Let’sPlaySF! Initiative (2012 Bond)

BackgroundAlice Chambers

Let’sPlaySF! has its origins in the $195 million San Francisco Clean and Safe Neighborhood Parks General Obligation Bond approved by 71.6% of voters in November 2012. The Bond allocated $15.5 million to renovate dilapidated playgrounds through the City.

In 2014, the Recreation and Park Commission appointed a Citizen Task Force to determine which playgrounds were most in need of renovation. The Task Force prioritized six Tier 1 and seven Tier 2 playgrounds for renovation based on four criteria: (1) the presence of Chromated Copper Arsenate (CCA) Pressure Treated Wood, (2) low Household Median Income, (3) high Youth Density and (4) low Playground Report Card Grades.

In December 2014, the Recreation and Park Commission unanimously adopted the list recommended by the Task Force, of which the Department committed to renovate all six Tier 1 playgrounds and to renovate some or all Tier 2 playgrounds provided if additional funding were procured. 

In the wake of that determination, in 2016, the Department launched the Let’sPlaySF! Initative, a public-private partnership dedicated to raising sufficient funds to ensure that all 13 playgrounds could be reimagined for San Francisco’s children.

Program Status

The initiative has fully completed 11 of 13 playgrounds and they are open to the public.

Of the two remaining playgrounds, Stern Grove began construction in late 2024 and slated to open in Mid-2025. Buchanan Street Mall Playground has been incorporated into a larger renovation of the park. This project began construction in summer 2025 and slated to open in 2026.

For status updates on the individual sites, click on a project:


Status of Tier 1 SitesAll Tier 1 sites are completed and open to the public.

Status of Tier 2 Sites:

Herz PlaygroundProject Updates

If you would like to sign-up for Project Update blog posts like the ones below, click here, scroll down to the News Flash section, and then select "RPD Park Improvements | All Project Updates" to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. You'll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.

  1. Project Update Blog
  2. Additional Background
  3. Documents and Materials
  4. Meeting Materials
  5. Task Force Members
  1. Project Update

    Buchanan Street Mall | Traffic and Parking impacts on Golden Gate Ave on Friday, February 13

    On Friday, February 13, our contractor will remove a hazardous tree on Golden Gate Avenue near Rosa Parks Senior Center. Expect work vehicles in the roadway, lane closures, slow traffic, and temporary “No Parking | Tow Away” restrictions near the Read on...
  2. Project Update

    Buchanan Street Mall | Construction update, February 2026

    The tree work on Golden Gate Avenue near Rosa Parks Senior Center, originally scheduled for Wednesday, February 4, was postponed. We will keep you posted once a new date for this tree work has been determined. Other project work is continuing at a Read on...
  3. Project Update

    Buchanan Street Mall | Traffic and Parking impacts on Golden Gate Ave on Wednesday, February 4

    On Wednesday, February 4, our contractor will remove a hazardous tree on Golden Gate Avenue near Rosa Park Senior Center. Expect work vehicles in the roadway, lane closures, slow traffic, and temporary “No Parking | Tow Away” restrictions near the Read on...
  4. Project Update

    Community Opportunity Fund (COF) | Nominations for projects are now open!

    Nominations for Community Opportunity Fund (COF) projects are now open! To get started today: Visit the program page, review the sample application, application instructions, scoresheet, FAQs, and the Implementation Plan! Sign up for a Read on...
  5. Project Update

    Buchanan Street Mall | Construction update, January 2026

    Please be advised: PG&E will be working on McAllister Street on January 12-16. The work requires a lane closure on McAllister during working hours. Expect work vehicles in the roadway, as well as impacts to parking and traffic. Please follow all Read on...
  6. Project Update

    Buchanan Street Mall | Memory Walk update, December 16, 2025

    Artists Selected to Contribute to the Memory Walk at Buchanan Street Mall! Thank you to everyone who applied in the spring. After a thoughtful review process, guided by the Memory Walk Art Advisory Committee, nine artists have been selected to Read on...
  7. Project Update

    Buchanan Street Mall | Construction update, December 2025

    Please be advised: Soil off haul is scheduled for Wednesday, December 3 and Friday, December 5. Expect construction vehicles entering and exiting the worksite, as well as impacts to parking and traffic. Please follow all posted signage and Read on...
  8. Capital Project Update

    Buchanan Street Mall | Construction update, October 2025

    Sewer work is nearly complete, and electrical conduit and light pole footing installation begins this week. Irrigation mainline installation is underway, led by a Black-owned LBE plumbing subcontractor brought on by McGuire and Hester. Structural footing Read on...
  9. Capital Project Update

    Stern Grove Playground Renovation | Construction update, October 2025

    We are happy to share that the new lawn below the playground is now open to the public! After completing its establishment period – resting, watering, and two mowing cycles, the grass is healthy and ready for visitors to enjoy. You may still see our Read on...
  10. Capital Project Update

    Stern Grove Playground Renovation | Construction update, September 2025

    We are super excited that the playground is now open to the public! Thank you to everyone who supported this special project. Over the next few months, you will continue to see our contractor on-site periodically to make adjustments and Read on...
  11. Capital Project Update

    Buchanan Street Mall | Construction update, September 22, 2025

    Our contractor is continuing to work on replacing the lateral sewer lines, including installing new sewer vents for easier maintenance for the park and adjacent properties. Also, they are continuing to map and verify existing underground Read on...
  12. Capital Project Update

    Stern Grove Playground Renovation | Stern Grove Playground Transformed into Tree House Village

    Beloved Sunset District play space reopens as whimsical, nature-inspired retreat. Read on...
  13. Capital Project Update

    Stern Grove Playground Renovation | REMINDER! Playground Ribbon Cutting on September 10, 3:30 pm

    Come out for the reopening of Stern Grove Playground on Wednesday, September 10 from 3:30 to 4:30 p.m. The event will feature brief remarks, a ribbon cutting ceremony, and the debut of the new, nature-based play area of the Read on...
  14. Capital Project Update

    Buchanan Street Mall | Construction update, September 2025

    We’re happy to share that the final segment of cured-in-place sewer lining was completed on August 29, officially wrapping up our planned night work. A big thank you to our nearby neighbors for your patience, we know night work can be disruptive. Although Read on...
  15. Capital Project Update

    Stern Grove Playground Renovation | Playground Ribbon Cutting on September 10

    Come out for the reopening of Stern Grove Playground on Wednesday, September 10 from 3:30 to 4:30 p.m. The event will feature brief remarks, a ribbon cutting ceremony, and the debut of the new, nature-based play area of the Read on...
  16. Capital Project Update

    Buchanan Street Mall | REMINDER: Workforce Development Community Meeting, this Thursday, 8/21 at 2pm

    REMINDER: Workforce Development Community Meeting, this Thursday, August 21 at 2pm at Rosa Parks Senior Center on Buchanan Mall (at Golden Gate Ave.). Come learn more about job opportunities, training, and employment support. For the Read on...
  17. Capital Project Update

    Buchanan Street Mall | Construction update, August 2025

    Construction is currently focused on specialized sewer work, surface demolition, and careful investigations to locate and protect existing utilities. The project team has completed the second of three 48-hour sewer lining operations, where a Read on...
  18. Capital Project Update

    Buchanan Street Mall | REMINDER: Night work scheduled for August 11 and 12

    DAY AND NIGHT WORK REMINDER: Sewer and construction work will be continuous for 48 hours from August 11-13. This includes two evenings of night work (August 11 & 12). The contractor will Read on...
  19. Capital Project Update

    Buchanan Street Mall | Saturday work scheduled for August 9

    NOTICE OF WEEKEND WORK: There will be on-site construction work this Saturday. The contractor will follow all noise ordinance requirements. DAY AND NIGHT WORK REMINDER: Sewer and construction work will be continuous for 48 hours from August 11-13. This Read on...
  20. Capital Project Update

    Buchanan Street Mall | Workforce development update, August 7, 2025

    For the past two years, we have partnered with Success Centers, a hyper-local community-based workforce nonprofit dedicated to connecting local Western Addition and Fillmore residents with trade job opportunities, training, and employment support for Read on...
  21. Capital Project Update

    Buchanan Street Mall | Night work scheduled for August 11 and 12

    Notice of Night Work: Please be advised that there will be 48 hours of continuous construction activity from Monday, August 11, 7 a.m. to Wednesday, August 13, 7 a.m. Work will be performed on the sewer between Turk St. and Eddy St. Sewer lining work must Read on...
  22. Capital Project Update

    Stern Grove Playground Renovation | Construction update, August 2025

    There has been an unforeseen delay in the installation of the safety surfacing at the playground. This will push the playground’s reopening to sometime in September. We will follow up with more information once an opening date is Read on...
  23. Capital Project Update

    Buchanan Street Mall | Workforce development update

    Thanks to the nearly thirty people who stopped by office hours yesterday. Rec and Park and Success Centers staff shared information about the various workforce development initiatives that are in place on the Buchanan Street Mall Renovation project as Read on...
  24. Capital Project Update

    Buchanan Street Mall | Workforce development

    We're hosting workforce development-focused office hours this Thursday, July 31, 2025, at 10:30am at Rosa Parks Senior Center computer lab. We encourage everyone to attend to learn more about our workforce development initiatives and about Read on...
  25. Capital Project Update

    Stern Grove Playground Renovation | Construction update, July 2025

    We’re excited to report that the new playground’s final piece of custom play equipment – the large, curved, metal slide – arrived on July 16 and installation of the slide is now underway. Our contractor is also working to complete the Read on...
  26. Capital Project Update

    Buchanan Street Mall | REMINDER: Night work scheduled for July 22 & July 23

    Notice of Night Work: Please be advised that there will be 48 hours of continuous construction activity from July 22, 7 a.m. to July 24, 7 a.m. Cured-in-place lining work will be completed on the sewer between Fulton and McAllister on Read on...
  27. Capital Project Update

    Buchanan Street Mall | Night work scheduled for July 22 & July 23

    Notice of Night Work: Please be advised that there will be 48 hours of continuous construction activity from July 22, 7 a.m. to July 24, 7 a.m. Cured-in-place lining work will be completed on the sewer between Fulton and McAllister on Read on...
  28. Capital Project Update

    Buchanan Street Mall | Construction update, July 2025

    Construction fences are now in place on the four southern-most blocks, from Grove St to Turk Street. Construction fencing will be installed on the northernmost block between Turk Street and Eddy Street starting next Monday, July 7. All doors and Read on...
  29. Capital Project Update

    Stern Grove Playground Renovation | Construction update, June 2025

    All play equipment is now installed, except for one piece of custom play equipment that will be delivered to the site soon. In the meantime, the construction team is preparing the new pedestrian pathways for paving. Construction is progressing nicely, and Read on...
  30. Capital Project Update

    Buchanan Street Mall | Construction update, June 2025

    Construction at Buchanan Street Mall is making great progress! Major work has been focused on carefully mapping and assessing existing utilities, and refining our plans for health and safety, site logistics, and traffic control. There has also been some Read on...
  31. Capital Project Update

    Stern Grove Playground Renovation | Construction update, May 2025

    The playground continues to take shape with the installation of the playground towers and other climbing elements. We are looking forward to wrapping up construction this summer Read on...
  32. Capital Project Update

    Buchanan Street Mall | Construction update, May 2025

    Our contractor has mobilized, and tree work has begun at Buchanan Street Mall. Tree work on the southern blocks is well underway, with a cluster of pine trees south of McAllister to be removed next week. Tree work will continue progressing to the Read on...
  33. Capital Project Update

    Buchanan Street Mall | Construction update - Tree Removals and Construction Fencing in early May

    PLEASE BE ADVISED: Tree work and tree removal will begin at Buchanan Street Mall the week of May 5. This work is expected to take approximately 2 weeks. Tree work will happen between 7am - 3pm. Expect to see barriers around work zones, marked detours for Read on...
  34. Capital Project Update

    Stern Grove Playground Renovation | Construction update, April 2025

    The second shipment of custom play equipment was received last week, and the final delivery is expected within the next two weeks. On-site installation of catch basins is currently underway, and the construction team continues to make steady progress on Read on...
  35. Capital Project Update

    Buchanan Street Mall | Calling Artists (who have strong ties to the Fillmore)

    You are invited to submit an application for your art to be considered for the Buchanan Street Mall Memory Walk! Applications are due on May 23, 2025, by 5:00 pm. The initiative includes art that honors the neighborhood’s rich history, culture and Read on...
  36. Capital Project Update

    Buchanan Street Mall | Construction begins at Buchanan Street Mall

    Thank you to everyone who joined us for the groundbreaking on March 27th! It was a beautiful celebration for and with the Fillmore community. We’re excited to share this milestone moment with you. After more than 10 years of visioning, planning, and Read on...
  37. Capital Project Update

    Stern Grove Playground Renovation | Construction update, March 2025

    The first shipment of the custom play equipment has been received, and the contractor is preparing the site to install the same Read on...
  38. Capital Project Update

    Buchanan Street Mall | Mayor Lurie Breaks Ground on Renovation of Buchanan Street Mall

    Long-Anticipated Project Marks the Culmination of a Partnership Between the City and Fillmore Community. Community Space Will Celebrate the History of the Neighborhood While Marking a New Chapter for Western Addition. Read on...
  39. Capital Project Update

    Stern Grove Playground Renovation | Construction update, February 2025

    The contractor is currently installing gopher wires between the boulders and preparing to install the permeable rock base for the play area. There has been a delay in the delivery of the custom play equipment due to the snowstorms in Toronto but the Read on...
  40. Capital Project Update

    Let’sPlaySF! Initiative | Let'sPlaySF! Playground Survey extended to Friday, February 28!

    Survey extended through the end of February! Thanks to the successful Let’sPlaySF! Initiative funded by the 2012 Park Bond, SF Parks Alliance, and philanthropic partners we are renovating 13 dilapidated playgrounds across our city. With 11 playgrounds Read on...
  41. Capital Project Update

    Stern Grove Playground Renovation | Construction update, January 2025

    The contractor is currently focused on replacing the fencing along Sloat Avenue and completing the final stages of boulder placement within the playground Read on...
  42. Capital Project Update

    Let’sPlaySF! Initiative | REMINDER: Let'sPlaySF! Playground Survey open through January 31

    Thanks to the successful Let’sPlaySF! Initiative funded by the 2012 Park Bond, SF Parks Alliance, and philanthropic partners we are renovating 13 dilapidated playgrounds across our city. With 11 playgrounds already beautifully renovated and two more Read on...
  43. Capital Project Update

    Stern Grove Playground Renovation | Construction update, December 2024

    The contractor is installing the boulder border at the edge of the playground and constructing the wooden boardwalk. Next step will be installing the playground equipment in early 2025 Read on...
  44. Capital Project Update

    Let’sPlaySF! Initiative | Take the Let'sPlaySF! Playground Survey open through January 31, 2025

    Thanks to the successful Let’sPlaySF! Initiative funded by the 2012 Park Bond, SF Parks Alliance, and philanthropic partners we are renovating 13 dilapidated playgrounds across our city. With 11 playgrounds already beautifully renovated and two more Read on...
  45. Capital Project Update

    Stern Grove Playground Renovation | Construction update, November 2024

    Since our last update in October, the contractor is pouring concrete for the boardwalk footings and working on the tiered seating that connects the lawn to the playground Read on...
  46. Capital Project Update

    Stern Grove Playground Renovation | Construction update, October 2024

    Site demolition is complete, and the contractor is currently laying out the boardwalk and concrete footings for the new stepped seating. They are also making site drainage improvements Read on...
  47. Capital Project Update

    Stern Grove Playground Renovation | Construction update, September 2024

    Construction has begun! Construction fences are up and the contractor is now working on demolition and off-haul of the old playground equipment. They will begin site utilities next Read on...
  48. Capital Project Update

    Richmond Playground | Construction complete! Playground now open!

    Richmond Playground is now open! Thank you for your support throughout construction. This will be our last blog update for this project. Please visit our park improvements webpage to learn about other major projects happening in the parks Read on...
  49. Capital Project Update
  50. Capital Project Update

    Stern Grove Playground Renovation | Construction update, August 2024

    We are eagerly awaiting construction to begin on-site. We anticipate that work will start on-site in September. The contractor is putting together a schedule, and the playground equipment is being fabricated Read on...
  51. Capital Project Update

    Stern Grove Playground Renovation | Playground Renovation Begins!

    Last week, we kicked off the Stern Grove Playground renovation! The project will include new furnishings, accessibility improvements, and a complete makeover of the children’s play area with tree-like play structures, natural timber logs, climbing nets Read on...
  52. Capital Project Update

    Stern Grove Playground Renovation | Construction update, July 2024

    Our contractor is getting ready for the Stern Grove Playground Renovation. They recently ordered the new playground equipment and will begin work at the site in September. Read on...
  53. Capital Project Update

    Stern Grove Playground Renovation | Construction update, June 2024

    We are excited to share that construction will begin this summer on the Stern Grove Playground Renovation Project. The project includes a full renovation of the playground elements with new structures, surfacing and landscaping. There will also be a new Read on...
  54. Capital Project Update

    Stern Grove Playground Renovation | Project update, May 2024

    The contractor selected for the Stern Grove Playground Renovation Project is working on their paperwork and getting insurance and bonds together. We anticipate being able to share a construction start date soon Read on...
  55. Capital Project Update

    Stern Grove Playground Renovation | Project update, April 2024

    The Recreation and Park Commission approved the award of the Stern Grove Playground Renovation project’s add alternates, which include new fencing along a portion of Sloat Blvd, a new irrigation system for the field adjacent to Read on...
  56. Capital Project Update

    Stern Grove Playground Renovation | Project update, March 2024

    Our contractor, Minerva Construction, is working on signing the contract and completing paperwork related to starting construction. We are also happy to share that we will be Read on...
  57. Capital Project Update

    Richmond Playground | Construction update February 2024

    Construction continues to be moving along well. Our contractor has continued with demolition, preparation of base material and forming of concrete seat walls for the playground area. Large play equipment has been Read on...
  58. Capital Project Update

    Richmond Playground | Construction update January 2024

    Since our last update at the end of November, construction work is making good progress. We’ve kicked off demolition, abatement, and renovation work on the restroom. Most of the old sand has been removed from the play area, and the site is being prepped Read on...
  59. Capital Project Update

    Richmond Playground | Construction update, Nov-Dec 2023 | Richmond Playground Renovation Begins!

    We're excited to share that the Richmond Playground renovation has begun! The project will include new furnishings, upgrades to the Read on...
  60. Capital Project Update

    Stern Grove Playground Renovation | Project update, November 2023

    Construction is estimated to start by mid-2024. We are working now to finalize our Read on...
  61. Capital Project Update

    Richmond Playground | Construction update October 2023

    We issued the Notice to Proceed (NTP) to our contractor and you should expect to see construction mobilization on-site starting in December or January. Once construction starts, there will be Read on...
  62. Capital Project Update

    Richmond Playground | Project update July 2023

    We’re excited to share that a construction contract award for the Richmond Playground was approved by Rec and Park Commission on July 20! Read on...
  63. Capital Project Update

    Merced Heights Playground’s Lower Terrace Transformed by Renovation

    Former field now has something for everyone: families, seniors, and dogs. Read on...
  64. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace | Project update May 2023

    We're putting the finishing touches on the Lower Lawn Terrace of Merced Heights Playground, in preparation for our re-opening celebration next Friday Read on...
  65. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace | Construction Nearing Completion

    The contractor should be reaching substantial completion on the project within the next 1-2 weeks. A portion of the Read on...
  66. Capital Project Update

    Construction Progress for Merced Heights Playground Lower Lawn Terrace

    Trees and plants are in the ground and contractor will be completing installation of mulch by early next week. . . . Read on...
  67. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace Construction Update

    Construction is progressing and the lower terrace of Merced Heights Playground is starting to look like a park! . . . Read on...
  68. Herz Groundbreaking

    SF City leaders, families celebrate groundbreaking of improvement project at Herz Playground

    The Recreation & Park Department broke ground on renovations at Herz Playground in Visitacion Valley on Monday as part of the Let’sPlaySF! initiative that is delivering creative play spaces to children across San Francisco. Read on...
  69. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace Construction Update

    You may have noticed a pause in construction recently. . . Read on...
  70. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace Construction Update

    You may have noticed a pause in construction recently. Work stopped as we discovered some infrastructure below ground that we had not anticipated. . . Read on...
  71. Capital Project Update

    Sidewalk Work at Merced Heights Playground.

    Today our contractor began work demolishing sections of the sidewalk along Byxbee, . . . Read on...
  72. Capital Project Update

    Construction Updates for Merced Heights Lower Lawn Area!

    We are excited to report that, as of early June, the contractor’s certified consulting biologist has confirmed that bird nesting activity on site has been completed. . . Read on...
  73. Capital Project Update

    Construction Has Begun on Merced Heights Lower Lawn Area!

    We are excited to announce Notice to Proceed was issued to the Contractor, . . Read on...
  74. Capital Project Update

    Merced Heights - Notice to Proceed to Contractor in Early April 2022

    We are excited to announce that we are on track to issue Notice to Proceed to the Contractor Read on...
  75. Capital Project Update

    Merced Heights - Award of Construction Goes Before RecPark Commission

    We are happy to report that we will be presenting award of construction contract to the Recreation and Park Commission for approval this Thursday, February 17. Read on...
  76. Capital Project Update

    Merced Heights Lower Terrace Project - Contractor Bid Advertisement!

    We are happy to report that the project has been advertised to contractors! Read on...
  77. Capital Project Update

    Juri Commons is now open to the public!

    Juri Commons is open to the public! On September 13th the city held a ribbon cutting celebration to commemorate the park’s opening with . . . Read on...
  78. Juri Commons Ribbon Cut

    Juri Commons Park Reopens Following Renovation

    Juri Commons reopened following a $1.9 million renovation honoring the Mission District park’s railroad history, featuring a redesign with new plantings, an improved play space for children, grass for dogs, & an adult exercise area with fitness equipment. Read on...
  79. Capital Project Update

    Juri Commons Construction continues 8/16!

    Thank you everyone for your continued patience with this renovation project. . . Read on...
  80. Capital Project Update

    Merced Heights - Our design team is moving along with construction document production!

    As we work on that, we’re reaching back out to solicit input from the community. . . Read on...
  81. Capital Project Update

    Merced heights Lower Lawn Project Update 6/15/21!

    The Arts Commission Civic Design Review Committee approved the design in April, under their “Small Project Review” category. Read on...
  82. Capital Project Update

    Juri Commons Construction Update 6/7!

    We’re excited to share that planting is nearing completion, embedded rails are installed in the pathway and the team is about to lay down play surfacing in the playground. . . Read on...
  83. Capital Project Update

    Juri Commons Construction Update 4/23!

    We’re excited to share that the pathways and walls are nearly complete, the play equipment is installed, planting has begun . . . Read on...
  84. Capital Project Update

    Arts Commission Review and Design Coordination for Merced Heights Lawn Terrace Project!

    Following Rec and Park Commission of concept design in March, we are moving forward! Read on...
  85. Capital Project Update

    Merced heights Lower Lawn Project Update 3/19/21!

    The Recreation and Park Commission approved a concept design for the Merced Heights Playground Lower Lawn . . . Read on...
  86. Capital Project Update

    West Portal Playground Project Update 3/19/21!!

    We hope you are enjoying the recently renovated West Portal Playground! Read on...
  87. Capital Project Update

    Merced Heights Lower Lawn Terrace Project Headed to Commission for Approval!

    Staff will be presenting the proposed concept design to the Full Recreation and Park Commission this week. . . Read on...
  88. Capital Project Update

    Merced Heights Lower Lawn Terrace Project Update 3/1!

    We have received great input to help us finalize a proposed concept design . . . Read on...
  89. Capital Project Update

    Juri Commons Construction Update 2/9!

    Juri Commons is moving forward in construction and hitting a good stride . . . Read on...
  90. Capital Project Update

    Merced Heights Lower Lawn Terrace Project Community Meeting!

    Thank you for your patience as some important preparations were made . . . Read on...
  91. Capital Project Update

    West Portal Playground: Update on Temporary Closure of Children’s Play Area This Week

    The West Portal Playground (Children’s Play Area Only) was temporarily closed today and will reopen at 5 p.m. Read on...
  92. Capital Project Update

    West Portal Playground: Temporary Closure of Children’s Play Area This Week

    The West Portal Playground (Children’s Play Area Only) will be temporarily closed this week, beginning December 3 Read on...
  93. Capital Project Update

    Children’s Play Area Now Open at West Portal Playground!

    The contractor has a few minor items remaining . . . Read on...
  94. Capital Project Update

    Merced Heights Lower Lawn Terrace Project Update 10/9!

    A community meeting was held in November 2019 to review preliminary designs . . . Read on...
  95. Capital Project Update

    Merced Heights Playground Lower Lawn Terrace Project Update 10/9!

    A community meeting was held in November 2019 to review preliminary designs for a . . . Read on...
  96. Capital Project Update

    West Portal Playground Project Update 10/8!

    The restored field, as well as the nature exploration area, picnic area, and clubhouse restrooms, are now open . . . Read on...
  97. Capital Project Update

    Juri Commons Construction continues 9/21!

    Demolition is nearing completion and the Juri Commons Renovation is underway. . . Read on...
  98. Capital Project Update

    Juri Commons Construction is Underway!

    We have broken ground! Renovation of Juri Commons Park is underway . . . Read on...
  99. Capital Project Update

    Merced Heights Project Update 5/28!

    Merced Heights Playground Renovation scope of work includes a new children’s play area, upgrades to the clubhouse restrooms and . . . Read on...
  100. Capital Project Update

    West Portal Playground Project is Nearing Completion!

    We are excited to report that the renovation of the West Portal Playground is nearing completion. Read on...
  101. Capital Project Update

    CANCELLED: Merced Heights Community Meeting #2 on March 7

    CANCELLED: Please join us for Open House and Public Meeting #2 for the Merced Heights Playground Multi-Purpose Field Improvements Project Read on...
  102. Capital Project Update

    WASHINGTON SQUARE UPDATE- FEB 2020

    You may have noticed areas of grass are sometimes cordoned off at Washington Square this winter. Here’s the good news: Read on...
  103. Capital Project Update

    West Portal Playground Renovation - Playground Equipment Installation

    The playground is looking colorful, as the contractor has begun installing playground equipment! Read on...
  104. Capital Project Update

    Juri Commons Renovation Moving Forward!

    Construction documents are complete and we expect to receive contractor bids by early February Read on...
  105. Capital Project Update

    WASHINGTON SQUARE REOPENS- DEC 2019

    Washington Square Park is now open! And thank you to all of the partners that helped to make this a great project Read on...
  106. Capital Project Update

    West Portal Playground Renovation - Tennis Court Lighting Restored

    Tennis court lighting has been restored at West Portal Playground, covering both night time and morning hours. Read on...
  107. Capital Project Update

    Merced Heights Playground Community Meeting on November 20

    In June of this year, Assemblymember Phil Ting secured a $1,370,000 State Local Assistance Grant for Merced Heights Playground Read on...
  108. Capital Project Update

    West Portal Playground Renovation - Tennis Court Lighting Out of Service

    Due to construction activities, including the need to get waterproofing work done as soon as possible, tennis court lighting is temporarily out of service Read on...
  109. Capital Project Update

    West Portal Playground Renovation - Construction Update

    Construction is moving along on West Portal Playground renovation. The contractor is finishing up Read on...
  110. Capital Project Update

    West Portal Playground Renovation - Construction to Start

    After a successful “Play Day” on Saturday, September 21, we are excited to report that construction will start Read on...
  111. Capital Project Update

    WASHINGTON SQUARE CONSTRUCTION UPDATE- JUL 2019

    We are in the third week of construction on the Washington Square project. Azul Works has been making great progress Read on...
  112. Capital Project Update

    WASHINGTON SQUARE CLOSURE- JUN 2019

    Washington Square Water Conservation Project set to begin this week. Construction fencing will be installed Read on...
  113. Capital Project Update

    REDWOODS IN JURI COMMONS??

    Not exactly, but you may have noticed some beautiful redwood logs stacked near the San Jose end of the park Read on...
  114. Capital Project Update

    JURI COMMONS - DESIGN RECEIVES FINAL APPROVAL

    More good news! Our conceptual design was approved this morning by the full Rec & Park Commission. Read on...
  115. Capital Project Update

    JURI COMMONS DESIGN APPROVED

    Good news! Our conceptual design for Juri Commons, including a smooth accessible pathway, nature play, slide & swings, and lush greenery throughout, has been approved! Read on...
  116. Project Update

    Buchanan Street Mall | Traffic and Parking impacts on Golden Gate Ave on Friday, February 13

    On Friday, February 13, our contractor will remove a hazardous tree on Golden Gate Avenue near Rosa Parks Senior Center. Expect work vehicles in the roadway, lane closures, slow traffic, and temporary “No Parking | Tow Away” restrictions near the Read on...
  117. Project Update

    Buchanan Street Mall | Construction update, February 2026

    The tree work on Golden Gate Avenue near Rosa Parks Senior Center, originally scheduled for Wednesday, February 4, was postponed. We will keep you posted once a new date for this tree work has been determined. Other project work is continuing at a Read on...
  118. Project Update

    Buchanan Street Mall | Traffic and Parking impacts on Golden Gate Ave on Wednesday, February 4

    On Wednesday, February 4, our contractor will remove a hazardous tree on Golden Gate Avenue near Rosa Park Senior Center. Expect work vehicles in the roadway, lane closures, slow traffic, and temporary “No Parking | Tow Away” restrictions near the Read on...
  119. Project Update

    Buchanan Street Mall | Construction update, January 2026

    Please be advised: PG&E will be working on McAllister Street on January 12-16. The work requires a lane closure on McAllister during working hours. Expect work vehicles in the roadway, as well as impacts to parking and traffic. Please follow all Read on...
  120. Project Update

    Buchanan Street Mall | Memory Walk update, December 16, 2025

    Artists Selected to Contribute to the Memory Walk at Buchanan Street Mall! Thank you to everyone who applied in the spring. After a thoughtful review process, guided by the Memory Walk Art Advisory Committee, nine artists have been selected to Read on...
  121. Project Update

    Buchanan Street Mall | Construction update, December 2025

    Please be advised: Soil off haul is scheduled for Wednesday, December 3 and Friday, December 5. Expect construction vehicles entering and exiting the worksite, as well as impacts to parking and traffic. Please follow all posted signage and Read on...
  122. Capital Project Update

    Buchanan Street Mall | Construction update, October 2025

    Sewer work is nearly complete, and electrical conduit and light pole footing installation begins this week. Irrigation mainline installation is underway, led by a Black-owned LBE plumbing subcontractor brought on by McGuire and Hester. Structural footing Read on...
  123. Capital Project Update

    Buchanan Street Mall | Construction update, September 22, 2025

    Our contractor is continuing to work on replacing the lateral sewer lines, including installing new sewer vents for easier maintenance for the park and adjacent properties. Also, they are continuing to map and verify existing underground Read on...
  124. Capital Project Update

    Buchanan Street Mall | Construction update, September 2025

    We’re happy to share that the final segment of cured-in-place sewer lining was completed on August 29, officially wrapping up our planned night work. A big thank you to our nearby neighbors for your patience, we know night work can be disruptive. Although Read on...
  125. Capital Project Update

    Buchanan Street Mall | REMINDER: Workforce Development Community Meeting, this Thursday, 8/21 at 2pm

    REMINDER: Workforce Development Community Meeting, this Thursday, August 21 at 2pm at Rosa Parks Senior Center on Buchanan Mall (at Golden Gate Ave.). Come learn more about job opportunities, training, and employment support. For the Read on...
  126. Capital Project Update

    Buchanan Street Mall | Construction update, August 2025

    Construction is currently focused on specialized sewer work, surface demolition, and careful investigations to locate and protect existing utilities. The project team has completed the second of three 48-hour sewer lining operations, where a Read on...
  127. Capital Project Update

    Buchanan Street Mall | REMINDER: Night work scheduled for August 11 and 12

    DAY AND NIGHT WORK REMINDER: Sewer and construction work will be continuous for 48 hours from August 11-13. This includes two evenings of night work (August 11 & 12). The contractor will Read on...
  128. Capital Project Update

    Buchanan Street Mall | Saturday work scheduled for August 9

    NOTICE OF WEEKEND WORK: There will be on-site construction work this Saturday. The contractor will follow all noise ordinance requirements. DAY AND NIGHT WORK REMINDER: Sewer and construction work will be continuous for 48 hours from August 11-13. This Read on...
  129. Capital Project Update

    Buchanan Street Mall | Workforce development update, August 7, 2025

    For the past two years, we have partnered with Success Centers, a hyper-local community-based workforce nonprofit dedicated to connecting local Western Addition and Fillmore residents with trade job opportunities, training, and employment support for Read on...
  130. Capital Project Update

    Buchanan Street Mall | Night work scheduled for August 11 and 12

    Notice of Night Work: Please be advised that there will be 48 hours of continuous construction activity from Monday, August 11, 7 a.m. to Wednesday, August 13, 7 a.m. Work will be performed on the sewer between Turk St. and Eddy St. Sewer lining work must Read on...
  131. Capital Project Update

    Buchanan Street Mall | Workforce development update

    Thanks to the nearly thirty people who stopped by office hours yesterday. Rec and Park and Success Centers staff shared information about the various workforce development initiatives that are in place on the Buchanan Street Mall Renovation project as Read on...
  132. Project Update icon

    Buchanan Street Mall | Workforce development

    We're hosting workforce development-focused office hours this Thursday, July 31, 2025, at 10:30am at Rosa Parks Senior Center computer lab. We encourage everyone to attend to learn more about our workforce development initiatives and about Read on...
  133. Capital Project Update

    Buchanan Street Mall | REMINDER: Night work scheduled for July 22 & July 23

    Notice of Night Work: Please be advised that there will be 48 hours of continuous construction activity from July 22, 7 a.m. to July 24, 7 a.m. Cured-in-place lining work will be completed on the sewer between Fulton and McAllister on Read on...
  134. Capital Project Update

    Buchanan Street Mall | Night work scheduled for July 22 & July 23

    Notice of Night Work: Please be advised that there will be 48 hours of continuous construction activity from July 22, 7 a.m. to July 24, 7 a.m. Cured-in-place lining work will be completed on the sewer between Fulton and McAllister on Read on...
  135. Capital Project Update

    Buchanan Street Mall | Construction update, July 2025

    Construction fences are now in place on the four southern-most blocks, from Grove St to Turk Street. Construction fencing will be installed on the northernmost block between Turk Street and Eddy Street starting next Monday, July 7. All doors and Read on...
  136. Capital Project Update

    Buchanan Street Mall | Construction update, June 2025

    Construction at Buchanan Street Mall is making great progress! Major work has been focused on carefully mapping and assessing existing utilities, and refining our plans for health and safety, site logistics, and traffic control. There has also been some Read on...
  137. Capital Project Update

    Buchanan Street Mall | Construction update, May 2025

    Our contractor has mobilized, and tree work has begun at Buchanan Street Mall. Tree work on the southern blocks is well underway, with a cluster of pine trees south of McAllister to be removed next week. Tree work will continue progressing to the Read on...
  138. Capital Project Update

    Buchanan Street Mall | Upcoming Job Fair + Opportunities for Artists

    We want to make sure folks are aware of these upcoming opportunities. First, if you are interested in making art for the Memory Walk at Buchanan Street Mall, please compete the interest form by Friday, May 23. This is a great chance for both new and Read on...
  139. Capital Project Update

    Buchanan Street Mall | Equity Action Opportunities

    As part of our Buchanan Street Mall Renovation Project and Park Improvement Equity Action Initiative, we want to make sure folks are aware of these upcoming opportunities. Come out to talk to members of the Memory Walk Art Advisory Committee about the Read on...
  140. Capital Project Update

    Buchanan Street Mall | Construction update - Tree Removals and Construction Fencing in early May

    PLEASE BE ADVISED: Tree work and tree removal will begin at Buchanan Street Mall the week of May 5. This work is expected to take approximately 2 weeks. Tree work will happen between 7am - 3pm. Expect to see barriers around work zones, marked detours for Read on...
  141. Capital Project Update

    Buchanan Street Mall | Calling Artists (who have strong ties to the Fillmore)

    You are invited to submit an application for your art to be considered for the Buchanan Street Mall Memory Walk! Applications are due on May 23, 2025, by 5:00 pm. The initiative includes art that honors the neighborhood’s rich history, culture and Read on...
  142. Capital Project Update

    Buchanan Street Mall | Construction begins at Buchanan Street Mall

    Thank you to everyone who joined us for the groundbreaking on March 27th! It was a beautiful celebration for and with the Fillmore community. We’re excited to share this milestone moment with you. After more than 10 years of visioning, planning, and Read on...
  143. Capital Project Update

    Buchanan Street Mall | Mayor Lurie Breaks Ground on Renovation of Buchanan Street Mall

    Long-Anticipated Project Marks the Culmination of a Partnership Between the City and Fillmore Community. Community Space Will Celebrate the History of the Neighborhood While Marking a New Chapter for Western Addition. Read on...
  144. Capital Project Update

    Buchanan Street Mall | Groundbreaking event on March 27!

    Join us for the groundbreaking of the Buchanan Street Mall Project on Thursday, March 27 beginning at 9:45 a.m. Buchanan Street Mall is a pedestrian walkway and city park that runs through a five-block section of the Western Addition, from Eddy Street to Read on...
  145. Capital Project Update

    Buchanan Street Mall | Panel Discussion on Black Public Art in SF + Paid Opportunities for Youth

    We’re pleased to share two upcoming opportunities to participate in the development of the Memory Walk at Buchanan Street Mall. Join legendary artists Dana King, Kristine Mays, and Malik Seneferu in a panel discussion moderated by Adrian Owens and Read on...
  146. Capital Project Update

    Buchanan Street Mall | Exciting Opportunity Alert - Orientation for Construction Training!

    Build Your Future with Success Centers and the Buchanan Street Mall Renovations Project! Are you ready to jumpstart your career in construction? Our workforce development partner, Success Centers, is hosting Pre-Apprenticeship Construction Training Read on...
  147. Capital Project Update

    Buchanan Street Mall | Project update, November 2024

    Thanks to all who joined us for a Community Gathering at the African American Arts & Culture Complex on 11/12! It was nice to see so many familiar faces, and we are filled with gratitude for you community members who have been such wonderful advocates for Read on...
  148. Capital Project Update

    Buchanan Street Mall | Buchanan Mall Gathering & Project Updates

    Join the San Francisco Recreation and Park Department (SFRPD), Trust for Public Land (TPL), Citizen Film, and the Memory Walk Art Advisory Committee (MWAC) for a festive gathering to review the latest updates on the Buchanan Street Mall Renovations Read on...
  149. Capital Project Update

    Buchanan Street Mall | Sunday Streets in Western Addition, this Sunday, Sept 22!

    Join us at Buchanan Street Mall this Sunday, September 22 for Sunday Streets’ Western Addition Community Block Party! Our project team will be sharing a table with Trust for Public Land to show plans and renderings of the renovated Buchanan Street Mall Read on...
  150. Capital Project Update

    Buchanan Street Mall | Buchanan Mall Memory Walk and Workforce Development

    It’s been an active August at Buchanan Street Mall! Rec and Park and project team staff participated in the carnival/ backpack give away/ jobs fair on August 3 and National Night Out on August 6. At both events, we shared information on two key elements: Read on...
  151. Capital Project Update

    Buchanan Street Mall | Carnival and Job Fair at Buchanan Mall this Saturday

    The project team has been busy the first half of this year, finalizing drawings and specifications, and we are just about ready to put the project out for public bid under a Best Value contract. Rec and Park is working to complete several workforce Read on...
  152. Capital Project Update

    Thank you! Contractor Meet & Greet on July 22 a big success!

    Thank you to all who attended the contractor meet & greet event on July 22! At the event we shared information on three important RPD projects that will be advertising this summer and fall: Buchanan Street Mall, Portsmouth Square, and India Basin Read on...
  153. Capital Project Update

    Contractor Meet & Greet event on July 22, 1pm-3pm

    Attention General contractors and Local Business Enterprise contractors: Please join us for a Contractor Meet & Greet event on July 22, 1pm-3pm, at 49 South Van Ness to learn about Rec & Park’s investment in equity and upcoming opportunities on Read on...
  154. Capital Project Update

    Upcoming Job Fairs related to Buchanan Street Mall Renovations

    As part of the Park Improvement Equity Action Initiative, SF Rec and Park is working with partner organization Success Centers to connect Fillmore community members with current and upcoming job opportunities. We have two scheduled Read on...
  155. Capital Project Update

    Buchanan Street Mall | $8.1 million federal ORLP grant awarded for Buchanan Street Mall renovation

    In early 2023, the state of California recommended to the National Park Service that the Buchanan Street Mall Renovations project receive additional federal funding. We just found out that an additional $8.1 million is being awarded to Read on...
  156. Capital Project Update

    Buchanan Street Mall | 2023: Community Building Before Park Building

    Tremendous thanks to everyone who has participated in community gatherings, events, focus groups, and surveys in 2023! The Fillmore Community showed up, shared honestly and Read on...
  157. Capital Project Update

    Buchanan Street Mall | End-of-year Community Gathering, Thursday, December 14

    In 2023 Rec and Park and core partners hosted twelve gatherings in the Fillmore Community, with a focus on community-building, equity, and healing. The Park Improvement Equity Action Initiative has led to the development of Read on...
  158. Capital Project Update

    Buchanan Street Mall | Project update October 2023

    Design continues to progress, and—though there is a slight delay due to utility conflicts—park renovations are still planned to begin early summer 2024 and complete in Read on...
  159. Capital Project Update

    Buchanan Street Mall | Memory Walk design reviews + workforce development meetings this week!

    This is a full week for the Buchanan Street Mall Renovations project! The Buchanan Street Mall project team is seeking San Francisco Arts Commission Civic Design Review committee approval on the Read on...
  160. Capital Project Update

    Last call for the Buchanan Mall Memory Walk survey!

    If you haven’t yet, please take 10 minutes to complete the survey before 5pm on this Thursday, 8/10/2023! Read on...
  161. Capital Project Update

    Buchanan Street Mall Renovations | Healing circles and Memory Walk design

    Thanks to everyone who is showing up and participating in summer healing circles. Community gatherings continue every other Read on...
  162. Capital Project Update

    Buchanan Street Mall Renovations | Join us for Summer Community Gatherings in June, July, and August

    Join neighbors and facilitators to continue conversations on healing and transformation in our community Read on...
  163. Capital Project Update

    Buchanan Street Mall Renovations | Summer Community Gatherings, June-August

    Join neighbors and facilitators to continue conversations on healing and transformation in our community Read on...
  164. Capital Project Update

    Buchanan Street Mall | May Community Gatherings focus on the Memory Walk

    Thanks to everyone who has participated in healing circles over the past several weeks as part of the Buchanan Street Mall Equity Action Initiative Read on...
  165. Capital Project Update

    UPDATED! - Buchanan Mall Equity in Action April Gatherings

    Community gathering scheduled for April 5 is now cancelled. Please join us for the next meeting, scheduled for April 19. Be a part of the Read on...
  166. Capital Project Update

    Buchanan Mall Equity in Action April Gatherings!

    Join our April Equity in Action gatherings Read on...
  167. Capital Project Update

    Community Gathering on March 22 | Buchanan Street Mall – Park Improvement Equity Action Initiative

    Join Us for the Next Community Healing Circle. Help shape the future of Buchanan Street Mall Read on...
  168. Capital Project Update

    Buchanan Street Mall – Park Improvement Equity Action Initiative: First Community Gathering on 3/15

    Help shape the future of the Fillmore! Your participation is key for redesigning Buchanan Street Mall Read on...
  169. Capital Project Update

    LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING.

    LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING. . . . Read on...
  170. Capital Project Update

    Memory Walk Design at Buchanan Street Mall - Community Meeting

    Core to the community-driven redesign of Buchanan Street Mall, the Memory Walk is envisioned to physically connect all five blocks of the park . . . Read on...
  171. Capital Project Update

    Buchanan Mall stage preview and last call for the Phase 1 design refinement survey!

    Design is progressing for the stage on the McAllister to Fulton block, thanks to the thoughtful input input provided by local performing art stakeholders Read on...
  172. Capital Project Update

    Richmond Playground | Construction update, June 2024

    Construction is moving fast! Since our last update in May, we have installed the surfacing around the play structures, nearly completed the planting in the landscapes, and we are currently installing the new Read on...
  173. Capital Project Update

    Richmond Playground | Construction update, May 2024

    The feel of the playground has really taken shape. Concrete seat walls have been poured and the playground equipment is up! If you walk by the park you’ll notice the centerpiece of the new playground, a giant wooden grizzly bear, as well as the Read on...
  174. Capital Project Update

    Richmond Playground | Construction update September 2023

    Construction work for Richmond Playground will begin soon and includes a complete renovation of the children’s play area with new Read on...
  175. Capital Project Update

    Richmond Playground | Project update June 2023

    We’re looking forward to starting construction at Richmond Playground later this year. The project will feature a complete renovation of Read on...
  176. Capital Project Update

    Richmond Playground Construction Update 8/17.

    We’re almost at 100% completion of the construction drawings . . . Read on...
  177. Capital Project Update

    Richmond Playground Project Update April 2022

    Richmond Playground is moving forward! Read on...
  178. Capital Project Update

    Stern Grove Playground Renovation | Construction update, October 2025

    We are happy to share that the new lawn below the playground is now open to the public! After completing its establishment period – resting, watering, and two mowing cycles, the grass is healthy and ready for visitors to enjoy. You may still see our Read on...
  179. Capital Project Update

    Stern Grove Playground Renovation | Construction update, September 2025

    We are super excited that the playground is now open to the public! Thank you to everyone who supported this special project. Over the next few months, you will continue to see our contractor on-site periodically to make adjustments and Read on...
  180. Capital Project Update

    Stern Grove Playground Renovation | Stern Grove Playground Transformed into Tree House Village

    Beloved Sunset District play space reopens as whimsical, nature-inspired retreat. Read on...
  181. Capital Project Update

    Stern Grove Playground Renovation | REMINDER! Playground Ribbon Cutting on September 10, 3:30 pm

    Come out for the reopening of Stern Grove Playground on Wednesday, September 10 from 3:30 to 4:30 p.m. The event will feature brief remarks, a ribbon cutting ceremony, and the debut of the new, nature-based play area of the Read on...
  182. Capital Project Update

    Stern Grove Playground Renovation | Playground Ribbon Cutting on September 10

    Come out for the reopening of Stern Grove Playground on Wednesday, September 10 from 3:30 to 4:30 p.m. The event will feature brief remarks, a ribbon cutting ceremony, and the debut of the new, nature-based play area of the Read on...
  183. Capital Project Update

    Stern Grove Playground Renovation | Construction update, August 2025

    There has been an unforeseen delay in the installation of the safety surfacing at the playground. This will push the playground’s reopening to sometime in September. We will follow up with more information once an opening date is Read on...
  184. Project Update icon

    Stern Grove Playground Renovation | Construction update, July 2025

    We’re excited to report that the new playground’s final piece of custom play equipment – the large, curved, metal slide – arrived on July 16 and installation of the slide is now underway. Our contractor is also working to complete the Read on...
  185. Capital Project Update

    Stern Grove Playground Renovation | Construction update, June 2025

    All play equipment is now installed, except for one piece of custom play equipment that will be delivered to the site soon. In the meantime, the construction team is preparing the new pedestrian pathways for paving. Construction is progressing nicely, and Read on...
  186. Capital Project Update

    Stern Grove Playground Renovation | Construction update, May 2025

    The playground continues to take shape with the installation of the playground towers and other climbing elements. We are looking forward to wrapping up construction this summer Read on...
  187. Capital Project Update

    Stern Grove Playground Renovation | Construction update, April 2025

    The second shipment of custom play equipment was received last week, and the final delivery is expected within the next two weeks. On-site installation of catch basins is currently underway, and the construction team continues to make steady progress on Read on...
  188. Capital Project Update

    Stern Grove Playground Renovation | Construction update, March 2025

    The first shipment of the custom play equipment has been received, and the contractor is preparing the site to install the same Read on...
  189. Capital Project Update

    Stern Grove Playground Renovation | Construction update, February 2025

    The contractor is currently installing gopher wires between the boulders and preparing to install the permeable rock base for the play area. There has been a delay in the delivery of the custom play equipment due to the snowstorms in Toronto but the Read on...
  190. Capital Project Update

    Stern Grove Playground Renovation | Construction update, January 2025

    The contractor is currently focused on replacing the fencing along Sloat Avenue and completing the final stages of boulder placement within the playground Read on...
  191. Capital Project Update

    Stern Grove Playground Renovation | Project update, February 2024

    The Recreation and Park Department Commission has approved awarding the construction contract for the Stern Grove Playground Renovation to Minerva Construction. Staff have also Read on...
  192. Capital Project Update

    Stern Grove Playground Renovation | Project update, January 2024

    We are excited to announce that we received three bids from prospective contractors for the Stern Grove Playground Renovation! We are currently evaluating the bids and we will Read on...
  193. Capital Project Update

    Stern Grove Playground Renovation | Project update, December 2023

    We have officially published the bid documents for the Stern Grove Playground Renovation. We held an on-site meeting with Read on...
  194. Capital Project Update

    Stern Grove Playground Renovation | March 2023 update

    As a quick update on the Stern Grove Playground Renovation, we are making some refinements to the final concept design, while continuing regulatory and construction bid preparation Read on...
  195. Capital Project Update

    Stern Grove Playground Renovation | February 2023 update

    We are wrapping up our construction documentation for the playground renovation at Stern Grove... Read on...
  1. Alexis Ward

    Project Manager