equipment, play surfacing and underlying concrete, as well as interior curbs, then will move to tree removal. As construction progres...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 17, 2019

CONSTRUCTION BEGINS AT TURK-HYDE MINI PARK

Capital Project Update

We are in the exciting times as work on the ground has officially begun. All major demolition is complete and next up is utility work. Stay tuned for more updates and, as always, please contact the project manager with any questions. We will be sure to po...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 15, 2019

Shoreview Park - Community Day

Capital Project Update

Join us at Hilltop Park (La Salle and Whitney Young Circle) to commemorate the upcoming renovation of Shoreview Park! Bring the family and climb high above the Bayview on our mobile rock wall! For more information, contact Paulina Araica here or ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 12, 2019

TAKE A SELFIE AND WIN OUTSIDE LANDS TICKETS!

Capital Project Update

Do you take the best selfies? Do you like parks? Here’s your chance to channel your inner influencer and win tickets to 2019 Outside Lands Music and Art Festival. We are celebrating India Basin Park coming to the Bayview Community!

Starting June 7, the San...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 10, 2019

New Mural on Historic Shipwright’s Cottage Celebrates India Basin Community

Capital Project Update

SAN FRANCISCO – Amid a neighborhood celebration, city officials today unveiled a new mural celebrating the Bayview-Hunters Point community on a historic building that will become an integral part of its future. The block party featured free food ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 31, 2019

RALPH D HOUSE COMMUNITY PARK GRAND OPENING!

Capital Project Update

The Ralph D House Community Park reopened on Wednesday May 29th!

By: Lexi Sharma


RPD Park Improvements | All Project Updates
Posted on: May 9, 2019

HAIGHT / STANYAN WORK – PUBLIC WORKS AND RECPARK COORDINATION – COMMUNITY REQUESTS

Capital Project Update

A quick update: The Department recently bid the construction contract for this renovation project and we will be awarding the contract this month.    The goal is to move into the construction phase of the project which is tentatively sch...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 1, 2019

Margaret Hayward Playground - Demolition Nearly Complete

Capital Project Update

Demolition is 99% complete – and the park is taking shape: See photos of the new community building form work and the location of the new playground nestled against Turk Street.

Thank you for your patience during construction. Due to unforeseen weather imp...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 25, 2019

SF Recreation and Park Department Breaks Ground on Five Playgrounds

Capital Project Update

SAN FRANCISCO – Under the watchful eyes of 45 preschoolers, city officials and community members broke ground today on five playground renovations—a major milestone in a project that promises to transform 13 timeworn play areas used by 20,000 children in ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 17, 2019

SF Rec and Parks Breaks Ground on $27M Tennis Center

Capital Project Update

SAN FRANCISCO – Tennis enthusiasts of all ages gathered today with City officials, the Tennis Coalition of San Francisco, and the San Francisco Parks Alliance to celebrate a new era for public tennis in San Francisco with the groundbreaking of the Golden ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 12, 2019

Let’sPlaySF! Groundbreaking

Capital Project Update

Join us and the San Francisco Parks Alliance for a groundbreaking event marking the beginning of the next five playground renovation projects under the Let’sPlaySF! initiative. The event will take place on Thursday, April 25 from 11 a.m. to noon at the Pa...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 9, 2019

YOUNGBLOOD COLEMAN COF PROJECT COMPLETE!

Capital Project Update

The drinking fountain has been installed and the grill replaced with a double wide version. The final component of this project is to install a community bulletin board and our staff is waiting for the rains to end for that to happen. We hope everyone is ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 29, 2019

Japantown Peace Plaza - COMMUNITY MEETING 3 – DESIGN AND SURVEY ARE LIVE

Capital Project Update

Hi Everyone –

Community meeting 3 on March 19th was a great success! Thank you to all who helped put the event together and to all who attended. The presentation from community meeting 3 is on our website, as well as the survey.

Please review the presentati...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 27, 2019

GARFIELD POOL – CONSTRUCTION UPDATE

Capital Project Update

We are making great progress on the construction at Garfield Pool. The old clubhouse building has been demolished, and the pool building has been cleared. The site has been a bit muddy due to the rain, but the foundation for the new clubhouse is well unde...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 19, 2019

Japantown Peace Plaza Vision Plan Meeting #3

Capital Project Update

March 19, 2019 @ 6:00 pm - 7:30 pm

The Vision Plan is a community driven process for the future of Japantown’s central public space that builds on the sites legacy.

Please join us to review a refined concept that integrates the community f...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 8, 2019

FRANKLIN SQUARE CONSTRUCTION UPDATE

Capital Project Update

The Franklin Square Improvement Project is continuing construction following the rainy weather.  During construction, the project was awarded additional funding that allowed for expanded/improved lighting and replacement of the park’s west asphal...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 22, 2019

NEW TRAIL DEDICATED TO PHIL ARNOLD- FEB 2019

Capital Project Update

The San Francisco Recreation and Park Department today unveiled its new main trail through the Oak Woodlands of Golden Gate Park, dedicating the scenic path to Phil Arnold, a longtime advocate for local parks, open space, and recreational trail opportunit...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 13, 2019

REDWOODS IN JURI COMMONS??

Capital Project Update

Not exactly, but you may have noticed some beautiful redwood logs stacked near the San Jose end of the park. Salvaged from McLaren Park, these will be part of the new natural play area in Juri Commons, just above the new slide and swing. As big as these s...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 13, 2019

Construction Update FEB 2019 | Willie "Woo Woo" Wong Playground Improvement Project

Capital Project Update

Demolition is complete and the site is now nearly a clean slate. After a hiatus for Chinese New Year, we are now beginning foundation work both in the building (what’s left of it!) and outdoors as well for the walls and ramps. After this work is done in a...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 4, 2019

TWIN PEAKS FIGURE 8 REDESIGN NEXT STEPS

Capital Project Update

Thanks again to all who came to our community open house this Spring and to those who provided input via email. We have integrated much of this feedback and have a preliminary conceptual design for a linear park or “promenade” in the location of the close...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 19, 2019

OAK WOODLANDS PROJECT UPDATE- JAN 2019

Capital Project Update

Here are a few updates on the Golden Gate Park Oak Woodlands Trails Improvement Project:

We are getting very close to construction completion!

  • Many of the trail segments are completed and open for use
  • Way finding signage will be installed in the coming days
  • L...
Read on...

RPD Park Improvements | All Project Updates
Posted on: January 10, 2019

Preparing to Bid | Youngblood Coleman Synthetic Turf Replacement Project

Capital Project Update

We are in the home stretch of preparing the bid package and plan to put this project out to bid by the end of January.

Construction is anticipated to start in December 2019 and will run approximately 4 months.

RPD Park Improvements | All Project Updates
Posted on: November 5, 2018

GENE FRIEND REC CENTER DESIGN CLEARS ARTS COMMISSION CIVIC DESIGN REVIEW PHASE 1

Capital Project Update

The Gene Friend Rec Center design team presented project design and drawings to the San Francisco Arts Commission’s Civic Design Review Committee on Monday, October 15. The Commissioners were enthusiastic and supportive of the design. The design received ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: November 1, 2018

BUCHANAN STREET MALL – COMMUNITY WORKSHOP ON NOV. 1st!

Capital Project Update

Please join us on Nov 1st as we begin to create the conceptual design for the entire five block length of Buchanan Mall. Together with our high caliber landscape design partnership of the Office of Cheryl Barton and Studio-MLA, we will begin a series of i...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 27, 2018

Schlage Lock development project - Successful Community Meeting

Capital Project Update

Saturday July 28th the Planning and Recreation and Park Departments hosted a meeting to discuss the Schlage Lock development project and plans for use of development impact fees in Visitacion Valley. 

Meeting information

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 23, 2018

Design Underway OCT 2018 | Youngblood Coleman Synthetic Turf Replacement Project

Capital Project Update

Verde Design, Inc. is moving along with the design of this project and we will be reviewing 90% construction documents shortly.

RPD Park Improvements | All Project Updates
Posted on: October 19, 2018

FRANKLIN SQUARE PAR COURSE AND LIGHTING CONSTRUCTION UNDERWAY

Capital Project Update

The construction project will be completed in early Winter 2018. 

By: Lexi Sharma 

RPD Park Improvements | All Project Updates
Posted on: October 18, 2018

Construction Underway | Willie "Woo Woo" Wong Playground Improvement Project

Capital Project Update

If you have walked by the park lately, you will have noticed big changes! Site demolition is well underway, and work inside the building will begin within two weeks. Concrete demolition will continue into November, after which things should quiet down a b...

Read on...

RPD Park Improvements | All Project Updates
Posted on: October 17, 2018

GENEVA CAR BARN CONSTRUCTION

Capital Project Update

Beautiful weather means construction is moving along smoothly at the Car Barn.  

By: Reem Assaf

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 21, 2018

ANNOUNCEMENT: GARFIELD POOL CLOSING OCTOBER 15TH!

Capital Project Update

The Recreation & Park Department is excited to announce the upcoming renovation of the Garfield Pool and Clubhouse.

The final day to swim at Garfield Pool is Sunday October 14th, 2018. Garfield Pool will be closed for renovation starting Monday October...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 20, 2018

JURI COMMONS - DESIGN RECEIVES FINAL APPROVAL

Capital Project Update

More good news!  Our conceptual design was approved this morning by the full Rec & Park Commission.  This means we are on schedule for completing the design by late winter 2019, and beginning construction by summer 2019.

Look forward ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 7, 2018

DESIGNER SELECTED FOR BUCHANAN MALL

Capital Project Update

We are excited to have The Office of Cheryl Barton (O|CB) join us as designers for the conceptual design proposals for the entire 5 block length of Buchanan Mall. O|CB was selected by a joint committee of Rec & Park, the Trust for Public Land, and com...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 7, 2018

JURI COMMONS DESIGN APPROVED

Capital Project Update

Good news!  Our conceptual design for Juri Commons, including a smooth accessible pathway, nature play, slide & swings, and lush greenery throughout, has been approved!  The RPD Commission Capital Committee approved the design on Sep...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 7, 2018

FRANCISCO PARK UPDATE

Capital Project Update

The design development for the future park at Francisco Reservoir continues to develop, providing a diversity of fully accessible public spaces, preserving dramatic mature trees, creating natural habitat, and of course maximizing the spectacular views.

In ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 7, 2018

Construction Begins! | Willie "Woo Woo" Wong Playground Improvement Project

Capital Project Update

As you may have seen, construction has just gotten underway at the park. The Construction fence is up and play equipment has been salvaged for reuse in other parks (including Portsmouth Square). Passersby may not see much outdoor activity since work in Se...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 27, 2018

Portsmouth Square Improvement Project - Workshop #5 Summary

Capital Project Update

Thanks to everyone who came out to our fifth and final community workshop on July 11th, where over 200 people attended. We are grateful for the consistently high level of engagement the Chinatown community has demonstrated throughout our community process...

Read on...

RPD Park Improvements | All Project Updates
Posted on: August 23, 2018

GENEVA CAR BARN CONSTRUCTION UPDATE

Capital Project Update

We are still moving through construction at the Geneva Car Barn. We have been removing paint and graffiti from the brick walls inside the powerhouse. Take a look for a comparison of two walls, one before and one after!

By: Reem Assaf

Read on...

RPD Park Improvements | All Project Updates
Posted on: July 11, 2018

Portsmouth Square Improvement Project - Workshop #3 Summary

Capital Project Update

Thanks again to everyone who came out to our third community workshop on October 25th. The design team is compiling the feedback received (over 250 survey responses) to incorporate into a single revised concept for our forth community workshop in early Ja...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 27, 2018

ROSSI POOL PROJECT UPDATE

Capital Project Update

Planning for the Rossi Pool renovation is moving along as the design team completes construction documents. We intend to put the project out to bid later this year – 2018.

The department anticipates keeping the pool and programming open through the fall, a...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 27, 2018

Garfield Pool Improvements - PROJECT UPDATE

Capital Project Update

The Garfield Pool Renovation is coming soon!

The Department will be opening bids for the construction contract on June 27th. The pool and programming will remain open through the summer. We anticipate closing the pool for construction in fall of 2...

Read on...

RPD Park Improvements | All Project Updates
Posted on: June 21, 2018

BUCHANAN STREET MALL PROJECT UPDATE

Capital Project Update

In March 2017, Rec & Park’s partners, the Trust for Public Land (TPL) together with Citizen Film, completed an intensive community engagement process and published a Vision Statement for Buchanan Street Mall. Based on this vision, TPL has jus...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 16, 2018

GEORGE CHRISTOPHER PLAYGROUND PROJECT IS GOING OUT TO BID SOON!

Capital Project Update

George Christopher Playground renovation includes: site work/playground renovation, paving, restroom upgrades, maintenance road work and irrigation work. We plan to go out to bid in mid July 2018 and are aiming for a construction start date December 2018....

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 16, 2018

FRANCISCO PARK PROJECT UPDATE

Capital Project Update

On March 15, 2018 the Rec and Park Commission approved the conceptual design to renovate the Francisco Reservoir. The project design team continues to refine drawings with the desire to break ground in the Fall of 2018. 

By: Peter Moore 

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 10, 2018

CALL FOR INPUT: TWIN PEAKS PROMENADE CONCEPT DESIGN

Capital Project Update

Thanks to the 30+ community members who made it out to Midtown Terrace Clubhouse for our open house this Tuesday evening to review concept design progress for a new promenade along the eastern half of the Twin Peaks “Figure 8.”

For those of you who couldn’...

Read on...

RPD Park Improvements | All Project Updates
Posted on: March 18, 2018

SF Rec & Parks Moves Forward to Add Brand New 4.5 Acre Park to San Francisco

Capital Project Update

SAN FRANCISCO – The San Francisco Recreation and Park Department (SF Rec & Parks) announced today the commission approval of conceptual design to convert 4.5 acres of former reservoir to a brand new park located atop of Russian Hill.  The Par...

Read on...

RPD Park Improvements | All Project Updates
Posted on: February 21, 2018

TWIN PEAKS FIGURE 8 REDESIGN UPDATES

Capital Project Update

Rec and Park staff, together with SFMTA staff, recommend extending the Twin Peaks Figure 8 Pilot, which uses paint and concrete barriers to designate the eastern half of the Figure 8 roadway for people walking and biking. The Pilot has been in place since...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 25, 2018

Golden Gate Park – Stanyan St. Edge Project Open House

Capital Project Update

Stop by and let us know what you think!

Open House Agenda – Share concept plan.– Outline next steps in project process.

Thursday, January 25, 20186:30 – 8:00 pmPark Police Station (see map)

For more information contact the Project Manager Dan Mauer ...

Read on...

RPD Park Improvements | All Project Updates
Posted on: January 11, 2018

Portsmouth Square Improvement Project - Workshop #4 Summary

Capital Project Update

Thanks again to everyone who came out to our fourth community workshop on January 11th, where we once again had a wonderful turn out and a packed house! Since then, the design team has been vetting the concept design from a feasibility standpoint and maki...

Read on...

RPD Park Improvements | All Project Updates
Posted on: December 26, 2017

FRANKLIN SQUARE-DEC 2017 UPDATE

Capital Project Update

Franklin Square scope of improvements has been expanded to meet access code requirements and site constraints. The specific items are:

  • Access: When the path leading to the exercise equipment is made accessible, the slope to the neighboring paths are increa...
Read on...

RPD Park Improvements | All Project Updates
Posted on: September 27, 2017

San Francisco Marina Second Annual Tenant Event

Capital Project Update

September 27, 2017 @ 4:00 pm - 7:00 pm

Marina second tenant event will take place on September 27, 2017 from 4pm to 7pm.

Come join us for live music, drinks, snacks, and the fireboat will be here for water display.

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 12, 2017

GEORGE CHRISTOPHER FINAL CONCEPT RENDERINGS

Capital Project Update

Hi Everyone!

As an update to my last post, we have updated our renderings for the George Christopher project and I wanted to share them with you today. See the link below:

George Christopher Final Concept

We will be presenting this concept to the Recreation&...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 12, 2017

TWIN PEAKS TRAILS OPENED THIS AFTERNOON

Capital Project Update

The newly aligned, more sustainable trail adjacent to Mission Blue Butterfly habitat opened to the public this afternoon!  Improvements include the replacement of deteriorated steps, new wayfinding signs, erosion control and habitat protection. T...

Read on...

RPD Park Improvements | All Project Updates
Posted on: May 7, 2018

REMINDER: MAY 8 OPEN HOUSE FOR TWIN PEAKS FIGURE 8 PROMENADE DESIGN

Capital Project Update

A reminder that this Tuesday we are hosting an Open House to review and collect input on proposed designs for the eastern half of the Twin Peaks Boulevard “Figure 8 Promenade:”

Tuesday, May 8, 20186:30 – 8:00 pmMidtown Terrace ClubhouseClarendon Ave + Olym...

Read on...

RPD Park Improvements | All Project Updates
Posted on: April 19, 2017

TWIN PEAKS ROAD PAVING AND FIGURE 8 PROJECT UPDATES

Capital Project Update

San Francisco Public Works is moving forward as planned with the second phase of Twin Peaks Boulevard repaving.  The paving work includes the portion of the “Figure 8” that is currently closed to motorists as part of SFMTA’s pilot road closure. &...

Read on...

RPD Park Improvements | All Project Updates
Posted on: September 30, 2014

Marina Bay Trail Connector Community Meeting

Capital Project Update

September 30, 2014 @ 6:00 pm - 7:30 pm

Please join us for an informational meeting on the project plans for the Marina Bay Trail, along Marina Boulevard.

GOALS OF THE PROJECT

  • Ensure safety for people walking and biking;
  • Provide uninterrupted...
Read on...

RPD Park Improvements | All Project Updates