Let’sPlaySF! Initiative (2012 Bond)

BackgroundStacked box climbing structure with slide, swings, play structures, stacked donor blocks

Let’sPlaySF! has its origins in the $195 million San Francisco Clean and Safe Neighborhood Parks General Obligation Bond approved by 71.6% of voters in November 2012. The Bond allocated $15.5 million to renovate dilapidated playgrounds through the City.

In 2014, the Recreation and Park Commission appointed a Citizen Task Force to determine which playgrounds were most in need of renovation. The Task Force prioritized six Tier 1 and seven Tier 2 playgrounds for renovation based on four criteria: (1) the presence of Chromated Copper Arsenate (CCA) Pressure Treated Wood, (2) low Household Median Income, (3) high Youth Density and (4) low Parks Alliance Playground Report Card Grades.

In December 2014, the Recreation and Park Commission unanimously adopted the list recommended by the Task Force, of which the Department committed to renovate all six Tier 1 playgrounds and to renovate some or all Tier 2 playgrounds provided if additional funding were procured. In the wake of that determination, the Department and the Parks Alliance decided to partner on Let’sPlaySF!, a capital campaign dedicated to raising sufficient funds to ensure that all 13 playgrounds can be reimagined for San Francisco’s children. The Parks Alliance Board voted in December 2015 to undertake the campaign and in December of 2016, the Commission approved a MOU between the Parks Alliance and the Department to partner on the project and recommended that the Board of Supervisors accept up to $15 million from the Parks Alliance for the project.

Program Status

The initiative has fully completed 9 of the 13 playgrounds and are open to the public. Of the four remaining playground, Herz Playground is currently in construction. Stern Grove and Richmond are preparing for construction later in 2023. Buchanan Mall Playground has been incorporated into a larger renovation of the park and is currently in design phase. For status updates on the individual sites, click on a project.

Status of Tier 1 SitesAll Tier 1 Sties are completed and open to the public.Red play structure, blue play surface, silver metal picnic tables, pink painted flower

Status of Tier 2 Sites:

For more background and to donate through our partner, visit San Francisco Parks Alliance.


Project Updates

If you would like to sign up for updates click here and scroll down to the NewsFlash and select the alerts you would like to receive.

  1. Project Update Blog
  2. Additional Background
  3. Documents and Materials
  4. Meeting Materials
  5. Task Force Members
  1. Capital Project Update

    Richmond Playground | Project update July 2023

    We’re excited to share that a construction contract award for the Richmond Playground was approved by Rec and Park Commission on July 20! Read on...
  2. Herz Groundbreaking

    SF City leaders, families celebrate groundbreaking of improvement project at Herz Playground

    The Recreation & Park Department broke ground on renovations at Herz Playground in Visitacion Valley on Monday as part of the Let’sPlaySF! initiative that is delivering creative play spaces to children across San Francisco. Read on...
  3. Juri Commons Ribbon Cut

    Juri Commons Park Reopens Following Renovation

    Juri Commons reopened following a $1.9 million renovation honoring the Mission District park’s railroad history, featuring a redesign with new plantings, an improved play space for children, grass for dogs, & an adult exercise area with fitness equipment. Read on...
  4. Capital Project Update

    Buchanan Street Mall | Memory Walk design reviews + workforce development meetings this week!

    This is a full week for the Buchanan Street Mall Renovations project! The Buchanan Street Mall project team is seeking San Francisco Arts Commission Civic Design Review committee approval on the Read on...
  5. Capital Project Update

    Last call for the Buchanan Mall Memory Walk survey!

    If you haven’t yet, please take 10 minutes to complete the survey before 5pm on this Thursday, 8/10/2023! Read on...
  6. Capital Project Update

    Buchanan Street Mall Renovations | Healing circles and Memory Walk design

    Thanks to everyone who is showing up and participating in summer healing circles. Community gatherings continue every other Read on...
  7. Capital Project Update

    Buchanan Street Mall Renovations | Join us for Summer Community Gatherings in June, July, and August

    Join neighbors and facilitators to continue conversations on healing and transformation in our community Read on...
  8. Capital Project Update

    Buchanan Street Mall Renovations | Summer Community Gatherings, June-August

    Join neighbors and facilitators to continue conversations on healing and transformation in our community Read on...
  9. Capital Project Update

    Buchanan Street Mall | May Community Gatherings focus on the Memory Walk

    Thanks to everyone who has participated in healing circles over the past several weeks as part of the Buchanan Street Mall Equity Action Initiative Read on...
  10. Capital Project Update

    UPDATED! - Buchanan Mall Equity in Action April Gatherings

    Community gathering scheduled for April 5 is now cancelled. Please join us for the next meeting, scheduled for April 19. Be a part of the Read on...
  11. Capital Project Update

    Buchanan Mall Equity in Action April Gatherings!

    Join our April Equity in Action gatherings Read on...
  12. Capital Project Update

    Community Gathering on March 22 | Buchanan Street Mall – Park Improvement Equity Action Initiative

    Join Us for the Next Community Healing Circle. Help shape the future of Buchanan Street Mall Read on...
  13. Capital Project Update

    Buchanan Street Mall – Park Improvement Equity Action Initiative: First Community Gathering on 3/15

    Help shape the future of the Fillmore! Your participation is key for redesigning Buchanan Street Mall Read on...
  14. Capital Project Update

    LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING.

    LOCATION CHANGE FOR BUCHANAN STREET MALL MEETING THIS EVENING. . . . Read on...
  15. Capital Project Update

    Memory Walk Design at Buchanan Street Mall - Community Meeting

    Core to the community-driven redesign of Buchanan Street Mall, the Memory Walk is envisioned to physically connect all five blocks of the park . . . Read on...
  16. Capital Project Update

    Buchanan Mall stage preview and last call for the Phase 1 design refinement survey!

    Design is progressing for the stage on the McAllister to Fulton block, thanks to the thoughtful input input provided by local performing art stakeholders Read on...
  17. Capital Project Update

    Buchanan Street Mall Phase 1 – Community Meeting on 2/24/2022

    It’s time to CELEBRATE! For seven years, the Western Addition community has dreamed about what Buchanan Mall could become with the right vision and resources. Those dreams are coming true! Read on...
  18. Capital Project Update

    Buchanan Mall, Turk – Golden Gate at SFAC Civic Design Review Monday 9/20

    After almost seven years of community-driven engagement and visioning, SF Rec and Parks is thrilled to be moving forward with a clear schedule for . . . Read on...
  19. Capital Project Update

    Design continues and additional funding received for Buchanan Street Mall!

    Thanks to the 174 people who participated in the survey to refine the design of Buchanan Street Mall, Turk – Golden Gate block. . . Read on...
  20. Capital Project Update

    Complete the survey to refine the design of an all-ages play area in Buchanan Street Mall

    Thanks to everyone who participated in the Virtual Community Meeting . . . Read on...
  21. Capital Project Update

    Virtual Meeting and Survey to Refine the Design for Buchanan Street Mall

    The Buchanan Street Mall project team is seeking community feedback to inform the look and feel and the specific equipment included in the new all-ages recreation area in the Turk - Golden Gate block Read on...
  22. Capital Project Update

    BUCHANAN STREET MALL FINAL CONCEPTUAL DESIGN COMPLETE!

    The Fillmore community has been reimagining Buchanan Street Mall since late 2014, to design a safer more inclusive neighborhood space Read on...
  23. Capital Project Update

    BUCHANAN STREET MALL – COMMUNITY WORKSHOP ON NOV. 1st!

    Please join us on Nov 1st as we begin to create the conceptual design for the entire five block length of Buchanan Mall. Read on...
  24. Capital Project Update

    DESIGNER SELECTED FOR BUCHANAN MALL

    We are excited to have The Office of Cheryl Barton (O|CB) join us as designers for the conceptual design proposals for the entire 5 block length of Buchanan Mall Read on...
  25. Capital Project Update

    BUCHANAN STREET MALL PROJECT UPDATE

    In March 2017, Rec & Park’s partners, the Trust for Public Land (TPL) together with Citizen Film, completed an intensive community engagement process Read on...
  26. Capital Project Update

    Herz Playground Now Open! | Project update September 2023

    Thank you to all of the community members who attended the ribbon cutting ceremony, including our speakers: Mayor London Breed, District 10 Supervisor Shamann Walton Read on...
  27. Capital Project Update

    Herz Playground Now Open! | Community, City Officials Celebrate $3.38 Million Makeover

    Creative new play equipment for kids of all ages and a park makeover inspired by nature greeted families at the renovated Herz Playground in McLaren Park Read on...
  28. Capital Project Update

    Herz Playground | Reopening Celebration, August 24!

    Join us to celebrate the renovation and reopening of Herz Playground on August 24 Read on...
  29. Capital Project Update

    Herz Rec Center | Project update August 2023

    On June 15, our Rec and Park Commission unanimously approved a contract award to SJ Amoroso Construction Co., LLC. to construct the new Herz Rec Center Read on...
  30. Capital Project Update

    Complete the McLaren Park 2020 Bond Planning priorities survey

    We’ve created a new map-based survey to collect your thoughts on possible programming, infrastructure, and connectivity improvements in John McLaren Park. Please take 15-20 minutes Read on...
  31. Capital Project Update

    Herz Playground | Project update June 2023

    We are rounding the corner on progress with Herz Playgound and the space is really taking shape! The play equipment is Read on...
  32. Capital Project Update

    Herz Playground | Project update May 2023

    If you have driven down Visitacion Avenue this week, you may have noticed the large towers erected at the Herz Playground construction site. Read on...
  33. Capital Project Update

    SF Rec and Park Commission Meeting at Joe Lee Rec Center | March 16 at 10 a.m.

    Come meet your Rec and Park Commissioners at our offsite Commission meeting at Joe Lee Rec Center Read on...
  34. Capital Project Update

    Herz Playground – Construction Update | March 2023

    Even with these heavy winter rains, we continue to make progress at Herz Playground. The new sewer lines that serve the Read on...
  35. Capital Project Update

    Herz Playground – Construction Demolition Almost Complete!

    Treaty Construction is busy at work with their backhoe! Demolition is nearly complete at Herz Playground. . . . Read on...
  36. Capital Project Update

    Herz Playground Groundbreaking Celebration October 24th!

    Save the date! Please join, Monday, October 24 from 4:30-5:30 . . . Read on...
  37. Capital Project Update

    Contract Awarded for Herz Playground Construction

    On August 18, 2022, Commission approved that Treaty Construction be awarded the contract to renovate Herz Playground. . . . Read on...
  38. Capital Project Update

    Bids received for Herz Playground Construction!

    Hi everybody- We have great news to share- we received 7 bids on the Herz Playground Renovation Project! Read on...
  39. Capital Project Update

    Contractor bids are due on Wednesday, May 25! for Herz Playground!

    Hi all- We nearing the end of our advertisement period for Herz Playground! . . . Read on...
  40. Capital Project Update

    Herz Playground Project is going out to bid!

    Hi everyone- We will be advertising the Herz Playground Renovation Project this week. . . Read on...
  41. Capital Project Update

    Herz Playground Project Update March 2022

    We have finalized structural engineering for the playground equipment and we aim to bring the construction documents to the Department of Building Inspection Read on...
  42. Capital Project Update

    Herz Playground Project Update 2/23/2022

    We have our final set of drawings and specifications ready for bidding Read on...
  43. Capital Project Update

    Herz Playground Project Update 1/22!

    We are putting the final touches on our permit set of drawings and we are planning to advertise the project to contractors in February. . . Read on...
  44. Capital Project Update

    Herz Playground Project Update 12/17!

    Hi everybody- We have wrapped up our permit set of drawings and the next step is to have the drawings reviewed by the Building Department for approval. . . Read on...
  45. Capital Project Update

    Herz Playground Project Update 11/18!

    Hi everybody- We are putting the finishing touches on the permit set of drawings, which we will submit to the Building Department for approval. . . Read on...
  46. Capital Project Update

    Herz Playground Project Update 9/20!

    Hi everybody- We are getting close to wrapping up our construction document for the new playground and the bathroom renovation at Herz Clubhouse. . . Read on...
  47. Capital Project Update

    Herz Playground Project Update 8/20!

    The landscape architect is developing the construction documents for the project. . . Read on...
  48. Capital Project Update

    Herz Playground Project Update 7/19!

    Hi everybody, We are continuing work on the construction documents for the project. . . Read on...
  49. Capital Project Update

    Herz Playground Project Update 6/21!

    Hi all, We are wrapping up our cost estimating and we will be moving into construction documents for the playground renovation. . . Read on...
  50. Capital Project Update

    Herz Playground Project Update 5/21!

    Hi all, Our design has completed the detailed design phase and we are currently cost estimating the project and doing regulatory reviews. . . Read on...
  51. Capital Project Update

    Herz Playground Project Update4/20!

    Hi everyone, Thank you so much for your support at the Recreation and Park Commission and for participating in all our community outreach for this project. Read on...
  52. Capital Project Update

    Herz Playground Project is Going Before the Commission for Approval!!

    Hi all, This Thursday, March 18th at 10am, we will be presenting the playground concept plan to the Rec Park Commission . . . Read on...
  53. Capital Project Update

    News about the Herz Projects!

    We are excited to share that Rec Park staff will be presenting the . . . Read on...
  54. Capital Project Update

    Herz Playground Project Update 1/22!

    Hi everyone, We are very close to finalizing our concept plan . . . Read on...
  55. Capital Project Update

    Herz Playground Project Update Dec '20

    We are working with the Historic Preservation team at the Planning Department to review the playground design Read on...
  56. Capital Project Update

    Herz Playground Project Update 10/29!

    Thank you so much to those who joined us for our final community meeting. Read on...
  57. Capital Project Update

    Herz Playground Project Final Community Meeting!

    Join us to see the updated design for Herz. . . Read on...
  58. Capital Project Update

    Herz Playground Project Update 9/18!

    Hi all- Our project designers have been updating the playground design to reflect the survey results on the play equipment Read on...
  59. Capital Project Update

    Herz Playground Project Update 8/21!

    Hi all- Thank you so much to everyone who participated in our online survey! Read on...
  60. Capital Project Update

    Herz Rec Center Project Update 8/21!

    Hi everyone! Thanks to those who participated in our focus group meetings. . . Read on...
  61. Capital Project Update

    Herz Playground Project Survey Still Open!

    We have had a great response to our survey and we are going to keep it open a little longer . . . Read on...
  62. Capital Project Update

    Take a Brief Survey to Help Us with the Herz Playground Renovation!

    During these times of civil unrest, we hope that parks can provide essential spaces for gathering, recreating and connecting to nature. Read on...
  63. Capital Project Update

    Herz Playground Project Update 5/22

    We are putting finishing touches on our playground survey and getting it translated into multiple languages. Read on...
  64. Capital Project Update
  65. Capital Project Update

    HERZ PLAYGROUND

    The project team is refining the draft concept plan for the playground and getting a preliminary concept estimate done Read on...
  66. Capital Project Update

    HERZ- CHILDREN’S PLAYGROUND RENOVATION

    Rec Park is working with our project landscape architect to consolidate the community feedback into one design for the playground renovation Read on...
  67. Capital Project Update

    HERZ PLAYGROUND- WORKING ON THE CONCEPT DESIGN

    Thank you so much to those who have provided feedback on our different design options for the Herz Playground Renovation Read on...
  68. Capital Project Update

    Richmond Playground | Construction update September 2023

    Construction work for Richmond Playground will begin soon and includes a complete renovation of the children’s play area with new Read on...
  69. Capital Project Update

    Richmond Playground | Project update June 2023

    We’re looking forward to starting construction at Richmond Playground later this year. The project will feature a complete renovation of Read on...
  70. Capital Project Update

    Richmond Playground Construction Update 8/17.

    We’re almost at 100% completion of the construction drawings . . . Read on...
  71. Capital Project Update

    Richmond Playground Project Update April 2022

    Richmond Playground is moving forward! Read on...
  72. Capital Project Update

    Richmond Playground Project Update 8/20!

    Design work for the Richmond Playground renovation has resumed! Read on...
  73. Capital Project Update

    Richmond Playground Project Update 4/26!!

    Design work on the Richmond Playground renovation is temporarily halted but we are hopeful that the project can resume shortly . . . Read on...
  74. Capital Project Update

    Richmond playground Project Update 2/9!

    The concept design for Richmond Playground is complete! Read on...
  75. Capital Project Update

    Richmond Playground Concept Design Moving Forward 9/21!

    Thank you so much to all who attended the third and final community workshop and to all who have contributed feedback along the way. . . Read on...
  76. Capital Project Update

    Join us to discuss the final concept design for Richmond Playground!

    Please join us for a final community meeting to celebrate and discuss the final concept design for the upcoming renovation . . . Read on...
  77. Capital Project Update

    Richmond Playground Open House and Design Workshop

    Give your input on concept designs for the upcoming renovation of the play area at Richmond Playground Read on...
  78. Capital Project Update

    Richmond Playground Open House- Thank You!

    We had a wonderful Public Open House on November 2nd! About 50 people stopped by on a sunny Saturday morning to participate in the project Read on...
  79. Capital Project Update

    Richmond Playground Open House

    Recreation and Parks hosted an Open House in November 2019 regarding the upcoming renovation of the play area at Richmond Playground Read on...
  80. Capital Project Update

    Stern Grove Playground Renovation | March 2023 update

    As a quick update on the Stern Grove Playground Renovation, we are making some refinements to the final concept design, while continuing regulatory and construction bid preparation Read on...
  81. Capital Project Update

    Stern Grove Playground Renovation | February 2023 update

    We are wrapping up our construction documentation for the playground renovation at Stern Grove... Read on...
  82. Capital Project Update

    Stern Grove Playground Virtual Community Meeting #3 12/14 at 5pm!

    Join us for the third community meeting for the Stern Grove Playground Renovation Project. . . Read on...
  83. Capital Project Update

    Stern Grove Playground Virtual Community Meeting #2 (7/21 at 5pm)

    Join us for the second community meeting for the Stern Grove Playground Renovation Project. . . Read on...
  84. Capital Project Update

    POSTPONED - Stern Grove Virtual Community Meeting 3/25 at 5 pm!

    Join us for the second community meeting for . . . Read on...
  85. Capital Project Update

    Stern Grove Virtual Community Meeting 2/18 at 5 pm!

    We hope you can join us for the first of many virtual meetings to discuss the renovation of the playground at Stern Grove. . . Read on...
  86. Capital Project Update

    Stern Grove Playground Survey is Now Closed Thank you!

    The Stern Grove Playground Community Survey is now open! Read on...
  1. Kelli Rudnick

    Project Manager Supervisor