The Tennis Center construction team continues to move forward with construction as they adhere to all safety protocols for workers during COVID-19 shelter in place. This is great news for the construction schedule and opening the courts this fall.
The board-formed concrete walls are complete and the team is running utilities in the walls of the building. Next up will be installation of glass windows and walls. As for site work, underground utility work is underway, trenching for conduit for court lighting is nearly complete and the team is moving closer to spreading aggregate for the base for the tennis courts.
Stay tuned for updates as the building and site continue to take shape.

You can see the board-formed concrete wall on the left side of this photo.

This drone photo is a great image of the Tennis Center under construction in its Golden Gate Park context.