Crocker Amazon Soccer Fields

Scope of WorkDiagram indicating the two phases of the Crocker Amazon construction

Synthetic turf was installed at Crocker Amazon Soccer Fields over ten years ago. This field is at the end of its useful life and is in need of replacement. 

Construction will occur in two phases to allow for reduced soccer field access at any given time. 

The project includes the following improvements:

  • Replacing field turf with new material that utilizes natural infill 
  • Repairs and improvements to the perimeter fence and gates 
  • Installation of new site furnishings including field goals and drinking fountains 
  • Sidewalk accessibility improvements along Geneva Ave and accessible parking improvements at the Geneva Ave parking lot

The old turf will be shredded and recycled into new materials. 

Additional fields remain available such as West Sunset Playground (soccer), Beach Chalet Fields (soccer), South Sunset Fields (soccer), Parkside Square (non-soccer) and McCoppin Square (non-soccer). Please be sure to call our Permits and Reservation office, for availability, at 415-831-5500 or visit https://sfrecpark.org/423/Athletic-Field-Reservations

Funding

Recreation and Parks Department General Fund and the City Fields Foundation totaling $6.75 million.

The construction contract award for this project was approved by Recreation and Parks Commission on December 15, 2022 (PDF); Recreation and Parks Commission approved a contract amendment on July 20, 2023 (PDF). This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project's funding sources.

Project Schedule

PhaseTimeline
PlanningFall 2021
DesignSpring 2022
Construction contract approvedDecember 15, 2022
Construction beginsSpring 2023
Open to the publicLate 2023


Project Updates

If you would like to sign-up for Project Update blog posts like the ones below, click here, scroll down to the News Flash section, and then select "RPD Park Improvements | All Project Updates" to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. You’ll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.

  1. Project Update Blog
  2. Documents and Materials
  1. Capital Project Update

    Crocker Amazon Soccer Fields | Construction updates July 24, 2023

    Crocker Soccer Fields 1 and 2 are now completely renovated and opened to the public. We opted to Read on...
  2. Capital Project Update

    Crocker Amazon Soccer Fields | Construction updates July 2023

    We wanted to share an update on the turf replacement happening now at Crocker Soccer. Fields 1 and 2 will be re-opened by late July and then Read on...
  3. Capital Project Update

    Complete the McLaren Park 2020 Bond Planning priorities survey

    We’ve created a new map-based survey to collect your thoughts on possible programming, infrastructure, and connectivity improvements in John McLaren Park. Please take 15-20 minutes Read on...
  4. Capital Project Update

    Crocker Amazon Soccer Fields Project | Project updates May 2023

    We’re excited to report that construction work to replace the field turf at Crocker Amazon has begun! Construction will occur in three phases so that for the duration of construction Read on...
  5. Capital Project Update

    Crocker Amazon Fields Project Update 1/23!

    The fencing work for this project was completed in August 2022 and the . . . Read on...
  1. Omar Davis

    Project Manager