Let’sPlaySF! Initiative

BackgroundStacked box climbing structure with slide, swings, play structures, stacked donor blocks

Let’sPlaySF! has its origins in the $195 million San Francisco Clean and Safe Neighborhood Parks General Obligation Bond approved by 71.6% of voters in November 2012. The Bond allocated $15.5 million to renovate dilapidated playgrounds through the City.

In 2014, the Recreation and Park Commission appointed a Citizen Task Force to determine which playgrounds were most in need of renovation. The Task Force prioritized six Tier 1 and seven Tier 2 playgrounds for renovation based on four criteria: (1) the presence of Chromated Copper Arsenate (CCA) Pressure Treated Wood, (2) low Household Median Income, (3) high Youth Density and (4) low Parks Alliance Playground Report Card Grades.

In December 2014, the Recreation and Park Commission unanimously adopted the list recommended by the Task Force, of which the Department committed to renovate all six Tier 1 playgrounds and to renovate some or all Tier 2 playgrounds provided if additional funding were procured. In the wake of that determination, the Department and the Parks Alliance decided to partner on Let’sPlaySF!, a capital campaign dedicated to raising sufficient funds to ensure that all 13 playgrounds can be reimagined for San Francisco’s children. The Parks Alliance Board voted in December 2015 to undertake the campaign and in December of 2016, the Commission approved a MOU between the Parks Alliance and the Department to partner on the project and recommended that the Board of Supervisors accept up to $15 million from the Parks Alliance for the project.

Program Status

The initiative has fully completed 9 of the 13 playgrounds and are open to the public. Of the four remaining playground, Herz Playground is currently in construction. Stern Grove and Richmond are preparing for construction later in 2023. Buchanan Mall Playground has been incorporated into a larger renovation of the park and is currently in design phase. For status updates on the individual sites, click on a project.

Status of Tier 1 SitesAll Tier 1 Sties are completed and open to the public.Red play structure, blue play surface, silver metal picnic tables, pink painted flower

Status of Tier 2 Sites:

For more background and to donate through our partner, visit San Francisco Parks Alliance.


Project Updates

If you would like to sign up for updates click here and scroll down to the NewsFlash and select the alerts you would like to receive.

  1. What's New
  2. Additional Background
  3. Documents and Materials
  4. Meeting Materials
  5. Task Force Members
  1. Capital Project Update

    Construction Update- JAN 2020

    Construction activities continue at the Alice Chalmers Playground. The contractor, Azul Works, Inc., has completed the installation of most of the playground equipment Read on...
  2. Capital Project Update

    ALICE CHALMERS PLAYGROUND CONSTRUCTION PROGRESS UPDATE

    Construction work continues at the Alice Chalmers Playground. Azul Works, Inc. has completed the installation of all Read on...
  3. Capital Project Update

    Alice Chalmers Playground Receives $30,000 for Makeover

    Grant awarded by the National Recreation and Park Association and The Walt Disney Company Read on...
  4. Capital Project Update

    CONSTRUCTION BEGINS ON ALICE CHALMERS PLAYGROUND

    Just a quick update. On Tuesday, June 18, 2019, the Azul Works Inc. (Contractor) began construction at the Alice Chalmers Playground, a LetsPlaySF! project! Read on...
  5. Capital Project Update

    Buchanan Street Mall | May Community Gatherings focus on the Memory Walk

    Thanks to everyone who has participated in healing circles over the past several weeks as part of the Buchanan Street Mall Equity Action Initiative Read on...
  6. Capital Project Update

    UPDATED! - Buchanan Mall Equity in Action April Gatherings

    Community gathering scheduled for April 5 is now cancelled. Please join us for the next meeting, scheduled for April 19. Be a part of the Read on...
  7. Capital Project Update

    Buchanan Mall Equity in Action April Gatherings!

    Join our April Equity in Action gatherings Read on...
  8. Capital Project Update

    Community Gathering on March 22 | Buchanan Street Mall – Park Improvement Equity Action Initiative

    Join Us for the Next Community Healing Circle. Help shape the future of Buchanan Street Mall Read on...
  9. Capital Project Update

    Buchanan Street Mall – Park Improvement Equity Action Initiative: First Community Gathering on 3/15

    Help shape the future of the Fillmore! Your participation is key for redesigning Buchanan Street Mall Read on...
  10. Capital Project Update

    LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING.

    LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING. . . . Read on...
  11. Capital Project Update

    Memory Walk Design at Buchanan Street Mall - Community Meeting

    Core to the community-driven redesign of Buchanan Street Mall, the Memory Walk is envisioned to physically connect all five blocks of the park . . . Read on...
  12. Capital Project Update

    Buchanan Mall stage preview and last call for the Phase 1 design refinement survey!

    Design is progressing for the stage on the McAllister to Fulton block, thanks to the thoughtful input input provided by local performing art stakeholders Read on...
  13. Capital Project Update

    Buchanan Street Mall Phase 1 – Community Meeting on 2/24/2022

    It’s time to CELEBRATE! For seven years, the Western Addition community has dreamed about what Buchanan Mall could become with the right vision and resources. Those dreams are coming true! Read on...
  14. Capital Project Update

    Buchanan Mall, Turk – Golden Gate at SFAC Civic Design Review Monday 9/20

    After almost seven years of community-driven engagement and visioning, SF Rec and Parks is thrilled to be moving forward with a clear schedule for . . . Read on...
  15. Capital Project Update

    Design continues and additional funding received for Buchanan Street Mall!

    Thanks to the 174 people who participated in the survey to refine the design of Buchanan Street Mall, Turk – Golden Gate block. . . Read on...
  16. Capital Project Update

    Complete the survey to refine the design of an all-ages play area in Buchanan Street Mall

    Thanks to everyone who participated in the Virtual Community Meeting . . . Read on...
  17. Capital Project Update

    Virtual Meeting and Survey to Refine the Design for Buchanan Street Mall

    The Buchanan Street Mall project team is seeking community feedback to inform the look and feel and the specific equipment included in the new all-ages recreation area in the Turk - Golden Gate block Read on...
  18. Capital Project Update

    BUCHANAN STREET MALL FINAL CONCEPTUAL DESIGN COMPLETE!

    The Fillmore community has been reimagining Buchanan Street Mall since late 2014, to design a safer more inclusive neighborhood space Read on...
  19. Capital Project Update

    BUCHANAN STREET MALL – COMMUNITY WORKSHOP ON NOV. 1st!

    Please join us on Nov 1st as we begin to create the conceptual design for the entire five block length of Buchanan Mall. Read on...
  20. Capital Project Update

    DESIGNER SELECTED FOR BUCHANAN MALL

    We are excited to have The Office of Cheryl Barton (O|CB) join us as designers for the conceptual design proposals for the entire 5 block length of Buchanan Mall Read on...
  21. Capital Project Update

    BUCHANAN STREET MALL PROJECT UPDATE

    In March 2017, Rec & Park’s partners, the Trust for Public Land (TPL) together with Citizen Film, completed an intensive community engagement process Read on...
  22. Capital Project Update

    Golden Gate Heights Playground Update 8/20!

    We have wrapped up work on the Golden Gate Heights Playground & Field Renovation. . . Read on...
  23. Capital Project Update

    Golden Gate Heights Playground Final Construction Update 7/16!

    Hi everyone! We are thrilled to share that construction is wrapping up at Golden Gate Heights and we are opening on July 20th at 11:30. . . Read on...
  24. Capital Project Update

    Golden Gate Heights Playground is Opening 7/20!

    Hi everyone- We are thrilled to announce the opening celebration of the Golden Gate Heights Playground and Renovation Project! Read on...
  25. Capital Project Update

    Golden Gate Heights Playground Construction Update 6/21!

    Hi all, We are nearing completion of construction at Golden Gate Heights. . . Read on...
  26. Capital Project Update

    Golden Gate Heights Playground Construction Update 5/21!

    Hi everyone, The contractor has installed the sod and they are working on the remainder of the landscaping and site furnishings. . . Read on...
  27. Capital Project Update

    Golden Gate Heights Playground Construction Update 4/20!

    Hi folks- The contractor is working on flatwork around the playground including pouring concrete and asphalt for the paths and picnic area. Read on...
  28. Capital Project Update

    Golden Gate Heights Playground Construction Update 3/16!

    Hi folks- The playground equipment is installed and the contractor is working on grading the . . . Read on...
  29. Capital Project Update

    Golden Gate Heights Playground Construction Update 2/23!

    Hi everyone! The playground equipment is being installed at Golden Gate Heights! Read on...
  30. Capital Project Update

    Golden Gate Heights Playground Project Update 1/22/21

    Hi everyone! Construction is continuing at Golden Gate Heights. Read on...
  31. Capital Project Update

    Golden Gate Heights Update Dec '20

    The contractor will be working on the retaining wall on the north side of the playground Read on...
  32. Capital Project Update

    Golden Gate Heights Playground Construction Update 10/29!

    Hi everyone- The construction fences are going up at Golden Gate Heights. . . Read on...
  33. Capital Project Update

    Golden Gate Heights Playground Construction Has Begun!

    Hi folks- Construction has officially begun on the project! Read on...
  34. Capital Project Update

    Golden Gate Heights Construction Starting Soon!

    Hi everyone- We are getting close to the official start of construction! Read on...
  35. Capital Project Update

    Golden Gate Heights Playground Project - Construction Starting Soon!

    The contracts are getting signed and we are looking forward to starting construction very soon! Read on...
  36. Capital Project Update

    Golden Gate Heights Project is about to start Construction!

    We have great news to share! Yesterday, the San Francisco Recreation and Park Commission approved the construction contract award for the Golden Gate Heights Playground and Field Renovation Project! Read on...
  37. Capital Project Update

    Golden Gate Heights Playground Project Update 5/22!

    We are moving forward with awarding the construction contract on the project next month! Read on...
  38. Capital Project Update
  39. Capital Project Update

    Golden Gate Heights Playground Project Update March 26

    We have an exciting update on the Golden Gate Heights Playground & Renovation Project. Read on...
  40. Capital Project Update

    GOLDEN GATE HEIGHTS PROJECT OUT TO BID FEB 2020

    The project is currently out to bid, which means that potential contractors are reviewing the construction documents and pricing the work Read on...
  41. Capital Project Update

    GOLDEN GATE HEIGHTS PROJECT UPDATE FEB 2020

    We have exciting news to share! We have completed the design phase of the project Read on...
  42. Capital Project Update

    Juri Commons is now open to the public!

    Juri Commons is open to the public! On September 13th the city held a ribbon cutting celebration to commemorate the park’s opening with . . . Read on...
  43. Capital Project Update

    Juri Commons Construction continues8/16!

    Thank you everyone for your continued patience with this renovation project. . . Read on...
  44. Capital Project Update

    Juri Commons Construction Update 6/7!

    We’re excited to share that planting is nearing completion, embedded rails are installed in the pathway and the team is about to lay down play surfacing in the playground. . . Read on...
  45. Capital Project Update

    Juri Commons Construction Update 4/23!

    We’re excited to share that the pathways and walls are nearly complete, the play equipment is installed, planting has begun . . . Read on...
  46. Capital Project Update

    Juri Commons Construction Update 2/9!

    Juri Commons is moving forward in construction and hitting a good stride . . . Read on...
  47. Capital Project Update

    Juri Commons Construction continues 9/21!

    Demolition is nearing completion and the Juri Commons Renovation is underway. . . Read on...
  48. Capital Project Update

    Juri Commons Construction is Underway!

    We have broken ground! Renovation of Juri Commons Park is underway . . . Read on...
  49. Capital Project Update

    Juri Commons Renovation Moving Forward!

    Construction documents are complete and we expect to receive contractor bids by early February Read on...
  50. Capital Project Update

    REDWOODS IN JURI COMMONS??

    Not exactly, but you may have noticed some beautiful redwood logs stacked near the San Jose end of the park Read on...
  51. Capital Project Update

    DESIGN RECEIVES FINAL APPROVAL

    More good news! Our conceptual design was approved this morning by the full Rec & Park Commission. Read on...
  52. Capital Project Update

    JURI COMMONS DESIGN APPROVED

    Good news! Our conceptual design for Juri Commons, including a smooth accessible pathway, nature play, slide & swings, and lush greenery throughout, has been approved! Read on...
  53. Herz Groundbreaking

    SF City leaders, families celebrate groundbreaking of improvement project at Herz Playground

    The Recreation & Park Department broke ground on renovations at Herz Playground in Visitacion Valley on Monday as part of the Let’sPlaySF! initiative that is delivering creative play spaces to children across San Francisco. Read on...
  54. Juri Commons Ribbon Cut

    Juri Commons Park Reopens Following Renovation

    Juri Commons reopened following a $1.9 million renovation honoring the Mission District park’s railroad history, featuring a redesign with new plantings, an improved play space for children, grass for dogs, & an adult exercise area with fitness equipment. Read on...
  55. Capital Project Update

    Herz Playground | Project update May 2023

    If you have driven down Visitacion Avenue this week, you may have noticed the large towers erected at the Herz Playground construction site. Read on...
  56. Capital Project Update

    SF Rec and Park Commission Meeting at Joe Lee Rec Center | March 16 at 10 a.m.

    Come meet your Rec and Park Commissioners at our offsite Commission meeting at Joe Lee Rec Center Read on...
  57. Capital Project Update

    Herz Playground – Construction Update | March 2023

    Even with these heavy winter rains, we continue to make progress at Herz Playground. The new sewer lines that serve the Read on...
  58. Capital Project Update

    Herz Playground – Construction Demolition Almost Complete!

    Treaty Construction is busy at work with their backhoe! Demolition is nearly complete at Herz Playground. . . . Read on...
  59. Capital Project Update

    Herz Playground Groundbreaking Celebration October 24th!

    Save the date! Please join, Monday, October 24 from 4:30-5:30 . . . Read on...
  60. Capital Project Update

    Contract Awarded for Herz Playground Construction

    On August 18, 2022, Commission approved that Treaty Construction be awarded the contract to renovate Herz Playground. . . . Read on...
  61. Capital Project Update

    Bids received for Herz Playground Construction!

    Hi everybody- We have great news to share- we received 7 bids on the Herz Playground Renovation Project! Read on...
  62. Capital Project Update

    Contractor bids are due on Wednesday, May 25! for Herz Playground!

    Hi all- We nearing the end of our advertisement period for Herz Playground! . . . Read on...
  63. Capital Project Update

    Herz Playground Project is going out to bid!

    Hi everyone- We will be advertising the Herz Playground Renovation Project this week. . . Read on...
  64. Capital Project Update

    Herz Playground Project Update March 2022

    We have finalized structural engineering for the playground equipment and we aim to bring the construction documents to the Department of Building Inspection Read on...
  65. Capital Project Update

    Herz Playground Project Update 2/23/2022

    We have our final set of drawings and specifications ready for bidding Read on...
  66. Capital Project Update

    Herz Playground Project Update 1/22!

    We are putting the final touches on our permit set of drawings and we are planning to advertise the project to contractors in February. . . Read on...
  67. Capital Project Update

    Herz Playground Project Update 12/17!

    Hi everybody- We have wrapped up our permit set of drawings and the next step is to have the drawings reviewed by the Building Department for approval. . . Read on...
  68. Capital Project Update

    Herz Playground Project Update 11/18!

    Hi everybody- We are putting the finishing touches on the permit set of drawings, which we will submit to the Building Department for approval. . . Read on...
  69. Capital Project Update

    Herz Playground Project Update 9/20!

    Hi everybody- We are getting close to wrapping up our construction document for the new playground and the bathroom renovation at Herz Clubhouse. . . Read on...
  70. Capital Project Update

    Herz Playground Project Update 8/20!

    The landscape architect is developing the construction documents for the project. . . Read on...
  71. Capital Project Update

    Herz Playground Project Update 7/19!

    Hi everybody, We are continuing work on the construction documents for the project. . . Read on...
  72. Capital Project Update

    Herz Playground Project Update 6/21!

    Hi all, We are wrapping up our cost estimating and we will be moving into construction documents for the playground renovation. . . Read on...
  73. Capital Project Update

    Herz Playground Project Update 5/21!

    Hi all, Our design has completed the detailed design phase and we are currently cost estimating the project and doing regulatory reviews. . . Read on...
  74. Capital Project Update

    Herz Playground Project Update4/20!

    Hi everyone, Thank you so much for your support at the Recreation and Park Commission and for participating in all our community outreach for this project. Read on...
  75. Capital Project Update

    Herz Playground Project is Going Before the Commission for Approval!!

    Hi all, This Thursday, March 18th at 10am, we will be presenting the playground concept plan to the Rec Park Commission . . . Read on...
  76. Capital Project Update

    News about the Herz Projects!

    We are excited to share that Rec Park staff will be presenting the . . . Read on...
  77. Capital Project Update

    Herz Playground Project Update 1/22!

    Hi everyone, We are very close to finalizing our concept plan . . . Read on...
  78. Capital Project Update

    Herz Playground Project Update Dec '20

    We are working with the Historic Preservation team at the Planning Department to review the playground design Read on...
  79. Capital Project Update

    Herz Playground Project Update 10/29!

    Thank you so much to those who joined us for our final community meeting. Read on...
  80. Capital Project Update

    Herz Playground Project Final Community Meeting!

    Join us to see the updated design for Herz. . . Read on...
  81. Capital Project Update

    Herz Playground Project Update 9/18!

    Hi all- Our project designers have been updating the playground design to reflect the survey results on the play equipment Read on...
  82. Capital Project Update

    Herz Playground Project Update 8/21!

    Hi all- Thank you so much to everyone who participated in our online survey! Read on...
  83. Capital Project Update

    Herz Rec Center Project Update 8/21!

    Hi everyone! Thanks to those who participated in our focus group meetings. . . Read on...
  84. Capital Project Update

    Herz Playground Project Survey Still Open!

    We have had a great response to our survey and we are going to keep it open a little longer . . . Read on...
  85. Capital Project Update

    Take a Brief Survey to Help Us with the Herz Playground Renovation!

    During these times of civil unrest, we hope that parks can provide essential spaces for gathering, recreating and connecting to nature. Read on...
  86. Capital Project Update

    Herz Playground Project Update 5/22

    We are putting finishing touches on our playground survey and getting it translated into multiple languages. Read on...
  87. Capital Project Update
  88. Capital Project Update

    HERZ PLAYGROUND

    The project team is refining the draft concept plan for the playground and getting a preliminary concept estimate done Read on...
  89. Capital Project Update

    HERZ- CHILDREN’S PLAYGROUND RENOVATION

    Rec Park is working with our project landscape architect to consolidate the community feedback into one design for the playground renovation Read on...
  90. Capital Project Update

    HERZ PLAYGROUND- WORKING ON THE CONCEPT DESIGN

    Thank you so much to those who have provided feedback on our different design options for the Herz Playground Renovation Read on...
  91. Capital Project Update

    Virtual Community Meeting, April 11 | McLaren 2020 Bond – Possible Projects and Priorities

    Join us for a Virtual Community Meeting on April 11. The project team will share possible project ideas for specific program areas, infrastructure improvements, and Read on...
  92. Capital Project Update

    McLaren Group Picnic Area and Playground Project Update 11/10!

    We will be removing two additional trees that are . . . Read on...
  93. Capital Project Update

    McLaren Park Redwood Grove Playground is Open for Play!!!

    Hi everyone- We are officially open for play! Woohooo! Read on...
  94. Capital Project Update

    McLaren Group Picnic Area and Playground Project Update 9/18!

    Hi folks- We have completed installing the new table tops and barbecues. . . Read on...
  95. Capital Project Update

    McLaren Group Picnic Area and Playground Project Update 8/21!

    Hi all- We are close to wrapping up work at the new Redwood Grove Playground! Read on...
  96. Capital Project Update

    McLaren Group Picnic and Playground Project Update 7/27!

    We are continuing to finalize the entrance area at the new playground and restroom. Read on...
  97. Capital Project Update

    McLaren Group Picnic and Playground Project Update 6/25!

    Hi everyone, the construction team has been working hard at McLaren. Read on...
  98. Capital Project Update
  99. Capital Project Update

    McLaren Park Group Picnic and Playground Construction Update 3/24

    Work on public projects such as this one is continuing at this time. Read on...
  100. Capital Project Update

    MCLAREN PLAYGROUND & RESTROOM PROJECT UPDATE FEB 2020

    Work is continuing on-site with the installation of the new pathways which connect to the playground and the picnic areas Read on...
  101. Capital Project Update

    MCLAREN PLAYGROUND/GROUP PICNIC PROJECT UPDATE FEB 2020

    The contractor continues to make progress on-site. The boulders are in and they are currently working on Read on...
  102. Capital Project Update

    CONSTRUCTION UPDATE: MCLAREN GROUP PICNIC AREA PLAYGROUND & RESTROOM

    Work is continuing at the Group Picnic Area. The curb walls are being finished this week and the play equipment footings will start to be poured. Read on...
  103. Capital Project Update

    MCLAREN PARK GROUP PICNIC PLAYGROUND + RESTROOM

    We have exciting news to share. Earlier this month, the Rec Park Commission approved increasing the construction contract amount Read on...
  104. Capital Project Update

    Merced Heights Playground’s Lower Terrace Transformed by Renovation

    Former field now has something for everyone: families, seniors, and dogs. Read on...
  105. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace | Project update May 2023

    We're putting the finishing touches on the Lower Lawn Terrace of Merced Heights Playground, in preparation for our re-opening celebration next Friday Read on...
  106. Capital Project Update

    Merced Lower Terrace Re-Opening Celebration | May 19, 12 to 1 PM

    Join us on Friday, May 19, from 12 to 1 pm, for a re-opening celebration of the Merced Heights Playground Lower Lawn Terrace Read on...
  107. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace Construction Update

    You may have noticed a pause in construction recently. Work stopped as we discovered some infrastructure below ground that we had not anticipated. . . Read on...
  108. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace Project Update 10/9!

    A community meeting was held in November 2019 to review preliminary designs for a . . . Read on...
  109. Capital Project Update

    Merced Heights Project Update 5/28!

    Merced Heights Playground Renovation scope of work includes a new children’s play area, upgrades to the clubhouse restrooms and . . . Read on...
  110. Capital Project Update

    CANCELLED: Merced Heights Community Meeting #2 on March 7

    CANCELLED: Please join us for Open House and Public Meeting #2 for the Merced Heights Playground Multi-Purpose Field Improvements Project Read on...
  111. Capital Project Update

    Merced Heights Playground Community Meeting on November 20

    In June of this year, Assemblymember Phil Ting secured a $1,370,000 State Local Assistance Grant for Merced Heights Playground Read on...
  112. Capital Project Update

    SF Recreation and Park Department Breaks Ground on Five Playgrounds

    Under the watchful eyes of 45 preschoolers, city officials and community members broke ground today on five playground renovations Read on...
  113. Capital Project Update

    Let’sPlaySF! Groundbreaking

    Join us for a special groundbreaking even on April 25, 2019 Read on...
  114. Capital Project Update

    Richmond Playground Construction Update 8/17.

    We’re almost at 100% completion of the construction drawings . . . Read on...
  115. Capital Project Update

    Richmond Playground Project Update April 2022

    Richmond Playground is moving forward! Read on...
  116. Capital Project Update

    Richmond Playground Project Update 8/20!

    Design work for the Richmond Playground renovation has resumed! Read on...
  117. Capital Project Update

    Richmond Playground Project Update 4/26!!

    Design work on the Richmond Playground renovation is temporarily halted but we are hopeful that the project can resume shortly . . . Read on...
  118. Capital Project Update

    Richmond playground Project Update 2/9!

    The concept design for Richmond Playground is complete! Read on...
  119. Capital Project Update

    Richmond Playground Concept Design Moving Forward 9/21!

    Thank you so much to all who attended the third and final community workshop and to all who have contributed feedback along the way. . . Read on...
  120. Capital Project Update

    Join us to discuss the final concept design for Richmond Playground!

    Please join us for a final community meeting to celebrate and discuss the final concept design for the upcoming renovation . . . Read on...
  121. Capital Project Update

    Richmond Playground Open House and Design Workshop

    Give your input on concept designs for the upcoming renovation of the play area at Richmond Playground Read on...
  122. Capital Project Update

    Richmond Playground Open House- Thank You!

    We had a wonderful Public Open House on November 2nd! About 50 people stopped by on a sunny Saturday morning to participate in the project Read on...
  123. Capital Project Update

    Richmond Playground Open House

    Recreation and Parks hosted an Open House in November 2019 regarding the upcoming renovation of the play area at Richmond Playground Read on...
  124. Capital Project Update

    Sergeant John Macaulay Playground ready for opening!

    The site is getting final touches to be ready for opening . . . Read on...
  125. Capital Project Update

    Sergeant J Macaulay Park Construction is Nearing Completion!

    Sergeant J Macaulay Park is getting the final touches as we look towards the end of construction. Read on...
  126. Capital Project Update

    SGT MACAULAY PARK NEARING COMPLETION

    The park is quickly headed toward completion as the play features are currently being installed Read on...
  127. Capital Project Update

    Construction Photos DEC 2019

    Project updates and photos for the Sgt. John McCaulay Playground renovation Read on...
  128. Capital Project Update

    Construction Update OCT 2019

    Construction is in “full swing” at the park. Within the next month, much construction activity will Read on...
  129. Capital Project Update

    Construction Begins!

    We are in the exciting times as work on the ground has officially begun Read on...
  130. Capital Project Update

    Stern Grove Playground Renovation | March 2023 update

    As a quick update on the Stern Grove Playground Renovation, we are making some refinements to the final concept design, while continuing regulatory and construction bid preparation Read on...
  131. Capital Project Update

    Stern Grove Playground Renovation | February 2023 update

    We are wrapping up our construction documentation for the playground renovation at Stern Grove... Read on...
  132. Capital Project Update

    Stern Grove Playground Virtual Community Meeting #3 12/14 at 5pm!

    Join us for the third community meeting for the Stern Grove Playground Renovation Project. . . Read on...
  133. Capital Project Update

    Stern Grove Playground Virtual Community Meeting #2 (7/21 at 5pm)

    Join us for the second community meeting for the Stern Grove Playground Renovation Project. . . Read on...
  134. Capital Project Update

    POSTPONED - Stern Grove Virtual Community Meeting 3/25 at 5 pm!

    Join us for the second community meeting for . . . Read on...
  135. Capital Project Update

    Stern Grove Virtual Community Meeting 2/18 at 5 pm!

    We hope you can join us for the first of many virtual meetings to discuss the renovation of the playground at Stern Grove. . . Read on...
  136. Capital Project Update

    Stern Grove Playground Survey is Now Closed Thank you!

    The Stern Grove Playground Community Survey is now open! Read on...
  137. Capital Project Update

    Temporary Playground Closure Apr 26-27 and Donor Recognition Tile Installation Complete

    The West Portal Playground (Children’s Play Area Only) will be temporarily closed April 26 through sometime on April 27 as we do some safety surfacing repairs. Read on...
  138. Capital Project Update

    West Portal Playground Project Update 3/19/21!!

    We hope you are enjoying the recently renovated West Portal Playground! Read on...
  139. Capital Project Update

    West Portal Playground: Update on Temporary Closure of Children’s Play Area This Week

    The West Portal Playground (Children’s Play Area Only) was temporarily closed today and will reopen at 5 p.m. Read on...
  140. Capital Project Update

    West Portal Playground: Temporary Closure of Children’s Play Area This Week

    The West Portal Playground (Children’s Play Area Only) will be temporarily closed this week, beginning December 3 Read on...
  141. Capital Project Update

    Children’s Play Area Now Open at West Portal Playground!

    The contractor has a few minor items remaining . . . Read on...
  142. Capital Project Update

    West Portal Playground Project Update 10/8!

    The restored field, as well as the nature exploration area, picnic area, and clubhouse restrooms, are now open . . . Read on...
  143. Capital Project Update

    West Portal Playground Project is Nearing Completion!

    We are excited to report that the renovation of the West Portal Playground is nearing completion. Read on...
  144. Capital Project Update

    Playground Equipment Installation

    The playground is looking colorful, as the contractor has begun installing playground equipment! Read on...
  145. Capital Project Update

    Tennis Court Lighting Restored

    Tennis court lighting has been restored at West Portal Playground, covering both night time and morning hours. Read on...
  146. Capital Project Update

    Tennis Court Lighting Out of Service

    Due to construction activities, including the need to get waterproofing work done as soon as possible, tennis court lighting is temporarily out of service Read on...
  147. Capital Project Update

    Construction Update

    Construction is moving along on West Portal Playground renovation. The contractor is finishing up Read on...
  148. Capital Project Update

    Construction to Start

    After a successful “Play Day” on Saturday, September 21, we are excited to report that construction will start Read on...
  1. Kelli Rudnick

    Project Manager Supervisor