Precita Park Improvements Project

Scope of WorkPrecita_Restroom_Render_20250626

This project will add a prefabricated, single-stall, all-gender accessible restroom, as well as related site improvements, including a drinking fountain, trash receptacle, and landscape beautification immediately adjacent to the new structure. 

Background

Rec and Park is working to install free standing restrooms in high-use parks that would benefit from this much needed feature and community asset. Rec and Park recently installed a similar prefabricated restroom facility at the Noe Valley Town Square park.

Funding

Funding for this project will come from the California State Park Specified Grant.



Estimated Project Schedule

PhaseTimeline
Planning2024
Design2024
Bid/AwardEarly 2025
Construction beginsLate 2025
Open to the publicEarly 2026


Project Updates

If you would like to receive updates about the Precita Park Improvements Project, please visit the News Flash section of our webpage and subscribe to "Rec Park Improvements: Precita Park Improvements." To receive updates about all our active projects, subscribe to "Rec Park Improvements | All Project Updates."

  1. Project Updates
  2. Documents and Materials
  1. Project Update

    Precita Park Improvements | Construction update, January 2026

    The new prefabricated restroom has arrived! Big thanks to everyone who came out to watch this morning. It was a fun atmosphere. Our staff saw neighbors standing on the play structure to get a peek and heard a Read on...
  2. Project Update

    Precita Park Improvements | Construction Advisory, January 2026

    Please be advised that we expect that the park’s new, prefabricated restroom facility will be delivered this Thursday, January 8 in the morning. This delivery was originally scheduled for the week of December 22 but was postponed due to rain. This work Read on...
  3. Project Update

    Precita Park Improvements | Construction Advisory, December 22, 2025

    Please be advised that the delivery and installation of the park’s new, prefabricated restroom facility, which was originally scheduled for this week, has been postponed due to rain. We will post an update with the new delivery date once it is Read on...
  4. Project Update

    Precita Park Improvements | Construction Advisory, December 2025

    Please be advised that we expect that the park’s new, prefabricated restroom facility will be delivered on the morning of December 24. This work will require a large crane at the intersection of Precita Ave at Harrison Street for several hours in the Read on...
  5. Capital Project Update

    Precita Park Improvements | Construction update, October 2025

    Construction has begun on the Precita Park Improvements Project! So far, our contractor, Pacific Pars, has installed construction fencing around the site and they are now working to prep the areas that will be home to the new restroom facility and Read on...
  6. Capital Project Update

    Precita Park Improvements | Project update, September 2025

    Construction will be starting soon! This project will add a prefabricated, single-stall, all-gender accessible restroom, as well as related site improvements, including a drinking fountain, trash receptacle, and Read on...
  7. Capital Project Update

    Precita Park Improvements | Project update, April 2025

    Exciting news! The purchase order for the new restroom has been issued. The Public Restroom Company will secure state-level approvals for the design and then begin fabrication of the structure. Meanwhile, we’ll be bidding out the site work soon, which Read on...
  8. Capital Project Update

    Precita Park Restroom Project | Planning begins for a new restroom at Precita Park

    We are excited to announce that we are moving forward with the planning effort to install a new prefabricated restroom at Precita Park. Rec and Park staff recently attended the Read on...
  1. Dan Mauer

    Project Manager